Updated Financial Model

21 Sep 2016 07:00

RNS Number : 3695K
Edenville Energy PLC
21 September 2016
 

21 September 2016

 

 

 

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

Updated Financial Model

 

 

 

Edenville Enegy plc, the Company developing an integrated coal to power project in western Tanzania, would like to provide an update on the status of the financial modelling work for the project.

 

A newly constructed financial model (the "Financial Model") for the Company's Rukwa Coal to Power Project has been completed by Diamond Energy Ltd, an independent power modelling consultant, commissioned by the Company. Diamond Energy Ltd, specialise in building and reviewing valuation models for energy assets, and assisting clients with negotiation of commercial contracts supporting independent electricity projects. 

 

 

Key Points

 

· Newly developed independent 2016 Financial Model constructed by Diamond Energy Ltd

 

· 2015 Power Plant Feasibility Study financial model independently validated with new model results

 

· Improved NPV (using a nominal pre tax discount rate of 10%) of US$252 million for a 120MW power plant with a 30 year life

 

· Pre Tax Project nominal IRR 23.4%

 

 

Rufus Short CEO of Edenville Energy plc said: "I am extremely pleased with the completion of the new independent financial model for our Rukwa Coal to Power Project. We now have both an additional level of assurance to what has been done previously, and going forward, will be able to use a fully independently constructed model, structured for international project finance and so preferable for funding negotiations. In addition, we are currently in the process of completing significant work flow including an updated mining assessment; bulk sampling of the deposit and detailed coal wash plant requirements. These will feed into the overall financial analysis of the project over the coming weeks and months."

 

This new Financial Model further builds upon and validates the results and integrity of the financial model constructed from the results of the 2015 Power Plant Feasibility Study carried out by Lahmeyer India.

 

Positive and comparable results were obtained in the new Financial Model compared to the 2015 model with an increase of approximately 14% in pre-tax NPV, reflective of improved time granularity of cashflow modelling, pass through indexation and revised capital cost phasing.

 

For clarity, the 2015 model returned a pre-tax NPV(10%) of US$220 million with an IRR of 23.1% over a 30 year project life for an integrated 120MW coal to power project at the Company's Rukwa site. The newly constructed Financial Model using essentially the same cost inputs returns an improved pre-tax NPV(10%) of US$252 million demonstrating an IRR of 23.4% over the same time period of 30 years. The size of power plant in both models was set at 120MW with a plant utilisation of 80%.

 

 

Modelling Comparisons

 

 

2015 model

2016 Financial Model

Plant size

120 MW

120 MW

Utilisation

80%

80%

NPV (10%)

US$220 million

US$252 million

Project IRR

23.1%

23.4%

Period

30 years

30 years

 

Additionally, the work currently being completed by independent mining consultants, SMS, on evaluation of the mineable resource, will allow the potential for a larger power plant to be more fully assessed.

 

The Financial Model gives the Company an additional level of confidence on both the integrity of the work originally carried out in 2015 and the underlying modelling methodology.

 

We are extremely pleased that the original 2015 model has been independently verified through this latest work. Running essentially the same inputs though the new Financial Model indicates the structure of our original modelling was conservative. The new Financial Model has been independently constructed from first principles and provides a basis to engage in detailed discussions with relevant institutions for project financing and development.

 

The Company along with its consultants is progressively updating various inputs and parameters for the project as feasibility work and other required tasks continue to be progressed and completed. We will continue to update the model and as appropriate will inform our shareholders accordingly of material changes.

 

Note: The Financial Model, which will be further developed as inputs and parameters are optimised, has been constructed and reviewed independently and undergone in-house review as part of the feasibility process.

 

The Financial Model is indicative and based on the best available data and estimates at the time. As technical and commercial work progresses the Financial Model will be further assessed and refined, both by the Company and by external consultants. Accordingly the valuation metrics set out in this announcement should not be taken as a financial forecast or definitively relied upon for economic assessment purposes.

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.

 

For further information please contact:

 

 

 

Edenville Energy Plc

Jeff Malaihollo - Chairman

Rufus Short - CEO

+44 (0) 20 7652 9788

 

Northland Capital Partners Limited

(Nominated Adviser)

Gerry Beaney

David Hignell

 

 

+44 (0) 20 3861 6625

 

Optiva Securities Limited

(Broker)

Jeremy King

Graeme Dickson

 

 

+44 (0) 20 3137 1902

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Heather Armstrong

+44 (0) 20 3053 8671

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEWFISFMSELU
Date   Source Headline
26th Nov 20137:00 amRNSEdenville Energy Strategy Update
22nd Oct 201311:49 amRNSGrant of Options
26th Sep 20138:43 amRNSHolding(s) in Company
24th Sep 20139:20 amRNSHolding(s) in Company
20th Sep 20137:01 amRNSHalf Yearly Report
20th Sep 20137:00 amRNSDirectorate Change
17th Sep 20138:00 amRNSDraw Down of Funds & Issue of Equity for drawdown
11th Sep 20137:00 amRNSEngagement of RAFCOGROUP & EIA Update
9th Sep 20137:00 amRNSRukwa Coal Project Scoping Study Results
30th May 201311:40 amRNSResult of AGM
7th May 20137:00 amRNSFinal Results
29th Apr 20138:57 amRNSHolding(s) in Company
22nd Apr 20138:23 amRNSDraw Down of Funds and Issue of Equity
22nd Apr 20137:00 amRNSOperational update
28th Mar 201311:51 amRNSHolding(s) in Company
27th Mar 20137:00 amRNS£5 million Financing Facility Agreed
26th Mar 20137:00 amRNSUpdated mineral resource estimate
19th Mar 20132:40 pmRNSHolding(s) in Company
7th Mar 20133:34 pmRNSHolding(s) in Company
5th Mar 20137:00 amRNSDirectorate Change
18th Feb 20137:00 amRNSAppointment of Non-Executive Director
13th Feb 20134:04 pmRNSHolding(s) in Company
21st Jan 20134:45 pmRNSHolding(s) in Company
15th Jan 201312:33 pmRNSHolding(s) in Company
10th Jan 20137:00 amRNSPositive drill results from the Muze deposit
27th Dec 20124:11 pmRNSHolding(s) in Company
26th Nov 20121:59 pmRNSHolding(s) in Company
21st Nov 20122:00 pmRNSHolding(s) in Company
16th Nov 20122:46 pmRNSExercise of Warrants
29th Oct 201212:04 pmRNSHolding(s) in Company
16th Oct 20124:01 pmRNSHolding(s) in Company
10th Oct 20129:08 amRNSHolding(s) in Company
8th Oct 20127:00 amRNSMkomolo Drill Results
2nd Oct 20127:00 amRNSChange of Adviser
19th Sep 20123:45 pmRNSHolding(s) in Company
17th Sep 20124:53 pmRNSHalf Yearly Report
28th Aug 20127:00 amRNSPositive Drill Results from the Rukwa Coal Project
20th Aug 20127:00 amRNSOption Exercised on Rukwa Coalfield Project
17th Aug 20124:53 pmRNSHolding(s) in Company
13th Aug 20129:45 amRNSInitial Mkomolo 2012 Drill Results
31st Jul 20127:00 amRNSRukwa Coalfield Update
12th Jul 20125:19 pmRNSHolding(s) in Company
4th Jul 201210:55 amRNSHolding(s) in Company
3rd Jul 20123:49 pmRNSHolding(s) in Company
3rd Jul 20127:00 amRNSNamwele Drilling Results
2nd Jul 20121:59 pmRNSHolding(s) in Company
27th Jun 20125:30 pmRNSHolding(s) in Company
27th Jun 201212:13 pmRNSResult of AGM
19th Jun 20122:30 pmRNSHolding(s) in Company
18th Jun 20123:57 pmRNSMuze Project Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.