DiamondCorp plcJSE share code: DMCAIM share code: DCPISIN: GB00B183ZC46(Incorporated in England and Wales)(Registration number 05400982)(SA company registration number 2007/031444/10)('DiamondCorp' or 'the Company')

 

 

OPERATIONS UPDATE

 

DiamondCorp plc, the African diamond mine development and exploration company, is pleased to provide an update on activities at the Lace mine in South Africa and kimberlite exploration in Botswana.

 

LACE MINE

 

The Company advises that SA Diamond Exchange has undertaken a revaluation of the 2,168 carats recovered from the bulk test at the Lace Mine last year and estimated a price of $172 per carat in the current market. This represents an 7.5 per cent increase from the $160 per carat valuation of the first 1,850 carats from the bulk test announced last October.

 

The increase in value is a reflection of slightly better overall diamond quality in the final 318 carats, as well as a moderate firming of prices for Lace diamonds since the market correction in September 2011.

 

In light of the prices for Lace diamonds, tailings retreatment has recommenced on an initial single shift basis. This will be monitored over the next 60 days to confirm that an increase to two shifts will generate a positive contribution to cashflow.

 

In the meantime, SRK Consulting is on track this month to complete the Independent Engineering Report on the 47 level block cave proposed for the Lace mine. The SRK report is required to progress negotiations with several potential project finance providers looking to finance the underground development which is designed to mine 1.2 million tonnes of kimberlite and produce up to 500,000 carats of diamonds per annum.

 

Construction of a new heavy equipment maintenance and rebuild workshop has been completed and major rebuilds of the Lace mine underground mining fleet have started in readiness for rapid re-commencement of underground development once project finance is secured.

 

DiamondCorp is pleased to report the current group cash balance is approximately £2 million with no debt, allowing project financing negotiations to be undertaken in a considered manner.

 

BOTSWANA KIMBERLITE EXPLORATION

 

Preliminary results of kimberlite samples recovered from the five large diameter (455mm) drill (LDD) holes undertaken on kimberlite J-01 are now available.

 

The samples totalling 388.34 tonnes were processed through a modified circuit on the 65tph dense media separation plant at the company's Lace Mine in South Africa. The circuit was modified specifically to treat the LDD samples from Jwaneng. Each borehole was treated as a separate sample with the plant being purged between samples. Each sample was spiked with tracers to monitor plant performance. All tracers were recovered.

 

A total of two macro diamonds (diamonds larger than 0.5mm in size) totalling 0.114 carats have been recovered to date.

 

In light of the low recovered grades from both J-01 and the previously low recoveries announced from J-05, DiamondCorp has decided not to proceed with further exploration on this property and will hand all rights back to the tenement holder Geoperspectives (Pty) Limited.

 

Commenting on the results, DiamondCorp's managing director Paul Loudon said: "Despite being located near to the richest diamond mine in the world and the encouraging mineral chemistry displayed by these kimberlites, mini bulk tests suggest they do not contain macrodiamond grades sufficient to support a large-scale commercial diamond mine.

 

Management remain in active discussion with numerous parties regarding additional kimberlite projects in Botswana and other diamondiferous regions of southern Africa."

 

 

London

 

10 February 2012

 

The Competent Person responsible for the technical information contained in this announcement is Mr Paul Zweistra (Pr. Sci. Nat., Registration number 400016/93) a full-time employee of VP3. VP3 and Mr Zweistra have given their permission for their work to be quoted in this announcement and have reviewed the information contained herein.

 

 

AIM Nomad: Fairfax I.S. plc

 

AIM Brokers: Fairfax I.S. plc, Ocean Equities LtdJSE Sponsor: PSG Capital (Pty) LimitedDiamondCorp plc, Paul Loudon +44 20 3151 0970/+27 56 212 2308Ewan Leggat/Laura Littley, Fairfax I.S. plc +44 207 598 5368Guy Wilkes, Ocean Equities Limited +44 207 786 4370John-Paul Dicks, PSG Capital (Pty) Limited +27 21 887 9602Charmane Russell/Marion Brower, Russell & Associates +27 11 880 3924

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBKKDPCBKKFBD
Date   Source Headline
19th Oct 20163:20 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20161:57 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20167:13 amRNSForm 8.3 - Diamondcorp Plc
18th Oct 20162:40 pmRNSForm 8.3 - DiamondCorp Plc
18th Oct 201612:59 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 201612:17 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 20167:00 amRNSSTRATEGIC REVIEW
18th Oct 20167:00 amRNSMining Resumes at the Lace Diamond Mine
14th Oct 20167:00 amRNSFunding Update
13th Oct 201610:10 amRNSOPERATIONAL AND FINANCIAL UPDATE
12th Oct 20167:00 amRNSProject and Financial Update
20th Sep 201612:45 pmRNSUpdate on Diamond Sales from the Lace Diamond Mine
13th Sep 20167:00 amRNSInterim Results and Operational Update
9th Aug 20167:00 amRNSLace Diamond Mine Operational Update
26th Jul 20163:00 pmRNSLACE DIAMOND MINE UNDERGROUND MINING RESUMES
18th Jul 20167:00 amRNSLace Diamond Mine
14th Jul 20167:00 amRNSDirector/PDMR Shareholding & Amendment
12th Jul 20167:00 amRNSExercise of Broker Option and Directors' Dealings
7th Jul 20169:59 amRNSPlacing and Subscription & Broker Option
16th Jun 20167:50 amRNSResult of AGM
14th Jun 20167:00 amRNSLace Diamond Mine - Diamond Sales & Project Update
19th May 20167:00 amRNSAnnual Financial Report
4th May 20167:00 amRNSFinal Results
19th Apr 20167:00 amRNSPolished Diamond Sales and Project Update
5th Apr 20167:00 amRNSLace Diamond Mine - March Quarter Update
2nd Mar 20167:00 amRNSResource Statement
1st Feb 20167:00 amRNSDirectorate Change
26th Jan 20167:00 amRNSLace Diamond Mine Project Update
7th Jan 20161:30 pmRNSResult of General Meeting
23rd Dec 20157:00 amRNSPosting of Circular
22nd Dec 20157:00 amRNSAdditional Listing
16th Dec 20157:00 amRNSLace Mine Ramp Up Commences From Uk4 Block
3rd Dec 20154:20 pmRNSResults of Placing and Directors' Dealings
3rd Dec 20157:00 amRNSIDC Loan & £4m Proposed Placing
2nd Dec 20154:37 pmRNSIDC Loan & £4m Proposed Placing
20th Nov 20157:00 amRNSLace Mine - 290M Level Development Resumes
12th Nov 20157:00 amRNSConveyor Belt Commissioned
3rd Nov 20157:00 amRNSLace Diamond Mine Project Update
13th Oct 20157:00 amRNSConveyor Belt Installation Diamond Sales Valuation
1st Sep 20157:03 amRNSInterim Results
31st Jul 20157:00 amRNSLace Diamond Mine Project Update
9th Jul 20151:00 pmRNSDirector/PDMR Shareholding
6th Jul 20157:00 amRNSResult of Open Offer
26th Jun 20157:00 amRNSResult of AGM
17th Jun 20157:00 amRNSOpen Offer
5th Jun 20157:00 amRNSPlacing and Subscription to raise £3.18 million
3rd Jun 20157:44 amRNSAnnual Financial Report
26th May 20158:14 amRNSFinal Results
15th May 20157:00 amRNSChange of Registered Office
14th May 20158:30 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.