Update on Definitive Feasibility Study

26 Mar 2014 07:00

RNS Number : 1838D
Chaarat Gold Holdings Ltd
26 March 2014
 

Chaarat Gold Holdings Limited

("Chaarat" or the "Company")

 

Update on Definitive Feasibility Study

 

Road Town, Tortola, British Virgin Islands (26th March 2014)

 

Chaarat (AIM - CGH), the AIM quoted exploration and development company with assets in the Kyrgyz Republic, is pleased to provide an progress update on the Definitive Feasibility Study ("DFS") for the Chaarat Project ("the Project").

 

Highlights

· Contractors have been selected to complete all components of the DFS

· Gustavson Associates ("Gustavson") will be project managers for the DFS as well as preparing the geology, mineral resource and mine design sections

· Resource Development Inc ("RDi") appointed as metallurgical consultants

· Golder Associates (UK) Ltd ("Golder") will provide the geotechnical, hydrological and environmental studies

· GBM Minerals Engineering Consultants Limited ("GBM") will undertake the process and infrastructure engineering for the Project as well as the study on logistics

· DFS on schedule for completion by the end of 2014 and on budget

 

Having completed a rigorous and competitive tender process, the team of consultants to deliver the DFS for the Chaarat Project is now in place. The team will work closely with Mac DeGuire, the Director responsible for the DFS, and with Gustavson, who assisted in the tender process.

 

The resource and reserve model is being updated by Gustavson. The drilling programme completed in the 2013 season will be incorporated into the new model, which is aimed at upgrading the JORC resource from inferred to the indicated and measured categories. Gustavson will also undertake the open pit and underground mine planning.

 

RDi has worked with Chaarat since the Prefeasibility Study which was completed in 2011. They have an unrivalled knowledge of the characteristics of the ore at the Chaarat Project and the results of their work will determine the optimal process plant design and estimates of metallurgical recovery for the mine optimisation and economic analyses. GBM will design the appropriate plant for the process and associated infrastructure for the Project.

 

Golder will undertake in depth investigations of the geotechnical and hydrological data collected to date, and commission additional drilling as required, to underpin the parameters for the mine design to be undertaken by Gustavson, the tailings management facility (to be designed by Golder) and the production facility (to be designed by GBM). The Environmental and Social Impact Assessment ("ESIA") will be prepared by Golder to local and International Finance Corporation ("IFC") standards.

 

Dekel Golan, Chief Executive Officer of Chaarat commented: "Mac DeGuire and Gustavson have assembled a highly experienced and professional team to ensure the DFS is of the quality that the Chaarat Deposit merits. The new team members will be visiting site as soon as it opens at the end of April. We will keep the market updated as work on the DFS progresses.

 

I am pleased that a number of projects in the Kyrgyz Republic have shown progress in recent weeks, as a sign of confidence in the country, following the positive progress made in the resolution of differences between the Kyrgyz Government and Centerra concerning the Kumtor mine.

 

We are looking forward to finalising the Chaarat DFS, moving towards permitting, construction and commencing the building of the next major gold mine in central Asia."

 

Enquiries:

 

Chaarat Gold Holdings Limited

+ 44 23 800 11747/+ 44 20 7499 2612

c/o Central Asia Services Limited

info@chaarat.com

Dekel Golan CEO

Linda Naylor FD

 

Numis Securities Limited

+44 (0) 20 7260 1000

John Prior, Stuart Skinner (NOMAD)

James Black (Broker)

 

 

Further information is available at www.chaarat.com

 

NOTES TO EDITORS:

About Chaarat Gold

 

Chaarat Gold is an exploration and development company operating in the Kyrgyz Republic with a large, high grade resource which is capable of generating low cost gold production - the Chaarat Gold Project.

 

The Company's key objective is to become a low cost gold producer targeting annual production of 200,000 ounces from the development of the Chaarat Gold Project. Chaarat is fully funded to complete a Definitive Feasibility Study (DFS) and continue its active community engagement programme to optimise the value of the Chaarat investment proposition.

Chaarat has several other promising prospects also located within the Kyrgyz Republic.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPGUBUWUPCGRA
Date   Source Headline
30th Apr 20187:00 amRNSTulkubash Feasibility Study Results
27th Apr 201811:35 amRNSEXERCISE OF OPTIONS AND ISSUE OF EQUITY
24th Apr 20189:43 amRNSSuspension - Chaarat Gold Holdings Limited
24th Apr 20189:10 amRNSProposed offer for the Kumtor Mine
10th Apr 20187:00 amRNSCorporate Update
3rd Apr 201811:47 amRNSUpdate on funds raised
26th Mar 20183:46 pmRNSAppointment to the Board
13th Mar 20187:00 amRNSHolding(s) in Company
8th Mar 20183:15 pmRNSHolding(s) in Company
8th Mar 20182:17 pmRNSDirector/PDMR Shareholding
28th Feb 20184:36 pmRNSUpdate on funds raised
19th Feb 20187:00 amRNSAppointment of Joint Corporate Broker
14th Feb 20187:00 amRNSAppointment of COO
2nd Feb 201811:53 amRNSIssue of Equity
31st Jan 20187:00 amRNSTulkubash Resource Update
27th Dec 20175:41 pmRNSEXERCISE OF OPTIONS AND ISSUE OF EQUITY
21st Dec 20174:25 pmRNSIssue of Equity
18th Dec 20177:00 amRNSFunds raised to advance the Tulkubash HL Project
5th Dec 20177:00 amRNSEXERCISE OF WARRANTS AND ISSUE OF EQUITY
4th Dec 20177:00 amRNSTULKUBASH PROJECT UPDATE
27th Nov 20177:00 amRNSSUPPORT FOR CHAARAT PROJECT IN COUNTRY RE-AFFIRMED
20th Nov 20177:00 amRNSCOMPLETION OF 2017 DRILLING PROGRAM
13th Nov 20177:00 amRNSAppointments to the Board
10th Nov 20177:00 amRNSAppointment of CFO designate
31st Oct 20179:17 amRNSHolding(s) in Company
27th Oct 20176:14 pmRNSDirector shareholdings
27th Oct 20172:16 pmRNSBoard Changes
19th Oct 201710:03 amRNSDirector/PDMR Shareholding
27th Sep 20177:00 amRNSInterim statement for six months ended 30 Jun 2017
21st Sep 20177:00 amRNSLOCAL PERMITTING ACHIEVED FOR TULKUBASH PROJECT
7th Sep 20177:00 amRNSPositive drilling results at Chaarat Gold Project
27th Jul 20177:00 amRNSDirector/PDMR Shareholding
26th Jul 20177:00 amRNSDirector/PDMR Shareholding
20th Jul 20179:58 amRNSDirector/PDMR Shareholding
17th Jul 20177:05 amRNSDirector/PDMR Shareholding
17th Jul 20177:00 amRNSDirector/PDMR Shareholding
14th Jul 20179:14 amRNSDirector/PDMR Shareholding
14th Jul 20179:12 amRNSDirector/PDMR Shareholding
13th Jul 20179:12 amRNSDirector/PDMR Shareholding
11th Jul 20177:00 amRNSGrant of options and Extension of waiver
10th Jul 20177:00 amRNSBoard and senior management changes
7th Jul 20177:00 amRNSResult of AGM
6th Jul 20177:00 amRNSUpdate on Tulkubash Heap Leach Project
26th Jun 20173:49 pmRNSDirector/PDMR Shareholding
23rd Jun 20179:17 amRNSDirector/PDMR Shareholding
21st Jun 201712:26 pmRNSDirector/PDMR Shareholding
16th Jun 20177:00 amRNSDirector/PDMR Shareholding
15th Jun 20174:57 pmRNSDirector/PDMR Shareholding
14th Jun 20177:00 amRNSDirector/PDMR Shareholding
13th Jun 20177:00 amRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.