The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksHochschild Regulatory News (HOC)

Share Price Information for Hochschild (HOC)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 151.20
Bid: 151.20
Ask: 151.80
Change: 0.00 (0.00%)
Spread: 0.60 (0.397%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 151.20
HOC Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q2 2016 Production Report

21 Jul 2016 07:00

RNS Number : 7965E
Hochschild Mining PLC
21 July 2016
 

 

__________________________________________________________________________________

21 July 2016

 

Production Report for the 6 months ended 30 June 2016

 

 

Ignacio Bustamante, Chief Executive Officer said:

"The first half of 2016 has proved to be pivotal in Hochschild's recent history with the delivery of strong production results, continued cost reduction, further debt repayments and recently, re-entry into the FTSE 250 Index. Our Inmaculada operation has performed above expectations and is on track to exceed its production and cost targets for the year emphasising its world class competitive position. We are now raising our target for overall 2016 production by 6% to 34 million silver equivalent ounces whilst at revising our all all-in sustaining cost down to between $11.0 and $11.5 per silver equivalent ounce. Furthermore, despite additional debt repayment, our cash position remains very strong at over $100 million."

 

Operational highlights

§ Q2 2016 attributable production exceeded expectations1

o 4.5 million ounces of silver

o 67.0 thousand ounces of gold

o 9.5 million silver equivalent ounces, up 86% versus Q2 2015 (5.1 million ounces)

o 128.5 thousand gold equivalent ounces

§ H1 2016 attributable production driven by strong Inmaculada performance

o 8.2 million ounces of silver

o 118.1 thousand ounces of gold

o 17.0 million silver equivalent ounces

o 229.1 thousand gold equivalent ounces

o Inmaculada produced 111.2 thousand gold equivalent ounces

 

Strengthening financial position

§ $70m of debt repaid to date in 2016

§ Total cash of approximately $103 million as at 30 June 2016 ($84 million as at 31 December 2015)

§ Net debt of approximately $280 million as at 30 June 2016 ($366 million as at 31 December 2015)

 

Revised outlook

§ Full year production now forecast to be 34 million silver equivalent ounces (460 thousand gold equivalent ounces) from 32 million ounces

§ All-in sustaining costs per silver equivalent ounce now expected to be between $11.0-11.5 for 2016 (previously $12.0- 12.5)

 

Capital Markets Event

§ Capital Markets Event to be held on 6th September 2016 in London

__________________________________________________________________________________

 

A conference call will be held at 2.30pm (London time) on Thursday 21 July 2016 for analysts and investors.

Dial in details as follows:

International Dial in: +44 (0) 20 3139 4830

UK Toll-Free Number: +44(0) 808 237 0030

Pin: 38264089#

A recording of the conference call will be available for one week following its conclusion, accessible from the following telephone number:

International: +44 (0) 20 3426 2807

UK Toll Free: +44(0) 808 237 0026

Pin: 674714#

 

 

________________

 1 All equivalent figures assume the average gold/silver ratio for 2015 of 74x.

 

 

_________________________________________________________________________________

Overview

In Q2 2016, the Company delivered attributable production of 128.5 thousand gold equivalent ounces or 9.5 million silver equivalent ounces. This comprised of 4.5 million ounces of silver and 67.0 thousand ounces of gold. Overall, in the first half of 2016, the Company delivered attributable production of 229.1 thousand gold equivalent ounces or 17.0 million silver equivalent ounces, including 8.2 million ounces of silver and 118.1 thousand ounces of gold.

 

TOTAL GROUP PRODUCTION

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Silver production (koz)

5,415

4,329

4,178

9,744

7,701

Gold production (koz)

79.39

60.04

34.67

139.43

61.33

Total silver equivalent (koz)

11,290

8,772

6,744

20,062

12,240

Total gold equivalent (koz)

152.57

118.54

91.13

271.11

165.40

Silver sold (koz)

5,614

4,471

4,437

10,085

7,785

Gold sold (koz)

83.55

62.54

32.36

146.10

58.01

Total production includes 100% of all production, including production attributable to Hochschild's joint venture partner at San Jose.

ATTRIBUTABLE GROUP PRODUCTION

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Silver production (koz)

4,548

3,662

3,386

8,210

6,265

Gold production (koz)

67.04

51.08

23.40

118.12

40.60

Silver equivalent (koz)

9,509

7,442

5,117

16,951

9,269

Gold equivalent (koz)

128.50

100.56

69.15

229.06

125.26

Attributable production includes 100% of all production from Arcata, Inmaculada, Pallancata and 51% from San Jose.

 

Production

Inmaculada

Product

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Ore production (tonnes treated)

338,630

280,530

52,325

619,161

52,325

Average grade silver (g/t)

142

121

89.16

132

89.16

Average grade gold (g/t)

4.42

4.05

2.92

4.25

2.92

Silver produced (koz)

1,396

974

95

2,370

95.45

Gold produced (koz)

45.18

34.02

3.42

79.20

3.42

Silver equivalent (koz)

4,739

3,492

348

8,231

348

Gold equivalent (koz)

64.04

47.19

4.71

111.23

4.71

Silver sold (koz)

1,585

882

-

2,468

-

Gold sold (koz)

50.26

31.91

-

82.17

-

 

Inmaculada delivered its strongest quarter since commissioning with gold production at 45,000 ounces and silver production of1.4 million ounces (gold equivalent production of 64 thousand ounces). Throughout the first half, grades and silver recoveries have been better than expected in the original mine plan and, combined with the ongoing improved tonnage per day rates, H1 production was able to reach 111 thousand gold equivalent ounces (8.2 million silver equivalent ounces).

 

Arcata

Product

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Ore production (tonnes treated)

172,305

161,092

155,373

333,397

300,924

Average grade silver (g/t)

345

309

349.56

327

340

Average grade gold (g/t)

1.31

1.13

0.97

1.22

0.97

Silver produced (koz)

1,592

1,377

1,439

2,970

2,726

Gold produced (koz)

5.68

4.68

3.69

10.36

7.17

Silver equivalent (koz)

2,013

1,724

1,713

3,736

3,256

Gold equivalent (koz)

27.20

23.29

23.14

50.49

44.00

Silver sold (koz)

1,572

1,349

1,626

2,922

2,683

Gold sold (koz)

5.70

4.43

4.07

10.14

6.92

 

At Arcata, silver production in the second quarter was 1.6 million ounces with gold production of 5,700 ounces which results in silver equivalent production of 2.0 million ounces, an 18% improvement on the first quarter of 2015 (Q2 2015: 1.7 million ounces). As in the first quarter this has been driven by better than expected mined tonnage resulting from the success of the Company's 2015 brownfield exploration programme in addition to higher silver recoveries. Overall in the first half Arcata has produced a very solid 3.7 million silver equivalent ounces (H1 2015: 3.3 million ounces).

 

Pallancata

Product

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Ore production (tonnes treated)

66,313

69,423

140,829

135,736

289,551

Average grade silver (g/t)

358

324

268

341

248

Average grade gold (g/t)

1.85

1.69

1.32

1.77

1.19

Silver produced (koz)

658

615

1,026

1,273

1,948

Gold produced (koz)

3.32

3.05

4.55

6.37

8.44

Silver equivalent (koz)

903

841

1,363

1,745

2,573

Gold equivalent (koz)

12.21

11.37

18.42

23.58

34.77

Silver sold (koz)

757

559

1,135

1.315

1,986

Gold sold (koz)

3.76

2.74

4.85

6.50

8.33

 

At Pallancata, as expected, tonnage through the plant in the first half was lower than the average 2015 rate with operations in a transitionary period before the introduction of feed from the new Pablo vein towards the end of the year. Production in Q2 was 658,000 ounces of silver and 3,320 ounces of gold bringing the silver equivalent total to 903,000 ounces (Q2 2015: 1.1 million).

 

The 950 metre ramp to reach the Pablo vein has now been completed and approximately 600 metres of further mine infrastructure has also been developed. Currently work is advancing on the vein gallery. The Company remains on track to start production at the end of 2016.

 

San Jose

Product

Q2 2016

Q1 2016

Q2 2015

H1 2016

H1 2015

Ore production (tonnes treated)

146,829

101,937

124,224

248,766

232,995

Average grade silver (g/t)

428

470

466

446

448

Average grade gold (g/t)

6.09

6.27

6.47

6.16

6.34

Silver produced (koz)

1,770

1,362

1,617

3,132

2,932

Gold produced (koz)

25.21

18.28

23.01

43.49

42.30

Silver equivalent (koz)

3,635

2,715

3,320

6,350

6,062

Gold equivalent (koz)

49.12

36.39

44.86

85.81

81.92

Silver sold (koz)

1,699

1,681

1,676

3,380

3,115

Gold sold (koz)

23.83

23.46

23.45

47.29

42.75

 The Company has a 51% interest in San Jose.

 

The San Jose operation delivered yet another solid quarter at 3.6 million silver equivalent ounces, slightly ahead of the corresponding period of 2015, resulting from better than planned grades (gold and silver) and higher than expected tonnage. Silver production in the first half totalled 3.1 million ounces and gold production was 43,490 ounces resulting in silver equivalent production of 6.4 million ounces, a 5% improvement on the H1 2015 (6.1 million ounces).

 

Average realisable prices and sales

Average realisable precious metal prices in Q2 2016 (which are reported before the deduction of commercial discounts and include the effects of the existing hedging agreements) were $1,213/ounce for gold and $17.9/ounce for silver (Q2 2015: $1,212/ounce for gold and $16.3/ounce for silver). For H1 2016, average realisable precious metal prices were $1,236/ounce for gold and $17.1/ounce for silver (H1 2015: $1,227/ounce for gold and $16.9/ounce for silver).

 

Brownfield exploration

Due to the rainy season in Peru, exploration programmes only commenced in the second quarter.

 

At Arcata 2,135 metres were drilled in the first half to test North-South structures in the central area of the mine. The plan for the remainder of the year is to drill in the Tunel 4 zone to extend existing structures and identify new ones. Some highlights are presented below:

 

Vein

Results

Ramal Marion Sur

DDH-941-GE16:1.3m @ 1.8 g/t Au & 576 g/t Ag

DDH-943-GE16:1.3m @ 4.1 g/t Au & 2,157 g/t Ag

Tunel 4

DDH-912-GE16:7.8m @ 1.1 g/t Au & 205 g/t Ag

DDH-939-LM16:1.3m @ 3.6 g/t Au & 2,655 g/t Ag

 

At Pallancata, a drilling campaign has just begun to the north and south of the Pablo structure to test anomalies and add potential resources (potentially an extension of the Luisa vein). So far, 698m have been drilled with results pending.

 

At San Jose 1,240m has been drilled mainly in the Aguas Vivas area with the programme ongoing.

 

Financial position

Total cash was approximately $103 million with net debt of approximately $280 million as at 30 June 2016.

 

On 8 June 2016, the remaining $50 million of the original $100 million Scotiabank medium term loan was prepaid with no penalties. In addition, on 17 June 2016 and 4 July 2016, a further $15 million and $5 million respectively of short term debt was repaid to BBVA in Peru. All payments were financed from existing cash resources.

 

Outlook

Following better than expected performances from the Inmaculada and Arcata mines, Hochschild has increased its full year production guidance from 32.0 million to 34 million of attributable silver equivalent ounces.

 

The all-in sustaining cost per silver equivalent ounce target has also been revised and is now expected to be between $11.0 to $11.5, a significant improvement on the previous guidance of $12.0 to $12.5 per ounce.

__________________________________________________________________________________

 

Enquiries:

 

Hochschild Mining plc

Charles Gordon +44 (0)20 3714 9040

Head of Investor Relations

 

Hudson Sandler

Charlie Jack +44 (0)207 796 4133

Public Relations

__________________________________________________________________________________

 

About Hochschild Mining plc

Hochschild Mining plc is a leading precious metals company listed on the London Stock Exchange (HOCM.L / HOC LN) with a primary focus on the exploration, mining, processing and sale of silver and gold. Hochschild has over fifty years' experience in the mining of precious metal epithermal vein deposits and currently operates four underground epithermal vein mines, three located in southern Peru and one in southern Argentina. Hochschild also has numerous long-term projects throughout the Americas.

__________________________________________________________________________________

 

Forward looking statements

This announcement may contain forward looking statements. By their nature, forward looking statements involve risks and uncertainties because they relate to events and depend on circumstances that will or may occur in the future. Actual results, performance or achievements of Hochschild Mining plc may, for various reasons, be materially different from any future results, performance or achievements expressed or implied by such forward looking statements.

 

The forward looking statements reflect knowledge and information available at the date of preparation of this announcement. Except as required by the Listing Rules and applicable law, the Board of Hochschild Mining plc does not undertake any obligation to update or change any forward looking statements to reflect events occurring after the date of this announcement. Nothing in this announcement should be construed as a profit forecast.

 

This announcement contains information which prior to its release could be considered inside information.

 

- ends -

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLQBLFLQDFEBBE
Date   Source Headline
24th Apr 20247:00 amRNSQ1 Production Report
2nd Apr 20247:00 amRNSSale of Crespo project for $15 million
13th Mar 20247:00 amRNSFinal Results
6th Mar 20247:00 amRNSNotice of Results and Investor Presentation
5th Mar 20247:00 amRNSOption to acquire Monte Do Carmo project, Brazil
23rd Feb 202411:01 amRNSDirector Declaration
21st Feb 20247:00 amRNSFirst Gold Pour at Mara Rosa
31st Jan 20248:33 amRNSDirector Declaration
24th Jan 20247:00 amRNSQ4 2023 Production Report
19th Jan 20242:58 pmRNSHolding in Company
14th Dec 20237:00 amRNSDirectorate Change
8th Dec 202311:00 amRNSAGM Update
22nd Nov 20239:42 amRNSCapital Markets event & 2024 Guidance - Correction
22nd Nov 20237:00 amRNSCapital Markets event & 2024 Guidance
17th Nov 202312:37 pmRNSHolding in Company
16th Nov 20237:00 amRNSNotice of retail investor presentation
18th Oct 20237:00 amRNSQ3 2023 Production Report
21st Sep 20237:00 amRNSAppointment of Non-Executive Director
6th Sep 20237:00 amRNSInterim Results
29th Aug 20237:00 amRNSConfirmation of Board and Management changes
17th Aug 20234:38 pmRNSHolding in Company
14th Aug 20237:00 amRNSHochschild Provides Update on Volcan Gold Project
11th Aug 20239:30 amRNSHolding in Company
4th Aug 202310:53 amRNSHolding in Company
2nd Aug 20237:00 amRNSInmaculada Environmental Permit Approved
25th Jul 20237:00 amRNSQ2 2023 Production Report
10th Jul 20236:05 pmRNSHolding in Company
30th Jun 20234:05 pmRNSReport on Payments to Governments 2022
9th Jun 20234:16 pmRNSAGM Result
31st May 202311:52 amRNSTotal Voting Rights
30th May 20237:00 amRNSHochschild Announces Leadership Transition
12th May 20235:51 pmRNSAdditional Listing & Voting Rights
10th May 20237:00 amRNSQ1 2023 Production Report
5th May 20232:14 pmRNSDirector Declaration
28th Apr 20233:59 pmRNS2022 Annual Report and Notice of 2023 AGM
20th Apr 20237:00 amRNSFinal Results
5th Apr 20237:00 amRNSHochschild Terminates Option Over Snip Gold
31st Mar 20237:00 amRNSInmaculada Permit Update
31st Jan 20237:00 amRNSQ4 2022 Production Report
30th Dec 20227:00 amRNSInmaculada Permit Update
15th Nov 20225:00 pmRNSHolding in Company
3rd Nov 20227:00 amRNSInmaculada Update
26th Oct 20227:00 amRNSQ3 2022 Production Report
20th Sep 20227:09 amRNSLaunch of New Website
5th Sep 20223:07 pmRNSConversion Rate for 2022 Interim Dividend
17th Aug 20227:00 amRNSInterim Results
16th Aug 20229:57 amRNSPublication of Sustainability Report for 2021
12th Aug 20222:06 pmRNSInvestor Presentation
10th Aug 20227:00 amRNSEnvironmental authorisation at Mara Rosa granted
22nd Jul 20229:55 amRNSDirector Declaration

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.