Operational Update

7 Sep 2011 07:00

RNS Number : 7266N
Diamondcorp Plc
07 September 2011
 



DiamondCorp plcJSE share code: DMCAIM share code: DCPISIN: GB00B183ZC46(Incorporated in England and Wales)(Registration number 05400982)(SA company registration number 2007/031444/10)('DiamondCorp' or 'the Company')

 

 

OPERATIONAL UPDATE

 

DiamondCorp plc, the African diamond mine development and exploration company, is pleased to provide an update of kimberlite bulk testing at the Lace mine in South Africa and drilling at Jwaneng South in Botswana.

 

LACE MINE, SOUTH AFRICA

 

- Mining continues in a northeast direction across the pipe and has now entered less diluted kimberlite, with the latest sub-sample of 1,553 tonnes returning grades of up to 22 carats per hundred tonnes ("cpht").

 

- To date, a total of 11,091 tonnes of volcaniclastic kimberlite has been sampled from between the 25 and 26 levels on the southern and western sides of the main Lace pipe. Much of the kimberlite in these zones is heavily diluted with up to 75% country rock (waste) inclusions.

 

- From the total kimberlite processed to date, 1,235 carats of diamonds have been extracted, with the biggest stone being a 16.08 carat non-gem diamond.

 

- The diamond quality remains consistent with the initial parcel which was valued last month by the SA Diamond Exchange at an average of $205 per carat.

 

- Approximately 40% of the diamonds are larger than one-third of a carat, and more than 80% of the diamonds are gem quality.

 

- The results of the bulk test will determine both the carat value of the Lace diamonds and the grade of kimberlite zones to be mined. These results will allow finalisation of the mine plan for the first mining block between the 26 level and the 29 level.

 

- The average recovered grade of 'diluted contact kimberlite material' processed to date is 11.90 cpht. This should not be considered indicative of either the whole pipe at this level or the grade of the kimberlite which will be incorporated into the mining plan.

 

- Sampling started in what historically was described as the "stony ground" side of the pipe, where waste inclusions dilute the grade. Mining is moving progressively northeast across the pipe into the zone where historically the best recoveries (higher grades) were reported.

 

- The pipe is being sampled in this manner so that development drives put in place for sampling can be used for full-scale mining in a sequence which allows the expected highest grade kimberlite in the northeast of the pipe to be mined first, and then progressively mine in a retreat manner to the lower grade southwest side.

 

- The tonnage processed to date represents approximately 37% of the total tonnage from the planned bulk test of 30,000 tonnes and less than 33% of the total area of the pipe to be sampled.

 

- The Lace processing plant continues to operate efficiently and no damage to any diamonds recovered to date has been identified.

 

- The sampling rate continues to be slower than originally planned to ensure mining takes place in as safe a manner as possible.

 

Commenting on the activities, DiamondCorp CEO, Paul Loudon said: 'We continue to be pleased with the results from the sampling, and look forward to reporting the results from the higher grade zones being sampled in the coming weeks.'

 

JWANENG SOUTH PROJECT, BOTSWANA

 

DiamondCorp is pleased to announce an update on exploration activities in Prospecting Licence PL/71 covering the Jwaneng South Joint Venture Area in Botswana.

 

Drilling contracts have been let for both additional core drilling and large diameter drilling on kimberlites J-01 and J-05. Site establishment and mobilisation of the drilling rigs is under way and drilling is expected to commence within the next week.

 

The objective of the programme is to obtain a better understanding of the geometry and geology and return a preliminary diamond grade of both kimberlites by the end of the year.

 

The J-01 kimberlite has an approximate geophysically defined area of 10ha and J-05 is approximately 1.5ha in size. The project area lies between 5km and 10km south of Debswana's Jwaneng mine, the richest diamond mine in the world measured by value.

 

DiamondCorp is earning a 77.5 per cent interest in PL/71 from Botswana company Geoperspectives (Pty) Limited by funding exploration activities.

 

London

 

7 September 2011

 

The Competent Person responsible for the technical information contained in this announcement is Mr Paul Zweistra (Pr. Sci. Nat., Registration number 400016/93) a full-time employee of VP3 Geoservices (Pty) Ltd. VP3 and Mr Zweistra have revieved the information contained herein and approved the contents of this press release.

 

 

AIM Nomad: Fairfax I.S. plc

 

AIM Brokers: Fairfax I.S. plc, Ocean Equities LtdJSE Sponsor: PSG Capital (Pty) Limited

DiamondCorp plc

Paul Loudon

+44 20 3151 0970 / +27 56 212 2308

Fairfax I.S. PLC

Ewan Leggat

+44 207 598 5368

Ocean Equities Limited

Guy Wilkes

+44 207 786 4370

PSG Capital (Pty) Limited

John-Paul Dicks

+27 21 887 9602

Russell & Associates

Charmane Russell/Marion Brower

+27 11 880 3924

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSSFFLMFFSEEU
Date   Source Headline
19th Oct 20163:20 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20161:57 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20167:13 amRNSForm 8.3 - Diamondcorp Plc
18th Oct 20162:40 pmRNSForm 8.3 - DiamondCorp Plc
18th Oct 201612:59 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 201612:17 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 20167:00 amRNSSTRATEGIC REVIEW
18th Oct 20167:00 amRNSMining Resumes at the Lace Diamond Mine
14th Oct 20167:00 amRNSFunding Update
13th Oct 201610:10 amRNSOPERATIONAL AND FINANCIAL UPDATE
12th Oct 20167:00 amRNSProject and Financial Update
20th Sep 201612:45 pmRNSUpdate on Diamond Sales from the Lace Diamond Mine
13th Sep 20167:00 amRNSInterim Results and Operational Update
9th Aug 20167:00 amRNSLace Diamond Mine Operational Update
26th Jul 20163:00 pmRNSLACE DIAMOND MINE UNDERGROUND MINING RESUMES
18th Jul 20167:00 amRNSLace Diamond Mine
14th Jul 20167:00 amRNSDirector/PDMR Shareholding & Amendment
12th Jul 20167:00 amRNSExercise of Broker Option and Directors' Dealings
7th Jul 20169:59 amRNSPlacing and Subscription & Broker Option
16th Jun 20167:50 amRNSResult of AGM
14th Jun 20167:00 amRNSLace Diamond Mine - Diamond Sales & Project Update
19th May 20167:00 amRNSAnnual Financial Report
4th May 20167:00 amRNSFinal Results
19th Apr 20167:00 amRNSPolished Diamond Sales and Project Update
5th Apr 20167:00 amRNSLace Diamond Mine - March Quarter Update
2nd Mar 20167:00 amRNSResource Statement
1st Feb 20167:00 amRNSDirectorate Change
26th Jan 20167:00 amRNSLace Diamond Mine Project Update
7th Jan 20161:30 pmRNSResult of General Meeting
23rd Dec 20157:00 amRNSPosting of Circular
22nd Dec 20157:00 amRNSAdditional Listing
16th Dec 20157:00 amRNSLace Mine Ramp Up Commences From Uk4 Block
3rd Dec 20154:20 pmRNSResults of Placing and Directors' Dealings
3rd Dec 20157:00 amRNSIDC Loan & £4m Proposed Placing
2nd Dec 20154:37 pmRNSIDC Loan & £4m Proposed Placing
20th Nov 20157:00 amRNSLace Mine - 290M Level Development Resumes
12th Nov 20157:00 amRNSConveyor Belt Commissioned
3rd Nov 20157:00 amRNSLace Diamond Mine Project Update
13th Oct 20157:00 amRNSConveyor Belt Installation Diamond Sales Valuation
1st Sep 20157:03 amRNSInterim Results
31st Jul 20157:00 amRNSLace Diamond Mine Project Update
9th Jul 20151:00 pmRNSDirector/PDMR Shareholding
6th Jul 20157:00 amRNSResult of Open Offer
26th Jun 20157:00 amRNSResult of AGM
17th Jun 20157:00 amRNSOpen Offer
5th Jun 20157:00 amRNSPlacing and Subscription to raise £3.18 million
3rd Jun 20157:44 amRNSAnnual Financial Report
26th May 20158:14 amRNSFinal Results
15th May 20157:00 amRNSChange of Registered Office
14th May 20158:30 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.