Glenover Project Update

5 Feb 2018 07:00

RNS Number : 8427D
Galileo Resources PLC
05 February 2018
Β 

Β 

Β 

5 February 2018

Galileo Resources Plc

("Galileo" or "the Company")

Glenover Phosphate -Update

Β 

Galileo (AIM: GLR) is pleased to announce that its 36%-owned subsidiary, Glenover Phosphate (Pty) Ltd ("Glenover"), has accepted a Heads of Agreement (the "Heads") from a major phosphate/fertiliser producer ("MPP") for the acquisition and supply to MPP of raw phosphate rock ("Phosphate Rock") in the form of flotation concentrate from Glenover's phosphate-rare earth project ("the Project") in the Limpopo Province of the Republic of South Africa.

Β 

Additionally, the Company announces that the Department of Mineral Resources ("DMR") has accepted Glenover's application for a mining right (submitted 15 November 2017) to mine and produce phosphate and in this regard Glenover has commenced the requisite environmental impact assessment ("EIA") programme on the Project for the grant of a mining right.

Highlights

Β 

Β· Glenover accepts Heads from MPP for the acquisiton and long term (minimum 15 years) supply of Phosphate Rock to MPP

Β 

Β· The Heads is the outcome of MPP's extensive initial testwork in collaboration with Glenover as to suitability of the Phosphate Rock for its phosphate process and a review of alternative local and international sources of Phosphate Rock

Β 

Β· Rare-earths (and niobium) in the tailingsΒ ofΒ anyΒ futureΒ processingΒ of Phosphate Rock byΒ MPP, would beΒ available to Glenover for recovery and furtherΒ beneficiation

Β 

Β· Mining Right Application for the Glenover Project submitted to the Department of Mineral Resources on 15 November 2017 and now accepted

Β 

Β· DMR acceptance increases Galileo's beneficial interest in the Project to 36%

Β 

Β· On successful grant of the Mining Right, Galileo will increase its beneficial interest to 38% in the Project

Β 

The Heads are subject to the parties entering into a definitive supply agreement and otherwise terminate on 30 April 2018. Furthermore, the Heads contains the following material terms:

- MPP requires further pilot scale work to determine the suitability of the Phosphate Rock in its process as one of the main conditions precedent, but further capital expenditure by the MPP for the second phase pilot scale test work will be subject to the Parties agreeing on the main commercial terms in the Heads;

- The Flotation Plant will be built at the mine site and funded and owned by Glenover which will require additional funding; and

- The MPP will purchase Glenover Phosphate Rock (33% P2O5 content) at international market prices

Colin Bird CEO commented: "Galileo and JV partner Ferminore have been in discussions with various interested groups concerning the development of the Project. One group has already carried out extensive bench scale testwork and on this basis has entered into a preliminary offtake agreement, with pilot scale scale testing remaining the main hurdle to a binding agreement. Importantly too, is the fact that the rare earths (and niobium) in the ore, an asset of value, would still be available for future beneficiation. The board is pleased that the potential exists by way of this Heads to realise a significant return on the Company's initial investment in the Project".

Β 

The Heads is the outcome of phase 1 of a 2-phase Pilot Plant Study investigation by MPP ("Investigation") (see previous announcement 12 June 2017) as to suitability of the Phosphate Rock for its process and also MPP's review of various other local and international sources of raw phosphate rock.

Β 

The Heads is subject, among others, to the second phase of Investigation, comprising technical and pilot plant work, including the production of 30 tonnes of Phosphate Rock for piloting by MPP, being successful and to the incorporation of the terms of Agreement into a definitive supply agreement.

Β 

The termination date of the Agreement is the earlier of 30 April 2018 and the signature date of the definitive supply agreement.

Β 

The Glenover ProjectΒ 

Β 

The Project is located approximately 90 km northwest of the town of Thabazimbi in the Waterberg region of Limpopo Province in the Republic of South Africa. The Project comprises an inactive phosphate mine comprising a SAMREC compliant 10.37 million tonnes (Mt) grading 18.73% phosphate (P2O5) including an inferred 2.685 Mt surface stockpiles of phosphate ore grading 22.21 %P2O5 and a measured and indicated 7.4 Mt grading 17.51 %P2O5 in an apatite (phosphate mineral)- breccia core remaining in the previously mined open pit. The open pit is approximately 100 metres deep with a surface width of approximately 200 metres.

Β 

Glenover Phosphate Resource (SAMREC compliant) 1

Resource

Resource

Tonnage

P2O5

Β 

Class

Mt

(%)

Apatite-Haematite Breccia

Measured

Β 

Β 

Indicated

7.407

17.57

Total Measured & Indicated

7.407

17.57

Inferred

0.274

15.83

Β 

Β 

Β 

Β 

Surface Stockpiles

Inferred

2.685

22.21

Total

Measured indicated & inferred

10.37

18.73

1 Data contained in the Preliminary Economic Assessment (PEA) referred to in RNS announcement of 07 March 2013 "Results of Glenover PEA"

Β 

Further details as set out in past announcements are available from the Company'sΒ website, www.galileoresources.com, which details the Company's project portfolio as well as a copy of this announcement:

Β 

YouΒ canΒ alsoΒ followΒ GalileoΒ onΒ Twitter:Β @GalileoResource

Β 

Β 

Β 

Β 

Technical Sign-Off

Andrew Sarosi, Director of Galileo, who holds a B.Sc. MetallurgyΒ and M.Sc. Engineering, University of Witwatersrand and is a member of the Institute of Materials, Minerals and Mining, is a "qualified person" as defined under the AIM Rules for Companies and a competent person under the reporting standards. The technical parts of this announcement have been prepared under Andrew's supervision and he has approved the release of this announcement.

Β 

ENDS

Β 

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014.

Β 

Β 

Β 

For further information, please contact:

Β 

Galileo Resources PLC

Colin Bird, Chairman

Tel +44 (0) 20 7581 4477

Andrew Sarosi, Executive Director

Tel +44 (0) 1752 221937

Beaumont Cornish Limited - Nomad

Roland Cornish/James Biddle

Tel +44 (0) 20 7628 3396

Beaufort Securities Limited - Broker

Jon Belliss

Tel +44 (0) 20 7382 8416

Β 

Technical Glossary:

Β 

Inferred Mineral Resource: that part of a Mineral Resource for which volume or tonnage, grade and mineral content can be estimated with only a low level of confidence. It is inferred from geological evidence and sampling and assumed but not verified geologically or through analysis of grade continuity. It is based on information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that may be limited in scope or of uncertain quality and

reliability.

Β 

Indicated Mineral Resource: Β that part of a Mineral Resource, for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a reasonable level of confidence. It is based on information from exploration, sampling and testing of material gathered from locations such as outcrops, trenches, pits, workings and drill holes. The locations are too widely or inappropriately spaced to confirm geological or grade continuity but are spaced closely enough for continuity to be assumed.

Β 

Measured Mineral Resource: that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a high level of confidence. It is based on detailed and reliable information from exploration, sampling and testing of material from locations such as outcrops, trenches, pits, workings and drill holes. The locations are spaced closely enough to confirm geological and grade continuity.

Β 

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
UPDTTMRTMBIMBTP
Date   Source Headline
11th May 20269:34 amRNSWorking Capital Facility, Issue of Equity & TVR
2nd Mar 20267:00 amRNSUpdate on Drill Targeting at Ferber Property
2nd Feb 20261:06 pmRNSHolding(s) in Company
20th Jan 20267:00 amRNSKalahari Copperbelt Drilling – Assay Results
24th Dec 202512:00 pmRNSHalf-year Financial Report
24th Dec 202512:00 pmRNSHalf-year Financial Report
4th Dec 20257:00 amRNSExploration Update from Ferber Property, Nevada
3rd Dec 20257:00 amRNSMolefe Project Drilling Update, Zambia
28th Nov 20257:00 amRNSCollaboration Agreement over Molefe Project
28th Oct 20251:54 pmRNSResult of AGM
3rd Oct 202511:57 amRNSNotice of AGM
29th Sep 20259:32 amRNSAudited Results for the year ended 31 March 2025
26th Sep 202511:51 amRNSHolding(s) in Company
17th Sep 202511:00 amRNSOversubscribed Placing, Issue of Equity & TVR
1st Sep 20257:00 amRNSKalahari Copperbelt Drilling – Update
26th Aug 20257:00 amRNSKalahari Copperbelt - RC drilling commences
18th Aug 20257:00 amRNSExploration Extends Target Footprint at Ferber
13th Aug 20257:00 amRNSKCB – Re-logging & Testing Confirms Copper
22nd Jul 20252:47 pmRNSHolding(s) in Company
13th May 20257:00 amRNSRoyalty and Exploration Agreement at Ferber
11th Apr 20258:00 amRNSBoard Appointment
25th Mar 20257:00 amRNSPhase 3 Drilling Results at Shinganda Project
19th Mar 202511:54 amRNSMining licence issued for the Kashitu Project
5th Mar 20251:46 pmRNSLicence 28001 Update, Western Foreland, NW Zambia
4th Mar 20257:00 amRNSKalahari Copperbelt Geophysical Survey Results
7th Jan 20253:55 pmRNSHolding(s) in Company
30th Dec 20243:43 pmRNSHalf-year Report
26th Nov 20247:00 amRNSDirector dealings
6th Nov 20242:44 pmRNSResult of AGM
28th Oct 20243:45 pmRNSDirector dealings
25th Oct 20247:00 amRNSADDITIONAL MINING LICENCE ISSUED FOR LUANSOBE
14th Oct 20244:33 pmRNSNotice of AGM
14th Oct 20247:00 amRNSCommencement of IP Geophysical Surveying
3rd Oct 20247:00 amRNSDrilling update on Shinganda Licence
27th Sep 202412:23 pmRNSAnnual Results for the year ended 31 March 2024
6th Sep 20247:00 amRNSUpdate on the Luansobe Copper Project
21st Aug 20247:00 amRNSDrilling underway on Shinganda Licence, Zambia
9th Aug 20247:00 amRNSNew drill programme for Shinganda
8th Aug 20247:00 amRNSDrilling underway on Licence 28001, NW Zambia
29th Jul 20247:00 amRNSCommencement of Drilling in the Western Foreland
11th Jul 202411:20 amRNSHolding(s) in Company
24th Jun 20247:00 amRNSShinganda Project Update
29th May 202411:26 amRNSMining licence issued for Luansobe Copper Project
2nd May 20249:52 amRNSReceipt of cash payment for Glenover sale
23rd Apr 20245:04 pmRNSDirector's Dealings
19th Mar 20247:00 amRNSKamativi Lithium-Tin Project – Drill Assay Results
29th Feb 20247:00 amRNSUpdate on 51% interest in Lithium & Gold Projects
1st Feb 20247:00 amRNSNew Targets Defined on PL039/2018 and PL040/2018
30th Jan 20247:00 amRNSThree Copper Targets Discovered on PL253/2018
28th Dec 20233:18 pmRNSHalf-year Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.