The latest Investing Matters Podcast episode featuring financial educator and author Jared Dillian has been released. Listen here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksEvraz Regulatory News (EVR)

  • This share is currently suspended. It was suspended at a price of 82.52

Share Price Information for Evraz (EVR)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 82.52
Bid: 0.00
Ask: 0.00
Change: 0.00 (0.00%)
Spread: 0.00 (0.00%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 82.52
EVR Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Interim Management Statement for Q3 2012

18 Oct 2012 07:00

RNS Number : 9712O
Evraz Plc
18 October 2012
 



EVRAZ Q3 2012 PRODUCTION REPORT AND

INTERIM MANAGEMENT STATEMENT

18 October 2012 - EVRAZ plc (LSE: EVR) today released its operational results for the third quarter of 2012 and Interim Management Statement.

 

 

Q3 2012 OPERATIONAL HIGHLIGHTS and RECENT DEVELOPMENTS:

 

·; Consolidated crude steel production decreased by 3% compared to Q2 2012 mainly due to lower production at EVRAZ Vitkovice Steel in the Czech Republic and EVRAZ Highveld in South Africa.

·; Despite reduced crude steel output total production volumes of steel products increased by 2% mostly due to greater use of purchased third parties slabs.

·; Coking coal production increased by 20% and steam coal production by 27% compared to Q2 2012 in absence of any longwall repositionings at the coal mines.

·; Prices for most steel product groups reduced due to ongoing uncertainty in global steel markets and decreasing prices of iron ore and coking coal.

·; In EVRAZ's two largest product groups (semi-finished and construction products) average selling prices for semi-finished products in Russia decreased by 13% quarter-on-quarter whilst prices for construction products remained flat.

·; In Q4 2012 we expect to be subject to usual seasonal trends, including slowdown in the construction activity in Russia.

·; EVRAZ continues to expect its net leverage ratio to increase at the end of 2012 versus 30 June 2012 (but within the limits set by our covenants).

·; On 4 October 2012 EVRAZ announced that it had agreed the terms of the acquisition of an indirect controlling interest in the Raspadskaya coking coal company through the purchase of the remaining 50% interest in Corber Enterprises Limited ("Corber"), which it did not previously hold. Corber holds 82% of the share capital of Raspadskaya. As consideration for the acquisition, EVRAZ will (i) issue 132.7 million new shares representing 9.9% of the existing issued share capital of EVRAZ; (ii) issue 33.9 million new warrants to subscribe for 33.9 million new shares representing 2.53% of the existing issued share capital of EVRAZ, and (iii) pay an amount, in cash, of US$1,949.80 for each of 103,600 ordinary Corber shares, payable in four equal instalments in Q1, Q2, Q3 2013 and Q1 2014. Completion of the deal is expected in Q4 2012.

·; In October EVRAZ announced the purchase of two scrap yards in Colorado that will become part of EVRAZ Recycling, a division of EVRAZ North America.

·; In October EVRAZ temporarily shut the steel production at EVRAZ Vitkovice Steel in the Czech Republic due to low demand and to optimise the raw materials inventory.

 

 

STEEL

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Coke (saleable)

367

324

13.4%

429

(14.5)%

Pig iron

3,006

2,865

4.9%

2,889

4.1%

Pig iron (saleable)

67

29

128.5%

27

149.0%

Crude steel

3,909

4,024

(2.9)%

4,035

(3.1)%

Steel products, net of re-rolled volumes*

3,658

3,697

(1.1)%

3,594

1.8%

Semi-finished products **

979

793

23.5%

803

21.9%

Finished products

2,679

2,904

(7.8)%

2,791

(4.0)%

Construction products

1,345

1,351

(0.4)%

1,249

7.7%

Railway products

392

517

(24.2)%

500

(21.6)%

Flat-rolled products

569

609

(6.5)%

648

(12.1)%

Tubular products

219

238

(8.2)%

211

3.5%

Other steel products

153

188

(18.7)%

183

(16.2)%

Note. Numbers in this table and the tables below may not add to totals due to rounding. Percent changes based on numbers prior to rounding.

 

* Total volume of steel products in the tables excludes those re-rolled at other EVRAZ's mills. These volumes are eliminated as intercompany sales for purposes of EVRAZ's consolidated operating results.

** Consolidated production volumes of semi-finished products are preliminary as intra-group re-rolling volumes are yet to be finalised 

 

 

In Q3 2012, EVRAZ's overall production of crude steel decreased by 3% against both Q2 2012 and Q3 2011, mainly due to decreased steel production levels at EVRAZ steel mills in the Czech Republic and South Africa as described below.

 

Production volumes of steel products increased by 2% because more slabs produced in Russia in Q3 2012 were sold to market and therefore included in the total steel volumes, while in Q2 2012 significant volumes of slabs were shipped to North America and Europe for further re-rolling and therefore were excluded from the total steel volumes. This reduction in the intragroup supply of semis was compensated by purchases of third party semis by EVRAZ mills in North America and Europe.

 

The production of semi-finished products increased by 24% compared to Q3 2011 and by 22% compared to Q2 2012. Consolidated production of finished steel goods decreased by 8% compared to the same period last year and by 4% compared to the previous quarter of this year due to lower output of flat-rolled products in Russia and Europe and lower production of rails in Russian and American mills. Finished products accounted for 73% of the consolidated output of steel products, a decrease from 79% in Q3 2011 and 78% in Q2 2012.

 

RUSSIA

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Coke (saleable)

135

128

5.4%

139

(3.1)%

Pig iron

2,695

2,540

6.1%

2,487

8.4%

Pig iron (saleable)

45

18

147.2%

22

101.9%

Crude steel

2,931

2,909

0.7%

2,819

4.0%

Steel products, net of re-rolled volumes

2,721

2,639

3.1%

2,574

5.7%

Semi-finished products

1,122

915

22.6%

949

18.2%

Finished products

1,599

1,724

(7.3)%

1,625

(1.6)%

Construction products

1,127

1,089

3.5%

1,037

8.7%

Railway products

277

396

(30.1)%

366

(24.4)%

Flat-rolled products

74

102

(27.2)%

84

(11.8)%

Other steel products

120

137

(11.9)%

138

(12.5)%

In Q3 2012 pig iron output increased by 6% compared to the same period last year and by 8% compared to Q2 2012 as overall repair downtime at EVRAZ's blast furnaces was shorter in Q3 2012 than in comparable periods. Crude steel production volumes remained flat year-on-year and increased by 4% in Q3 2012 compared to the previous quarter.

 

Production of construction products increased by 4% compared to Q3 2011 and by 9% vs. Q2 2012 reflecting growing demand for long steel products in Russia.

 

As the EVRAZ ZSMK's rail mill has been closed for modernisation since 20 April 2012, production of railway products, mainly rails, decreased by 30% vs. Q3 2011 and by 24% vs. Q2 2012. The modernised rail mill is expected to resume production, as scheduled, in Q4 2012.

 

It is expected that in Q4 2012 crude steel production in Russia will be negatively affected by scheduled repairs of converter No 4 at EVRAZ NTMK and of converter No 4 at EVRAZ ZSMK.

 

The completion of the PCI project at EVRAZ ZSMK has been delayed until Q2 2013 due to revisions in the project design documentation.

 

 

UKRAINE

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Coke (saleable)

232

196

18.6%

290

(20.0)%

Pig iron

227

209

8.3%

239

(4.9)%

Pig iron (saleable)

22

11

98.5%

5

366.9%

Crude steel

208

215

(3.5)%

251

(17.1)%

Steel products

162

186

(13.0)%

215

(24.5)%

Semi-finished products

49

47

3.8%

98

(50.2)%

Finished products

113

139

(18.6)%

117

(2.9)%

Construction products

88

118

(25.1)%

92

(3.8)%

Other steel products

25

22

16.5%

25

0.3%

 

In Q3 2012, crude steel production decreased by almost 4% compared to Q3 2011 and by 17% compared to Q2 2012 due to the scheduled maintenance in the converter shop which began in mid-September and which will continue to the end of October. The maintenance in the converter shop resulted in higher saleable volumes of pig iron compared to Q2 2012 and reduction of production volumes of steel products by 13% and 25% against Q3 2011 and Q2 2012 respectively.

 

Given that the converter shop maintenance is expected to continue until the end of October, steel production is expected to decrease by approximately 17% in Q4 2012 compared to Q3 2012.

 

 

NORTH AMERICA

 

Product, '000 tonnes

 

Q3 2012*

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Crude steel

611

599

2.1%

616

(0.8)%

Steel products, net of re-rolled volumes

664

675

(1.6)%

678

(2.1)%

Construction products

78

81

(3.4)%

79

(1.9)%

Railway products

115

121

(4.7)%

134

(13.9)%

Flat-rolled products

252

236

7.1%

254

(0.5)%

Tubular products

219

238

(8.2)%

211

3.5%

 

* Q3 2012 production volumes are preliminary

 

In Q3 2012, EVRAZ's North American steel output remained flat as our North American steel mills have continued to operate at high utilisation levels.

 

Rail production decreased by 14% compared to Q2 2012 due to scheduled annual maintenance at the Pueblo rail mill in September 2012. It decreased by 5% year-on-year, because, besides the regular maintenance of the rail mill in September 2011, crude steel production at EVRAZ Pueblo is limited and in Q3 2011 available crude steel volumes were shifted to production of construction products from rail production.

 

Production of tubular goods decreased by 8% compared to the same period last year as a result of a market slowdown leading in particular to temporary idling of the Camrose DSAW mill. Spiral weld pipe production was lower vs Q3 2011mainly due to a switch from 36 inch to 30 inch pipe in 2012 that resulted in a 9,000 tonnes decrease in production volumes. In Q3 2012 tubular goods production grew up 4% against the Q2 2012 volumes that were impacted by a Canadian National railroad strike and a labour dispute in Camrose in May 2012.

 

In Q4 2012 the rail mill is expected to be fully utilised as rail demand remains strong. Flat-rolled production is expected to grow slightly vs Q3 2012. Spiral pipe capacity in Canada is expected to be fully utilised under existing contracts. Overall demand for OCTG drilling activity remains stable with some slight signs of temporary weakness, while the seamless market is expected to remain solid in the near term.

 

 

EUROPE

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Crude steel

81

181

(55.1)%

197

(58.6)%

Steel products

237

270

(12.4)%

267

(11.3)%

Construction products

26

32

(19.5)%

0

n/a

Flat-rolled products

207

216

(4.1)%

243

(14.7)%

Other steel products

4

22

(83.8)%

23

(84.7)%

 

Production of crude steel at EVRAZ Vitkovice Steel (EVS) in Q3 2012 decreased by 55% compared to Q3 2011 and by 59% compared to Q2 2012 as the steel plant did not operate in July-August 2012 due to scheduled yearly maintenance. Meanwhile, production of steel products decreased by only 12% and 11% respectively as the plate mill used purchased slabs for its operations.

 

Production of flat-rolled products decreased by 4% vs. Q3 2011 and by 15% vs. Q2 2012 in response to weakening plate demand in the European markets, as well as a two week scheduled maintenance of the plate mills in the Czech Republic and Italy in August 2012.

 

The EVS heavy section mill, which was temporarily closed in February due to weak demand in Europe, resumed operations in July as a result of margin and price improvement.

 

On 11 October the crude steel production at EVRAZ Vitkovice Steel was temporarily closed due to low demand and the company's plan to reduce its inventory. The rolling mill and heavy section mills will remain open as the company has open orders through the end of 2012.

 

Q4 2012 crude steel production plans will be driven by market demand.

 

 

SOUTH AFRICA

 

Product, '000 tonnes

 

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Pig iron

84

116

(27.1)%

163

(48.3)%

Crude steel

78

120

(35.3)%

153

(49.3)%

Steel products

65

111

(40.9)%

124

(47.3)%

Semi-finished products

0

16

n/a

3

n/a

Finished products

65

95

(31.1)%

121

(46.1)%

Construction products

27

32

(17.4)%

41

(34.8)%

Flat-rolled products

35

55

(36.5)%

66

(47.5)%

Other steel products

4

8

(49.9)%

14

(72.4)%

 

In Q3 2012 production of crude steel and steel products at EVRAZ Highveld Steel and Vanadium decreased compared to last year and to the previous quarter as a result of a four-week industrial action initiated by Highveld's largest union NUMSA. An agreement has been reached between EVRAZ Highveld and NUMSA, and the steelworks re-commenced operations on 13 August 2012.

 

It is expected that the steelworks will return to full production in October and the output of crude steel and steel products will increase compared to Q3 2012.

 

 

MINING

 

IRON ORE

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Iron ore products

5,158

5,436

(5.1)%

5,258

(1.9)%

Lumpy ore (Ukraine)

559

724

(22.8)%

735

(23.9)%

Concentrate, saleable (Russia)

1,569

1,734

(9.5)%

1,427

9.9%

Sinter (Russia)

1,128

1,009

11.8%

1,130

(0.1)%

Pellets (Russia)

1,397

1,465

(4.7)%

1,528

(8.6)%

Fines ore (South Africa)

153

186

(18.0)%

132

15.8%

Lumpy ore (South Africa)

352

317

11.1%

307

14.7%

 

Overall production of saleable iron ore products by the Company decreased by 5% compared to Q3 2011 and was flat compared to Q2 2012.

 

Sukha Balka produced 23% and 24% less lumpy ore compared to Q3 2011 and Q2 2012 respectively due to production being scaled down as a result of a skip conveyor repositioning at the Yubileynaya mine that started in mid-September and is expected to continue until mid-November. Production of lumpy ore is expected to remain almost flat in Q4 2012 compared to Q3 2012.

 

Production of saleable concentrate in Russia increased by 10% in Q3 2012 compared to the previous quarter as a result of higher iron ore production. Pellets production decreased by 5% compared to Q3 2011 and by 9% compared to Q2 2012 due to kiln repair at EVRAZ KGOK iron ore processing plant.

 

COAL

 

Product, '000 tonnes

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Raw coking coal (mined)

2,313

1,237

86.9%

1,935

19.5%

Raw steam coal (mined)

892

889

0.3%

700

27.3%

Coking coal concentrate (production)

1,627

1,391

17.0%

1,575

3.3%

Steam coal concentrate (production)

132

338

(61.0)%

190

(30.7)%

Equity investments - Raspadskaya*

Coking coal (mined)

1,378

1,212

13.7%

1,843

(25.3)%

 

* Reported numbers are for 100% production. As at 30 September 2012 EVRAZ held a 41% effective interest in the Raspadskaya coal company.

 

Coking coal

 

In Q3 2012, raw coking coal production at Yuzhkuzbassugol increased by 87% compared to Q3 2011 and by 20% compared to Q2 2012 due to the absence of longwall repositionings at the mines in Q3 2012. The growth of raw coking coal production led to bigger production volumes of coking coal concentrate.

 

Q4 2012 coking coal production is expected to decrease, largely driven by a 60-day longwall repositioning at the Osinnikovskaya mine.

 

 

Steam coal

 

Production of raw steam coal remained unchanged compared to the same period last year and increased by 27% vs. Q2 2012 due to the loss of a month's production volumes at the Gramoteinskaya mine in April-May as a result of a fire at the mine. Steam coal concentrate production decreased by 61% vs. Q3 2011 and by 31% vs. Q2 2012 due to larger raw coal sales.

 

Q4 2012 steam coal production is expected to be flat, quarter-on-quarter.

 

 

 

VANADIUM

 

Product, tonnes of V*

 

Q3 2012

 

Q3 2011

 

Q3 2012/ Q3 2011, change

Q2 2012

 

Q3 2012/ Q2 2012, change

Vanadium in slag (gross production)

4,528

4,804

(5.7)%

5,343

(15.2)%

Russia

3,618

3,201

13.0%

3,683

(1.8)%

South Africa

911

1,603

(43.2)%

1,660

(45.1)%

Vanadium in final products (saleable)

Ferrovanadium

3,297

4,317

(23.6)%

3,769

(12.5)%

Produced at own facilities

1,671

1,535

8.9%

1,899

(12.0)%

Processed at 3rd parties' facilities

1,626

2,782

(41.6)%

1,871

(13.1)%

Nitrovan®

782

819

(4.6)%

763

2.4%

Oxides, vanadium aluminium and chemicals

443

302

46.9%

329

34.5%

 

* Calculated in pure vanadium equivalent.

 

In Q3 2012, EVRAZ's total production of primary vanadium (vanadium slag) decreased by 6% compared to Q3 2011 and by 15% compared to Q2 2012, negatively affected by the four-week union industrial action at EVRAZ Highveld Steel and Vanadium.

 

Production of ferrovanadium decreased by 24% compared to Q3 2011 and by 13% compared to Q2 2012 due to the scheduled maintenance at EVRAZ Nikom plant in the Czech Republic and reduced raw materials (slag) availability as a result of the industrial action at EVRAZ Highveld.

AVERAGE SELLING PRICES

 

USD/tonne (ex works) unless otherwise stated

Q3 2012

Q2 2012

Q3 2011

Steel products

Russia

Coke

189

201

222

Pig iron

340

465

494

Steel products

Semi-finished products

443

510

537

Construction products

680

683

761

Railway products

908

909

914

Flat-rolled products

577

628

707

Other steel products

714

728

833

Ukraine

Coke

201

222

311

Pig iron

349

465

498

Steel products

Semi-finished products

505

547

623

Construction products

634

660

706

Other steel products

883

924

1,103

Europe

Steel products

Construction products

877

n/a

906

Flat-rolled products

715

775

942

North America

Steel products

Construction products

804

890

944

Railway products

933

1,031

1,040

Flat-rolled products

986

1,086

1,188

Tubular products

1,486

1,566

1,540

South Africa

Steel products

Semi-finished products

742

465

642

Construction products

712

673

838

Flat-rolled products

740

738

926

Other steel products

615

673

961

Mining products

Iron ore

Lumpy ore (Ukraine)

61

67

84

Concentrate, saleable (Russia)

82

94

115

Sinter (Russia)

89

98

121

Pellets (Russia)

95

94

133

Fines ore (South Africa)

9

16

22

Coal

Raw coking coal

65

79

104

Raw steam coal

27

30

37

Coking coal concentrate

129

135

224

Steam coal concentrate

59

55

85

Vanadium products (USD/t of V)

Vanadium in final products

Ferrovanadium

24,527

25,405

27,811

Nitrovan®

28,615

29,815

30,333

Oxides, vanadium aluminium and chemicals

30,944

34,524

34,635

 

Notes:

Semi-finished products include slabs, billets, pipe blanks and other semi-finished products.

Construction products include beams, channels, angles, rebars, wire rods, wire, and other construction products.

Railway products include rails, wheels, tyres and other railway products.

Flat-rolled products include commodity plate, specialty plate and other flat products.

Tubular products include large diameter line pipes, ERW pipes and casings, seamless pipes and other tubular products.

Other steel products include rounds, grinding balls, mine uprights, strips etc. For Ukraine they also include railway products, for Europe - slabs and cut shapes; for South Africa - rails.

 

###

 

 

For further information:

 

Investor Relations:London: +44 207 832 8990 Moscow: +7 495 232 1370

ir@evraz.com

 

Media Relations:Oleg KuzminVP, Corporate CommunicationsLondon: +44 207 832 8998 Moscow: +7 495 937 6871media@evraz.com

 

 

EVRAZ is a vertically integrated steel, mining and vanadium business with operations in the Russian Federation, Ukraine, USA, Canada, Czech Republic, Italy and South Africa. EVRAZ is among the top 20 steel producers in the world based on crude steel production of 16.8 million tonnes in 2011. In 2011 EVRAZ sold 15.5 million tonnes of steel products. A significant portion of the company's internal consumption of iron ore and coking coal is covered by its mining operations. The company's consolidated revenues for the year ended 31 December 2011 were US$16,400 million and consolidated EBITDA amounted to US$2,898 million. The H1 2012 consolidated revenue was US$7,619 million and the H1 2012 EBITDA was US$1,175 million.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
IMSEASEPFFSAFEF
Date   Source Headline
28th Feb 20237:00 amEQSDISCONTINUATION OF DISCLOSURE VIA PRIMARY INFORMATION PROVIDER
27th Feb 20237:00 amEQSCLARIFICATION ON ANNUAL REPORT AND AUDITED FINANCIAL STATEMENTS FOR 2022
28th Dec 20228:30 amEQSEVRAZ plc announces that the Appointment and the Amendments adopted as part of the Consent Solicitation for its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024 have become effective
28th Dec 20227:30 amEQSEVRAZ plc announces that the Appointment and the Amendments adopted as part of the Consent Solicitation for its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024 have become effective
23rd Dec 20228:30 amEQSEVRAZ plc announces results of the Consent Solicitation for its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024
23rd Dec 20227:30 amEQSEVRAZ plc announces results of the Consent Solicitation for its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024
19th Dec 202212:00 pmEQSEVRAZ plc announces that the Appointment and the Amendments adopted as part of the Consent Solicitation for its outstanding notes due 2023 have become effective
19th Dec 202211:00 amEQSEVRAZ plc announces that the Appointment and the Amendments adopted as part of the Consent Solicitation for its outstanding notes due 2023 have become effective
8th Dec 20229:17 amEQSEVRAZ plc announces results of the Consent Solicitation for its outstanding U.S.$750,000,000 5.375 per cent. notes due 2023
8th Dec 20229:15 amEQSNOTICE OF ADJOURNED MEETING to the holders of outstanding U.S.$700,000,000 5.250 per cent. notes due 2024 issued by the Issuer
8th Dec 20228:17 amEQSEVRAZ plc announces results of the Consent Solicitation for its outstanding U.S.$750,000,000 5.375 per cent. notes due 2023
8th Dec 20228:16 amEQSNOTICE OF ADJOURNED MEETING to the holders of outstanding U.S.$700,000,000 5.250 per cent. notes due 2024 issued by the Issuer
15th Nov 20228:10 amEQSEVRAZ plc announces Consent Solicitation in respect of its outstanding U.S.$750,000,000 5.375 per cent. notes due 2023
15th Nov 20228:10 amEQSEVRAZ plc announces Consent Solicitation in respect of its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024
15th Nov 20227:10 amEQSEVRAZ plc announces Consent Solicitation in respect of its outstanding U.S.$750,000,000 5.375 per cent. notes due 2023
15th Nov 20227:10 amEQSEVRAZ plc announces Consent Solicitation in respect of its outstanding U.S.$700,000,000 5.250 per cent. notes due 2024
9th Nov 20221:45 pmEQSEVRAZ plc: ERNST & YOUNG TERMINATED ITS SERVICES FOR EVRAZ PLC
9th Nov 202212:46 pmEQSEVRAZ plc: ERNST & YOUNG TERMINATED ITS SERVICES FOR EVRAZ PLC
2nd Nov 20222:56 pmEQSEVRAZ plc: SANCTIONS IMPOSED ON MR. ABRAMOV AND MR. FROLOV
2nd Nov 20221:56 pmEQSEVRAZ plc: SANCTIONS IMPOSED ON MR. ABRAMOV AND MR. FROLOV
20th Oct 20227:45 pmEQSEVRAZ plc: EVRAZ SANCTIONED IN NEW ZEALAND
20th Oct 20227:45 pmEQSEVRAZ plc: EVRAZ SANCTIONED IN NEW ZEALAND
14th Oct 20224:35 pmEQSEVRAZ plc: CHANGES IN THE COMPOSITION OF THE BOARD OF DIRECTORS
14th Oct 20224:35 pmEQSEVRAZ plc: CHANGES IN THE COMPOSITION OF THE BOARD OF DIRECTORS
3rd Oct 202212:14 pmEQSEVRAZ plc: CHANGES IN THE COMPOSITION OF THE BOARD OF DIRECTORS
3rd Oct 202212:14 pmEQSEVRAZ plc: CHANGES IN THE COMPOSITION OF THE BOARD OF DIRECTORS
16th Sep 20226:45 pmEQSEVRAZ plc: UPDATE ON PAYMENT OF INTEREST DUE ON EUROBONDS ISSUED BY EVRAZ PLC
16th Sep 20226:45 pmEQSEVRAZ plc: UPDATE ON PAYMENT OF INTEREST DUE ON EUROBONDS ISSUED BY EVRAZ PLC
16th Sep 202210:24 amEQSEVRAZ plc: Changes in the composition of the Board of Directors
16th Sep 202210:24 amEQSEVRAZ plc: Changes in the composition of the Board of Directors
10th Aug 20224:00 pmEQSEVRAZ is launching soliciting of proposals for its North American subsidiaries acquisition
10th Aug 20224:00 pmEQSEVRAZ is launching soliciting of proposals for its North American subsidiaries acquisition
4th Aug 20227:39 amEQSEVRAZ plc: UNAUDITED INTERIM FINANCIAL RESULTS FOR H1 2022U
4th Aug 20227:37 amEQSEVRAZ plc: UNAUDITED INTERIM FINANCIAL RESULTS FOR H1 2022U
2nd Aug 20228:00 amEQSEVRAZ plc: NOTICE OF H1 2022 RESULTS AND CONFERENCE CALL DETAILS
2nd Aug 20228:00 amEQSEVRAZ plc: NOTICE OF H1 2022 RESULTS AND CONFERENCE CALL DETAILS
28th Jul 20222:33 pmEQSEVRAZ plc: Important notice to noteholders
28th Jul 20222:32 pmEQSEVRAZ plc: Important notice to noteholders
25th Jul 20224:22 pmEQSEVRAZ plc: SPECIAL LICENCE FOR EUROBONDS COUPON PAYMENTS REQUESTED
25th Jul 20224:22 pmEQSEVRAZ plc: SPECIAL LICENCE FOR EUROBONDS COUPON PAYMENTS REQUESTED
21st Jul 20226:15 pmEQSEVRAZ plc: Response to press speculations
21st Jul 20226:15 pmEQSEVRAZ plc: Response to press speculations
18th Jul 20228:39 amEQSEVRAZ plc: Termination of the registry and associated services
18th Jul 20228:38 amEQSEVRAZ plc: Termination of the registry and associated services
30th Jun 20221:55 pmEQSEVRAZ plc: Results of the Annual General Meeting
30th Jun 20221:55 pmEQSEVRAZ plc: Results of the Annual General Meeting
28th Jun 20223:45 pmEQSEVRAZ plc publishes its Modern Slavery Act Transparency Statement for 2021
28th Jun 20223:45 pmEQSEVRAZ plc publishes its Modern Slavery Act Transparency Statement for 2021
17th Jun 20226:57 pmEQSEVRAZ plc: EVRAZ HAS RECEIVED A SPECIAL LICENCE FROM OFSI FOR AGM2022
17th Jun 20226:57 pmEQSEVRAZ plc: EVRAZ HAS RECEIVED A SPECIAL LICENCE FROM OFSI FOR AGM2022

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.