LACE MINE DEVELOPMENT UPDATE

11 Apr 2013 07:00

RNS Number : 0714C
Diamondcorp Plc
11 April 2013
 

11 April 2013 

 

DiamondCorp plc

 

JSE share code: DMC & AIM share code: DCP

ISIN: GB00B183ZC46

(Incorporated in England and Wales)

(Registration number 05400982)

(SA company registration number 2007/031444/10)

 

("DiamondCorp", "the Group" or "the Company")

 

Lace mine development update

 

Highlights

 

·; Second US$3 million tranche of the Tiffany loan received finalising R320 million finance package for the Lace mine development.

·; New boxcut excavation and underground development activities commenced.

·; Additional underground loaders and trucks have been secured and rebuilds underway.

·; Plant upgrade work continues on schedule for tailings re-treatment to restart in the current quarter.

·; Key underground and plant personnel recruited.

·; Underground diamond drill rig ordered and awaiting delivery; bulge definition a priority.

 

DiamondCorp, the Southern African diamond development and exploration company, is pleased to provide the following update on activities relating to the 47 level block cave development at the Lace mine in the Free State province of South Africa.

 

Funding finalised

 

On 10 April 2013, the Company received on schedule the second and final tranche of $3 million (£1.96 million) of loan funds from Laurelton Diamonds, Inc., a wholly-owned subsidiary of Tiffany & Co. The combination of funding through the $6 million Tiffany loan, £4.2 million of convertible bonds (issued in December 2012) and R220 million (£15.6 million) from the Industrial Development Corporation of South Africa (as announced on 21 September 2012) completes the R320 million (£23 million) Lace project financing package.

 

The Main pipe at the Lace mine (DiamondCorp 74% interest) contains 33.1 million tonnes of kimberlite with an indicated and inferred resource to a depth of 855m containing approximately 13.4 million carats at an average grade of 40.1 carats per hundred tonnes. At a carat value of $160 per carat, the resource has an in-ground value in excess of $2.1 billion. The deposit will be mined by block cave mining, with three caves planned over the next 25 years on the 47, 67 and 85 levels (at depths of 470m, 670m and 850m respectively). The kimberlite is open at depth, and also contains a significant bulge between 250m and 360m depth with the potential to add additional tonnage and diamonds not currently included in the resource statement.

 

Development activities February-March 2013

 

In February, the Company commenced excavation of a new 66,000 bank cubic metre (bcm) boxcut which will provide the surface entrance to the twin conveyor belt and services declines for the life of the mine. A total of 23,000 bcm of surface sediments and clay material was excavated to the end of March and the boxcut is expected to be completed on schedule in the current quarter.

 

Underground blasting commenced during March with a vent raise on the 16 level to provide sufficient interim ventilation for continuous blasting of the twin decline development to the 47 level. The raise development is continuing on schedule and is expected be completed in the current quarter. Development also commenced on a tipping arrangement on the 24 level to allow loading of development waste into dump trucks for hauling to surface until such time as the conveyor belts are installed.

 

During the period, the Company completed the rebuild of a 9.5 tonne underground loader and two underground dump trucks in its on-site heavy equipment workshop. Two additional low profile loaders and three additional underground dump trucks were purchased in February, completing the fleet requirements for the underground development. These units will be rebuilt and commissioned during the next two quarters, in line with the planned development programme.

 

Essential upgrades are underway on the mine's 1.2 million tonne per annum dense media separation plant to allow smooth transition from tailings to kimberlite processing, and relieve front-end bottlenecks in the re-crush circuit. These modifications are on schedule and plant re-commissioning is planned during the current quarter, allowing tailings re-treatment activities to recommence.

 

Several key operational personnel were recruited during the period, including a mine overseer with considerable experience in underground kimberlite development and block caving and an experienced diamond processing plant manager. The Company is not experiencing any difficulty in securing personnel with the experience and skills required for the mine development.

 

The Company has prepared a drilling cubby on the 26 level inside the Main pipe and has ordered a new skid mounted underground drilling rig which is being shipped from Australia and is expected to be delivered and commissioned during the next quarter. A total of 2,000m of underground drilling is then planned in the bulge area as well as the 47 level block cave area to better define the kimberlite margins and facies distribution.

 

DiamondCorp's CEO, Paul Loudon said: "We are pleased with the progress achieved with operations in the first quarter and remain on target to commence diamond production from tailings re-treatment in the next three months. This will initially be on a one shift basis while the upgraded processing plant is re-commissioned. We will then have the capacity to ramp up to three shifts in the second half of the year depending on diamond prices."

 

The Company also announces that it will shortly publish an updated corporate presentation on its website.

 

Contact details:

 

DiamondCorp plc

Paul Loudon, Chief Executive

Tel: +44 20 3151 0970

+27 56 212 2930

 

UK Broker & Nomad

Panmure Gordon (UK) Limited

Dominic Morley/Adam James

Tel: +44 20 7886 2500

 

Joint Broker

SP Angel Corporate Finance LLP

Ewan Leggat/Laura Littley

Tel: +44 207 598 5368

 

JSE Sponsor

PSG Capital (Pty) Limited

John-Paul Dicks

Tel: +27 21 887 9602

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSFUFMSFDSEDL
Date   Source Headline
19th Oct 20163:20 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20161:57 pmRNSForm 8.3 - DiamondCorp Plc
19th Oct 20167:13 amRNSForm 8.3 - Diamondcorp Plc
18th Oct 20162:40 pmRNSForm 8.3 - DiamondCorp Plc
18th Oct 201612:59 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 201612:17 pmRNSForm 8.3 - Diamondcorp Plc
18th Oct 20167:00 amRNSSTRATEGIC REVIEW
18th Oct 20167:00 amRNSMining Resumes at the Lace Diamond Mine
14th Oct 20167:00 amRNSFunding Update
13th Oct 201610:10 amRNSOPERATIONAL AND FINANCIAL UPDATE
12th Oct 20167:00 amRNSProject and Financial Update
20th Sep 201612:45 pmRNSUpdate on Diamond Sales from the Lace Diamond Mine
13th Sep 20167:00 amRNSInterim Results and Operational Update
9th Aug 20167:00 amRNSLace Diamond Mine Operational Update
26th Jul 20163:00 pmRNSLACE DIAMOND MINE UNDERGROUND MINING RESUMES
18th Jul 20167:00 amRNSLace Diamond Mine
14th Jul 20167:00 amRNSDirector/PDMR Shareholding & Amendment
12th Jul 20167:00 amRNSExercise of Broker Option and Directors' Dealings
7th Jul 20169:59 amRNSPlacing and Subscription & Broker Option
16th Jun 20167:50 amRNSResult of AGM
14th Jun 20167:00 amRNSLace Diamond Mine - Diamond Sales & Project Update
19th May 20167:00 amRNSAnnual Financial Report
4th May 20167:00 amRNSFinal Results
19th Apr 20167:00 amRNSPolished Diamond Sales and Project Update
5th Apr 20167:00 amRNSLace Diamond Mine - March Quarter Update
2nd Mar 20167:00 amRNSResource Statement
1st Feb 20167:00 amRNSDirectorate Change
26th Jan 20167:00 amRNSLace Diamond Mine Project Update
7th Jan 20161:30 pmRNSResult of General Meeting
23rd Dec 20157:00 amRNSPosting of Circular
22nd Dec 20157:00 amRNSAdditional Listing
16th Dec 20157:00 amRNSLace Mine Ramp Up Commences From Uk4 Block
3rd Dec 20154:20 pmRNSResults of Placing and Directors' Dealings
3rd Dec 20157:00 amRNSIDC Loan & £4m Proposed Placing
2nd Dec 20154:37 pmRNSIDC Loan & £4m Proposed Placing
20th Nov 20157:00 amRNSLace Mine - 290M Level Development Resumes
12th Nov 20157:00 amRNSConveyor Belt Commissioned
3rd Nov 20157:00 amRNSLace Diamond Mine Project Update
13th Oct 20157:00 amRNSConveyor Belt Installation Diamond Sales Valuation
1st Sep 20157:03 amRNSInterim Results
31st Jul 20157:00 amRNSLace Diamond Mine Project Update
9th Jul 20151:00 pmRNSDirector/PDMR Shareholding
6th Jul 20157:00 amRNSResult of Open Offer
26th Jun 20157:00 amRNSResult of AGM
17th Jun 20157:00 amRNSOpen Offer
5th Jun 20157:00 amRNSPlacing and Subscription to raise £3.18 million
3rd Jun 20157:44 amRNSAnnual Financial Report
26th May 20158:14 amRNSFinal Results
15th May 20157:00 amRNSChange of Registered Office
14th May 20158:30 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.