Pin to quick picksHummingbird Regulatory News (HUM)

Share Price Information for Hummingbird (HUM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 8.25
Bid: 8.00
Ask: 8.50
Change: -0.08 (-0.99%)
Spread: 0.50 (6.25%)
Open: 7.90
High: 8.50
Low: 7.90
Prev. Close: 8.10
HUM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Positive Preliminary Assessment of HEP in Liberia

16 Sep 2015 07:00

RNS Number : 1232Z
Hummingbird Resources PLC
16 September 2015
 

Hummingbird Resources plc / Ticker: HUM / Index: AIM / Sector: Mining

16 September 2015

Hummingbird Resources plc ("Hummingbird Resources" or "the Company")

Receives Positive Preliminary Assessment of

Hydro-Electric Power Plant in Liberia

 

Hummingbird Resources, the multi-project gold company, is pleased to announce a positive preliminary report from Knight Piesold Consulting ("KP") for the proposed hydro-electric power ("HEP") plant in south-east Liberia, ±10km from Hummingbird's 4.2Moz Dugbe Gold Project.

 

This significant development follows the signature of a Collaboration Agreement for the funding and development of the HEP signed in April 2015 with IFC InfraVentures, the IFC Global Infrastructure Project Development Fund, and Aldwych International, a leading energy company active in the growing economies of Africa.

 

Highlights

· Report demonstrates a range of hydropower options that would be highly beneficial in the development of a sustainable and low-cost source of power for the Dugbe Gold Project, as well as the south-east Liberian region

· Assessed four run-of-river hydropower options ranging from 15MW to 30MW with varying intakes

· A hydropower development on the Dugbe River represents a legacy asset that will benefit the region by providing low cost renewable energy long after mine closure to the communities in the region

· Pre-Feasibility Assessment will be finalised on completion of additional hydrological studies and topographic mapping (satellite survey) - targeting final report in Q2 2016

· Pre-Feasibility Study funded (circa US$265,000) by IFC InfraVentures as part of the Collaboration Agreement

 

Dan Betts, CEO of Hummingbird Resources, said: "We are highly encouraged by the preliminary study for the development of a HEP plant in south-eastern Liberia which, if developed, will enable a sustainable and low-cost source of power for our Dugbe Gold Project and secure a source of domestic power supply for the local region. With the Pre-Feasibility study being fully funded by IFC InfraVentures, Hummingbird is ideally positioned to capitalise on the HEP development whilst mitigating risk and capital exposure. We also believe the HEP scheme will create a catalyst for growth in the region and provide a significant potential operating cost saving for the development of the Dugbe Gold Project."

 

Further Information

 

The Company is considering the development of a run-of-river (ROR) hydroelectric facility to support the development and operation of its Dugbe mining operation in the south-west region of Liberia. Hummingbird has instructed KP to conduct a Pre-Feasibility assessment of the potential hydropower development on the Dugbe River and its major tributaries. The Pre-Feasibility report has been issued in draft form, as a preliminary assessment of the project's viability and it will be updated in final form once additional hydrological studies and topographic mapping (satellite survey) have been completed.

 

The previous desktop HEP scoping study considered an operational mine power demand of 30 MW. However, the updated average power demand for the Dugbe Gold Project is forecast at 16 MW but with additional capacity for the local region to address the expected peak demands of 20 to 30 MW. KP has therefore assessed a range of hydropower project alternatives, including:

 

· Alternative 1 - 30 MW project with 3 intakes, on Dugbe River, Botou River and Geebo Creek

· Alternative 2 - 25 MW project with 2 intakes on Dugbe River and Botou River

· Alternative 3 - 20 MW project with 1 intake on Dugbe River

· Alternative 4 - 15 MW project with 1 intake on Dugbe River

 

The draft Pre-Feasibility hydropower study has been based on a mixture of regional rainfall data and topographical information ranging from 1m LiDAR data near the proposed powerhouse site, up to the 10m national topographic data. The study has so far included the following tasks: a site visit carried out in May 2015; stream gauging; a review of rainfall data; developing project concepts for the four alternative options; preparation of energy generation; capital cost estimation; and a review of licencing requirements and permitting.

 

The following table outlines the preliminary economics of the four alternative options.

 

DESCRIPTION

UNIT

ALTERNATIVE 1

ALTERNATIVE 2

ALTERNATIVE 3

ALTERNATIVE 4

Gross Head

m

41

41

41

41

Design Flow

m3/s

92

72

59

45

Installed Capacity

MW

30

25

20

15

Intakes & Canals

No.

3

Dugbe, Botou & Geebo

2

Dugbe & Botou

1

Dugbe

1

Dugbe

Capacity Factor

%

0.40

0.38

0.37

0.45

Mean Annual Energy

GWhr

106.3

82.5

64.7

59.5

Capital Cost Estimate (with Concrete Canal)

US$M

169.5

141.2

108.8

90.0

 

In addition to economic considerations, a hydropower development on the Dugbe River represents a legacy asset that will benefit the region by providing low cost renewable energy long after mine closure.

 

As noted, the draft Pre-Feasibility assessment has reduced conceptual HEP project design uncertainties, although there are still improvements needed before selecting the final layout and confirming the HEP feasibility. For the final Pre-Feasibility report a more detailed assessment of the hydrologic and topographic information will be needed over the coming months. Stream gauging will provide site specific hydrology data to prove the available water resource. Additionally, satellite topographic data offers the opportunity to improve capital cost certainty by refining canal and penstock alignments, and structure siting. This satellite survey information should be available in Q4 2015 and the completed Pre-Feasibility Report is expected to be finalised in Q2 2016.

 

About Knight Piésold

Knight Piésold has been in the hydropower business for over 80 years with extensive experience in large and small hydroelectric projects throughout the world. Their experience includes water storage projects, run-of-river projects and pumped storage projects. Knight Piésold provides a "one-stop-shop" for hydropower development, from resource identification and evaluation, financial services, environmental impact assessments and permitting, through to project management, site investigations, detailed engineering design, site supervision, O&M staffing and training, commissioning, and asset management. The improvement of existing units and facilities through power facility additions at existing dams, replacement of aging or low efficient equipment, and equipment upgrades or improvements, are also key elements of Knight Piesold's hydropower practice. Past projects include the 235MW East Toba and Montrose Projects and 150MW Kwalsa and Upper Stave Hydroelectric Projects in Canada, the 1,333MW Ingula Pumped Storage Scheme in South Africa, the 247MW Kalungwishi Hydroelectric Project in Zambia, and the 150MW Casecnan Multi-Purpose Hydroelectric Project.

 

Dugbe - Liberia

The Dugbe Gold Project is located within the Birimian Basin, the world's second largest gold producing region, characterised by exceptionally large, homogenous grade deposits which offer vast exploration and development scope. With a current Resource of 4.2 million ounces of gold at an average gold grade of 1.4 g/t, Dugbe offers a large-scale development opportunity for Hummingbird. The Company completed a Preliminary Economic Assessment ("PEA") in April 2013 which demonstrated the viable economics of developing a 20 year gold mining project with initial gold production of 125,000 ounces, an NPV of US$186 million, IRR of 29% using a US$1,300 gold price. Hummingbird is continuing to advance Dugbe and is progressing Definitive Feasibility Study optimisation work evaluating the large 4.2Moz gold resource, mining, processing and power capabilities with a view to future production viability.

 

**ENDS**

 

For further information please visit www.hummingbirdresources.co.uk or contact: 

 

Daniel Betts

Thomas Hill

Robert Monro

Hummingbird Resources plc

Tel: +44 (0) 203 416 3560

Stewart Dickson Jeremy Stephenson

Phil Davies

 

Cantor Fitzgerald Europe

Nominated Adviser and Joint Broker

Tel: +44 (0) 207 894 7000

 

Jon Belliss

Beaufort Securities Limited

Joint Broker

Tel: +44 (0) 20 7382 8300

Lottie Brocklehurst

Felicity Winkles

Hugo de Salis

St Brides Partners Ltd

Financial PR/IR

Tel: +44 (0) 20 7236 1177

 

Notes to Editors

Hummingbird Resources (AIM: HUM) is building a leading gold production, development and exploration company. The Company has two core gold projects, the near-term production Yanfolila Gold Project in Mali and the Dugbe development project in Liberia. Its current focus is on bringing Yanfolila, which has a 1.8Moz gold inventory, to production in 2016. The high grade gold project has the potential to turn a profit in a varying gold price environment and will allow for quick returns with low operating costs. A US$75 million debt facility has been agreed with Taurus Mining and mine construction is now underway with the aim of commencing production in 2016.

 

The 4.2Moz Dugbe Gold Project in Liberia provides Hummingbird with excellent development upside. An optimisation of the DFS is on-going whilst Yanfolila is brought to production in the near-term. Additionally, the Company has 5,000km2 highly prospective exploration ground in Mali and Liberia and is constantly evaluating new quality assets.

 

For more information, please visit www.hummingbirdresources.co.uk

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFELFFEKFZBBL
Date   Source Headline
25th Apr 20247:00 amRNSQ1 2024 Operational and Trading Update
19th Apr 20247:00 amRNSNotice of Q1-2024 Operational and Trading Update
16th Apr 20247:00 amRNSOperation Update & Kouroussa Production Roadmap
28th Mar 20247:00 amRNSUpdate of Mining Operations at Kouroussa
20th Mar 20243:26 pmRNSResponse to Corica Mining Statement
18th Mar 20249:32 amRNSUpdate on Mining Operations at Kouroussa
11th Mar 20248:00 amRNSBlock Listing Six Monthly Return
27th Feb 20247:00 amRNSPasofino Gold announces exploration update
5th Feb 20248:00 amRNSUpdated Corporate Presentation
31st Jan 20247:00 amRNSQ4-2023 Operational and Trading Update
25th Jan 20247:00 amRNSKouroussa Mine Update/Notice of Q4 Trading Update
24th Jan 20247:00 amRNSPasofino Gold Announces US$2.3m Private Placement
19th Jan 202412:47 pmRNSNotification of Major Holdings
10th Jan 20242:21 pmRNSResult of GM, Director Dealing and TVR
10th Jan 20247:00 amRNSResult of Open Offer and Director Dealing
21st Dec 20237:00 amRNSPlacement Update, Open Offer & Notice of GM
21st Dec 20237:00 amRNSOperational and Exploration Update
13th Dec 20237:00 amRNSCompletion of Pasofino Gold to 51% interest
7th Dec 20237:00 amRNSCorporate strategy update, equity placement & TVR
16th Nov 20237:00 amRNSUpdated Corporate Presentation
26th Oct 20237:00 amRNSQ3-2023 Operational and Trading Update
19th Oct 20237:00 amRNSNotice of Q3-2023 Operational and Trading Update
10th Oct 20237:00 amRNSUpdate Interview with Senior Management
28th Sep 20237:00 amRNS1H23 Group Interim Results
13th Sep 20237:00 amRNS2023 Updated Reserves and Resources Statements
11th Sep 20237:00 amRNSBlock Listing Six Monthly Return
25th Jul 20237:30 amRNSQ2 2023 Operational Trading Update Presentation
25th Jul 20237:00 amRNSQ2 2023 Operational and Trading Update
13th Jul 20237:00 amRNSNotice of Second Quarter Trading Update
29th Jun 202310:12 amRNSResult of AGM
29th Jun 20237:00 amRNS2023 AGM Statement
9th Jun 20237:00 amRNSFirst Gold Pour at Kouroussa Gold Mine
6th Jun 20237:00 amRNSPublication of Annual Report
6th Jun 20237:00 amRNSPublication of Sustainability Report 2022
5th Jun 20237:00 amRNSUpdated Corporate Presentation
22nd May 20237:00 amRNSKouroussa Gold Mine Commissioning Update
2nd May 20237:00 amRNSKouroussa Gold Mine Commissioning Begins
19th Apr 20237:30 amRNSMedia presentation of Q1 2023 Operational Update
19th Apr 20237:00 amRNSQ1 2023 Operational and Trading Update
18th Apr 202311:37 amRNSAIM Rule 17
31st Mar 20237:00 amRNS2023 LTIP & Deferred Share Awards and TVR
20th Mar 20239:05 amRNSSecond Price Monitoring Extn
20th Mar 20239:00 amRNSPrice Monitoring Extension
13th Mar 20232:54 pmRNSResult of General Meeting, Director Dealing & TVR
10th Mar 20237:30 amRNSKouroussa Gold Mine, Construction Media Update
10th Mar 20237:05 amRNSBlock Listing Six Monthly Return
10th Mar 20237:00 amRNSResult of Open Offer and Director Dealing
7th Mar 20232:05 pmRNSSecond Price Monitoring Extn
7th Mar 20232:00 pmRNSPrice Monitoring Extension
2nd Mar 202311:36 amRNSNotification of Major Holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.