Galactica Project Update

12 Feb 2026 07:00

RNS Number : 7495S
Helium One Global Ltd
12 February 2026
 

12 February 2026

 

Helium One Global Ltd

("Helium One" or the "Company")

 

Galactica Project Update

 

Helium One Global (AIM: HE1), the primary helium explorer in Tanzania with a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA ("the Galactica Project"), provides an update following the Blue Star Helium (ASX: BNL) ("Blue Star" or "Operator") announcement issued today regarding the Galactica Project.

 

Operator Reported Highlights

· Pinon Canyon Plant scheduled for integrated plant operations next week

· The amine unit will be operational removing CO2 from the input gas stream

· CO2 liquefaction and load components projected to be added H1 2026

· Sales arrangements have been made for spot sales of helium, and discussions regarding long-term contracts with both helium and CO2 off-takers progressing well

· Tie-ins for the State-9 and State-16 wells into the gathering system now complete and ready to be tied into the production facility

· Further expansion and construction of the gathering system for the Jackson-2 well is underway, including the T-section for future connection of Jackson-27

 

 

Facilities Update

The Operator has advised that operations at the newly installed Pinon Canyon Plant are progressing as planned.

Following first gas in December 2025, the plant was shut in to allow for integration of the amine unit. In January 2026, the first tube trailer was delivered as the plant underwent final technical readiness checks and optimisation.

The amine unit is part of the CO2 train that removes CO2 from the inlet stream and with the amine unit operational, gas will be processed and the helium stream will then be processed through the Helium Recovery Unit and into tube trailers.

The Company understands that integrated plant operations will commence next week.

The Operator's focus will now shift to the installation of the CO2 liquefaction and load components and the finalisation of commercial agreements.

The gathering system for State-9 and State-16 has been completed and construction of the gathering system to connect Jackson-2, including the T-section for future connection of Jackson-27, which will provide near-term production increase has commenced.

These follow-on tie-ins are part of the ramp-up through 2026. Planning is advanced for further tie-in and infill drilling aimed at increasing production through the Pinon Canyon Plant, with a clear focus on scaling gas processing and delivering increased revenues.

 

Commercial Progress by The Operator

The Operator is implementing a strategy that anticipates meeting market needs and maximises the value of the end product.

 

 Arrangements have been made for spot sales of helium and discussions in respect of long-term contracts with both helium and CO2 off-takers are progressing.

 

 These discussions are targeting a mix of short-term sales arrangements and long-term offtake agreements to match the targeted ramp-up of the Pinon Canyon Plant's capacity.

 

 

 

For further information please visit the Company's website: www.helium-one.com

 

 

Helium One Global Ltd

+44 20 7920 3150

Lorna Blaisse, CEO

Graham Jacobs, Finance and Commercial Director

Panmure Liberum Limited (Nominated Adviser and Joint Broker)

Scott Mathieson

Phoebe Bunce

+44 20 3100 2000

Zeus Capital Limited (Joint Broker)

Simon Johnson

Louisa Waddell

+44 20 3829 5000

 

Tavistock (Financial PR)

Nick Elwes

Saskia Sizen

 

+44 20 7920 3150

 

 

 

 

 

 

Notes to Editors

 

Helium One Global, the primary helium explorer in Tanzania with a 50% working interest in the Galactica-Pegasus helium development project in Colorado, USA. The Company holds helium licenses within two distinct helium project areas, across two continents. With an expanding global footprint, the Company has the potential to become a strategic player in resolving a supply-constrained helium market.

 

The Company's flagship southern Rukwa Project is located within the southern Rukwa Rift Basin in south-west Tanzania. This project entering a full appraisal and development stage following the success of the 2023/24 exploration drilling campaign, which proved a helium discovery at Itumbula West-1 and, following an extended well test ("EWT"), successfully flowed 5.5% helium continually to surface in Q3 2024.

 

Following the success of the EWT, the Company filed a Mining Licence ("ML") application with the Tanzania Mining Commission in September 2024 and the 480km2 ML was formally awarded to the Company in July 2025.

 

The Company also owns a 50% working interest in the Galactica-Pegasus helium development project in Las Animas County, Colorado, USA. This project is operated by Blue Star Helium Ltd (ASX: BNL) and successfully completed a six well development drilling campaign in H1 2025. The completion of the development programme is a key component of the broader Galactica-Pegasus development strategy; aimed at progressing the helium and CO2 discoveries to near-term commercial production.

 

This programme has seen a systematic approach to developing the extensive Lyons Formation reservoir. The programme has delivered encouraging results, in line with expectations, consistently encountering good helium (up to 3.3% He) and CO2 concentrations in the target formation and demonstrating promising flow potential. The initial Galactica wells were tied into first gas in Q4 2025, with further wells coming onstream in 2026 for both helium and CO2 production.

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCQLLBFQLLLBBZ
Date   Source Headline
4th Jun 20267:00 amRNSHelium Offtake Agreement for Galactica Project
5th May 20267:00 amRNSSigning Ceremony and Advisors Appointed
29th Apr 20267:00 amRNSAppointment of New Chairman
17th Apr 20267:00 amRNSIssue of Awards under the Company’s LTIP
27th Mar 20263:31 pmRNSResult of Oversubscribed WRAP Retail Offer
26th Mar 20267:10 amRNSWRAP Retail Offer Targeting £1,000,000
26th Mar 20267:05 amRNSFundraise of £3.5 million and Retail Offer
26th Mar 20267:00 amRNSGalactica Project Update
26th Mar 20267:00 amRNSUnaudited Interim Results
20th Mar 20267:00 amRNSAIM Rule 17 and Schedule 2(g) Update
5th Mar 20267:00 amRNSGalactica Project Update
16th Feb 20267:00 amRNSSouthern Rukwa Project Update
12th Feb 20267:00 amRNSGalactica Project Update
20th Jan 20267:00 amRNSGalactica Project Update
19th Jan 20267:00 amRNSSouthern Rukwa Helium Project Update
22nd Dec 20257:00 amRNSSuccessful First Gas at Galactica Helium Plant
22nd Dec 20257:00 amRNSSuccessful First Gas at Galactica Helium Plant
15th Dec 202511:19 amRNSResults of Annual General Meeting
15th Dec 20257:00 amRNSProduction Facility Update at Galactica Project
8th Dec 20257:00 amRNSSouthern Rukwa Helium Project Update
17th Nov 20257:00 amRNSNotice of Annual General Meeting
13th Nov 20257:00 amRNSAudited Results for the Year Ended 30 June 2025
31st Oct 20257:00 amRNSGalactica Development Update
13th Oct 20257:00 amRNSFinal Conversion and Termination of Agreement
13th Oct 20257:00 amRNSGalactica Development Update
24th Sep 20257:00 amRNSNotice of Conversion of Advance
22nd Sep 20257:00 amRNSSouthern Rukwa Helium Project Update
18th Sep 20257:00 amRNSGalactica Development Update
29th Aug 20257:00 amRNSNotice of Conversion of Advance
19th Aug 20257:00 amRNSNotice of Conversion of Advance
7th Aug 20257:00 amRNSResult of Oversubscribed WRAP Retail Offer
6th Aug 202512:16 pmRNSEarly Close of WRAP Retail Offer
5th Aug 20254:31 pmRNSWRAP Retail Offer of up to £1,000,000
5th Aug 202512:55 pmRNSPassing of Resolution at General Meeting
30th Jul 20257:00 amRNSConfirmation of NED Appointment and Board Change
18th Jul 202510:41 amRNSConfirmation of ML Award & Proposed £10m Fundraise
3rd Jul 20257:00 amRNSAppointment of New Non-Executive Director
25th Jun 20257:00 amRNSIndependent CPR
11th Jun 20257:00 amRNSUpdate on Southern Rukwa Mining Licence
10th Jun 20257:00 amRNSIntroduction of Employee Benefit Trust Scheme
10th Jun 20257:00 amRNSGalactica Project Update
3rd Jun 20257:00 amRNSState-9 Well Drilled to TD and Free Gas Confirmed
30th May 20251:02 pmRNSIssue of Equity
21st May 20257:00 amRNSState-9 Spud at Galactica Project
15th May 20257:00 amRNSJackson-2 Flow Test Results & Gas Analysis Update
6th May 20257:00 amRNSJackson-2 Well Drilled to TD & Free Gas Confirmed
30th Apr 20257:00 amRNSJackson-2 Spud at Galactica Project
30th Apr 20257:00 amRNSJackson-27 Flow Test Results & Gas Analysis Update
23rd Apr 20257:00 amRNSJackson-27 Well Drilled to TD & Free Gas Confirmed
22nd Apr 20257:00 amRNSJackson-29 Flow Test Results & Gas Analysis Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.