Interim Management Statement

10 Nov 2011 07:00

RNS Number : 8278R
Ferrexpo PLC
10 November 2011
Β 

ο»Ώ

10 November 2011

Ferrexpo plc

("Ferrexpo", the "Group" or the "Company")

Β 

Interim Management Statement

FerrexpoΒ plc ("Ferrexpo", the "Company" or the "Group") today issues its interim management statement in accordance with the UK Listing Authority's Disclosure and Transparency Rules.

Β 

Production

As announced on 6 October 2011, total pellet production from own ore in 3Q 2011 increased by 2.8% compared to 2Q 2011. Production of higher grade 65% Fe pellets increased by 12.3% compared to 3Q 2010 and by 6.6% year to date. Production of pellets from third party concentrate is dependent on availability in local markets. Overall, including third party concentrate, total pellet production in 3Q 2011 was in-line with 2Q 2011 at 2.5 million tonnes.

Β 

Production in Tonnes '000

3Q 2011

2Q 2011

Change

3Q 2010

Change

YTD

YTD

Change

%

%

2011

2010

%

Production from own raw materials

Iron Ore

7,497.3

7,182.0

4.4

7,386.4

1.5

21,695.5

21,589.1

0.5

Concentrate

2,949.8

2,865.4

2.9

2,873.3

2.7

8,524.5

8,382.9

1.7

Pellets

62% Fe

1,258.3

1,217.3

3.4

1,342.1

(6.2)

3,513.0

3,726.3

(5.7)

65% Fe

1,075.3

1,053.3

2.1

957.6

12.3

3,214.7

3,014.6

6.6

Total Pellets

2,333.6

2,270.5

2.8

2,299.7

1.5

6,727.7

6,740.9

(0.2)

Production/reprocessing from purchased raw materials

Pellets

62% Fe

64.4

56.2

14.6

42.2

52.5

154.0

132.9

15.9

65% Fe

74.0

155.1

(52.3)

217.6

(66.0)

375.1

571.5

(34.4)

Total Pellets

138.4

211.3

(34.5)

259.8

(46.7)

529.1

704.4

(24.9)

Total Pellets Produced

2,471.9

2,481.8

(0.4)

2,559.5

(3.4)

7,256.8

7,445.3

(2.5)

62% Fe

1,322.6

1,273.4

3.9

1,384.3

(4.5)

3,667.0

3,859.2

(5.0)

65% Fe

1,149.3

1,208.4

(4.9)

1,175.2

(2.2)

3,589.8

3,586.1

0.1

Β 

Production in October was in line with expectations and represented 774 thousand tonnes of pellets compared to 781 thousand tonnes of pellets in September 2011. Year to date production from own ore is in line with 2010 at 7.5 million tonnes.

Β 

Costs

From 1 July 2011 to 31 October 2011, the cost environment reflected local PPI inflation of 15.6% year to date driven principally by higher electricity and gas prices. The increase in the average C1 cash cost for the period was offset by higher production and efficiency improvements and as a result increased by 8.9% to US$52.5 per tonne (versus 1H 2011 of US$48.2 per tonne). The Ukrainian Hryvnia, in which 70% of the Group's operating costs are denominated, remained stable against the US Dollar at around 7.99 UAH to 1 US$.

Β Β 

Sales

Sales volumes from 1 July 2011 to 31 October 2011 were 3.3 million tonnes. The average realised price in 3Q 2011 was in line with that achieved for 2Q 2011. For the full year the Group is expected to sell approximately 25% of its output on spot with new long term contracts commencing in 2012. These new long term contracts are expected to be on an index linked price mechanism which will complement existing contracts on an index linked and quarterly negotiated basis.

Β 

Growth projects

The investment programme announced in November 2010 is progressing as planned:

Β 

Ferrexpo Yeristovo Mining (FYM)

First ore (budgeted cost US$267 million):

The Group is progressing in line with its schedule and budget to achieve first ore from the Yeristovo deposit in 2013. FYM took delivery of five 220 tonne CAT trucks in October 2011 increasing the current haul truck fleet to 21 units.

Β 

In terms of the next stage of development for FYM, design of the concentrator is ongoing. Full board approval is expected in March 2012, subject to market conditions.

Β 

Ferrexpo Poltava Mining (FPM)

Mine Life Extension Project (budgeted cost US$168 million):

This project is proceeding on schedule and is progressing as planned to extend the life of the FPM mine to 2038. Higher energy costs for stripping have inevitably caused cost increases; the Company expects this to moderate over the remaining life of the project which runs to 2018.

Β 

Quality Upgrade Project (budgeted cost US$212 million):

The project is underway to increase the proportion of 65% Fe pellets to 100% of production and costs are in line with the budget. The planned works will increase FPM's capacity by upgrading the existing ore floatation circuit and adding two additional circuits. Orders for long lead items have been placed and detailed design is underway. The Company forecasts that the project will be completed and fully commissioned in 2014 and ramp up to full 65% Fe production will occur in 2015.

Β 

In summary, the Group remains on track to increase pellet output capacity to 12 million tonnes per annum by the end of 2013 and to increase production of 65% Fe pellets to 100% of output by the end of 2014. These projects are fully financed.

Β 

Funding

During the period under review, Ferrexpo secured a new credit facility for US$420 million at 225 basis points above LIBOR. The Group now has gross borrowing facilities of over US$1 billion with an average tenor of 4 years. Net debt as of 31 October 2011 was US$60.0 million. The Group believes that it has sufficient financing to complete the core projects in its investment pipeline.

Β 

Michael Abrahams, Ferrexpo Chairman, said:

"Ferrexpo continues to benefit from its established reputation as a quality long term pellet supplier. Should there be further deterioration in market conditions, the Group remains well positioned in the global market to maintain full production due to its low cost position on the supply curve and established infrastructure to seaborne markets, supporting the local economy and its reputation as reliable supplier to the global steel industry."

Β 

Next Update

Ferrexpo willΒ releaseΒ a 4Q 2011 production report on 12 January 2012.

Β 

For further information, please contact:

Β 

Ferrexpo:

Ingrid McMahon

+44 207 389 8304

Pelham Bell Pottinger

Mark Antelme

+44 207 861 3894

Lorna Spears

+44 207 861 3883

Β 

Notes to Editors:

Β 

Ferrexpo is a Swiss headquartered iron ore company with assets in Ukraine. It is principally involved in the production and export of high quality iron ore pellets, which are used in the manufacture of steel. Ferrexpo's resource base is one of the largest iron ore deposits in the world. Its current producing asset, FPM, produced approximately 10 million tonnes of iron ore pellets in 2010 making it the largest exporter of pellets in the CIS. The Company has a diversified customer base supplying steel mills in Austria, Serbia, Slovakia, Czech Republic, Germany and other European states, as well as in China, India, Japan, and other Asian countries. Ferrexpo is listed on the main market of the London Stock Exchange under the ticker FXPO. For further information, please visit www.ferrexpo.com

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
IMSBLBLTMBTMBFB
Date   Source Headline
29th May 20267:00 amRNSNotice of 2026 Annual General Meeting
28th Apr 20267:00 amRNSFunding Update and Delay in Financial Statements
22nd Apr 20267:00 amRNSUpdate on funding options
20th Apr 20267:00 amRNSSale of Iron Destiny and Update on Funding Options
15th Apr 20267:00 amRNSProduction Report for 1Q 2026
1st Apr 20269:41 amRNSTrading Update
9th Mar 20267:00 amRNSOperations and Corporate Update
2nd Mar 20268:20 amRNSDirector/PDMR Shareholding
24th Feb 20263:35 pmRNSUpdate regarding Ukrainian subsidiary
20th Jan 20263:39 pmRNSUpdate on operations in Ukraine
14th Jan 20267:00 amRNSProduction Report for 4Q 2025
31st Dec 20257:00 amRNS-REnd of year letter from Interim Executive Chair
31st Dec 20257:00 amRNS-REnd of year letter from Interim Executive Chair
14th Nov 20257:05 amRNSDirector Declaration
10th Nov 20257:00 amRNSLimited attack on power infrastructure
4th Nov 20257:00 amRNSPublication of Responsible Business Report
6th Oct 20257:00 amRNSProduction Report for 3Q 2025
11th Sep 202511:59 amRNSGeneral Meeting voting results
11th Aug 20257:00 amRNSPublication of Notice of General Meeting 2025
6th Aug 20257:00 amRNSInterim Results for six months ended 30 June 2025
7th Jul 20257:00 amRNSProduction Report for 2Q 2025
10th Jun 20254:48 pmRNSDirector/PDMR Shareholding
9th Jun 20254:35 pmRNSDirector/PDMR Shareholding
22nd May 202512:47 pmRNSResult of AGM
16th May 20255:00 pmRNSReport on Payments to Governments
15th May 202512:15 pmRNSUpdate regarding Ukrainian subsidiary
30th Apr 20257:00 amRNSLetter to shareholders re: auditor engagement
17th Apr 20255:32 pmRNSUkraine subsidiaries VAT refunds
10th Apr 20257:00 amRNSNotice of Annual General Meeting and 2024 ARA
7th Apr 20257:00 amRNSProduction Report for 1Q 2025
21st Mar 20257:00 amRNSStatement regarding Ukraine VAT refunds
19th Mar 20258:00 amRNSInternational Investment Agreements Notification
19th Mar 20257:00 amRNSFull Year Financial Results for 2024
11th Mar 20257:00 amRNSAnnouncement of Full Year 2024 Financial Results
5th Mar 20257:00 amRNSResponse to SBI Statement
4th Feb 20253:17 pmRNSUpdate regarding Ukrainian subsidiary
23rd Jan 20259:52 amRNSUpdate regarding Ukrainian Subsidiary
16th Jan 202511:30 amRNSUpdate regarding Ukrainian subsidiary
13th Jan 20257:00 amRNSResignation of Non-Executive Director
9th Jan 20257:00 amRNSProduction Report for 4Q 2024
30th Dec 20245:00 pmRNSPublication of Climate Change Report
30th Dec 20245:00 pmRNSPublication of Responsible Business Report
7th Oct 20247:00 amRNSProduction Report for 3Q 2024
19th Sep 202412:31 pmRNSGeneral Meeting voting results
12th Aug 20247:00 amRNSNotice of General Meeting 2024
5th Aug 20244:50 pmRNSUpdate on restrictions on shares in subsidiary
31st Jul 202412:28 pmRNSInterim Results for six months ended 30 June 2024
31st Jul 20247:00 amRNSInterim Results for six months ended 30 June 2024
30th Jul 20245:50 pmRNSInterim Results Advisory
8th Jul 20247:00 amRNSProduction Report for 2Q 2024 and 1H 2024

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.