Goudron Pad 4 Testing and Infrastructure

17 Jun 2015 07:00

RNS Number : 3689Q
LGO Energy PLC
17 June 2015
 

For Immediate Release, 7 am

17 June 2015

 

LGO ENERGY PLC

("LGO" or the "Company")

 

Goudron Pad 4 Testing

and Infrastructure Update, Trinidad

 

 

LGO today announces its plans for the testing of the three recently drilled wells, GY-672, 673 and 674, on drilling Pad 4 at the Goudron Field, and provides an update on important infrastructure approvals and improvements that are designed to significantly increase oil sales capacity at the field from 2,750 barrels to over 12,000 barrels.

 

Well Testing:

The Company has now received final approval for the completion of all three wells recently drilled from Pad 4 as production wells. A combined total of 556 feet of perforations are planned across the prolific C-sand intervals in the three wells. The equipment required has been mobilised to the field and work is anticipated to start later this week.

 

As previously announced each of the new wells will be flow tested with the appropriate pressure build-up tests carried out over the coming weeks. Each well will be subject to a number of periods of flow testing up to 6 hours duration, followed by individual pressure build-up tests (pressure monitoring without flow) of approximately 24 hours. Once the test phase is complete, which may take up to 5 days per well, a stable flow rate will be selected to best manage the reservoir performance of the well in the short and medium term, and provide further information for the completion of further wells on the field. Oil produced from the wells during the test period will be sold.

 

Infrastructure:

LGO also confirms that it has now received the necessary approvals to construct two 5,000 barrel sales tanks to supplement the existing 2,000 barrel main sales tank and two smaller tanks at Battery #134. The Company is commencing construction of the first of these new 5,000 barrel tanks and the second tank will be added as and when it is required.

 

The installation of a lease area custody ("LACT") meter has therefore been rescheduled for no earlier than in the 4th quarter of this year. Petroleum Company of Trinidad and Tobago ("Petrotrin") has advised that the completion of the new 4-inch sales tie-in pipeline from Battery #134 to the main sales line and on to the Pointe-a-Pierre refinery remains outstanding pending a pipeline crossing agreement with a third party. In the interim additional pumping capacity has been installed on the existing 2 7/8-inch line, along with independent power generation, to eliminate any potential short term bottlenecks, with the additional production from new production wells.

 

Neil Ritson, LGO's Chief Executive, commented:

"As LGO looks towards the longer term production projections at Goudron, especially the potential of an EOR project, we need to acquire considerably more reservoir data than was historically collected. These new wells have excellent reservoir characteristics on logs and be believe can provide much of the information required as they are brought on to production. In the meantime drilling at GY-675 is continuing at over 360 feet."

 

Qualified Person's Statement:

 

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for LGO Energy plc, who has over 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers (SPE), an Active Member of the American Association of Petroleum Geologists (AAPG) and is a Fellow of the Geological Society of London.

 

Enquiries:

LGO Energy plc

+44 (0) 203 794 9230

Neil Ritson

Fergus Jenkins

Beaumont Cornish Limited

+44(0) 20 7628 3396

Nomad

Rosalind Hill Abrahams

Roland Cornish

FirstEnergy Capital LLP

+44(0) 20 7448 0200

Joint Broker

Jonathan Wright

David van Erp

 

Bell Pottinger

+44 (0) 20 3772 2500

Financial PR

Henry Lerwill

 

Glossary:

C-sand

sandstone reservoirs below the pre-Mayaro unconformity and above the pre-Lower Cruse unconformity encompassing sandstones of equivalent age to both the Gros Morne and the Lower Cruse formations

EOR

enhanced oil recovery

LACT

lease area custody transfer

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLFFSLRIIRLIE
Date   Source Headline
1st Jul 201610:54 amRNSHolding(s) in Company
14th Jun 20167:00 amRNSFinancing and Goudron Field Update
9th Jun 20164:26 pmRNSIssue of shares for services and TVR
9th Jun 20161:38 pmRNSAnnual Report and Accounts and Notice of AGM
25th May 20169:53 amRNSHolding(s) in Company
18th May 20166:07 pmRNSHolding(s) in Company
13th May 20165:23 pmRNSHolding(s) in Company
13th May 20165:18 pmRNSHolding(s) in Company
12th May 20165:41 pmRNSHolding(s) in Company
12th May 201612:52 pmRNSHolding(s) in Company
12th May 20167:00 amRNSWell GY-50 and first quarter 2016 production
10th May 20166:04 pmRNSHolding(s) in Company
10th May 201612:42 pmRNSHolding(s) in Company
4th May 20165:17 pmRNS£3.25million Fundraising, Loan Restructuring & TVR
27th Apr 20167:00 amRNSRecompletion of Well GY-671, Goudron
20th Apr 20167:00 amRNSGoudron Operational Update
18th Apr 20163:28 pmRNSResult of Meeting, Issue of Equity, TVR
6th Apr 20169:36 amRNSUpdate Goudron Workover Program
1st Apr 20164:13 pmRNSTotal Voting Rights
31st Mar 20167:00 amRNSNotice of General Meeting
24th Mar 20167:00 amRNSGoudron Overriding Royalty Rates Reduced
16th Mar 20167:00 amRNS£1.95 million Share Issues
14th Mar 20167:00 amRNSUpdate Goudron production investment
9th Mar 20167:00 amRNSTermination of Offer Period and Goudron update
4th Mar 20167:00 amRNSBanking Update
25th Feb 20162:49 pmRNSREPLACEMENT Form 8.3 - LGO Energy PLC
25th Feb 201610:01 amRNSForm 8.3 - LGO Energy PLC
24th Feb 20167:00 amRNSCorporate and Operations Update
4th Feb 20162:05 pmRNSForm 8 (OPD) LGO Energy Plc (Replacement)
1st Feb 201612:23 pmRNSTotal Voting Rights
29th Jan 20164:25 pmRNSForm 8.3 - LGO Energy PLC
22nd Jan 20167:00 amRNSIssue of Shares, TVR and Rule 2.10
19th Jan 20166:00 pmRNSConference Presentation
31st Dec 20157:00 amRNSTotal Voting Rights
24th Dec 201512:23 pmRNSUpdate on Trinity-Inniss
17th Dec 20154:38 pmRNSForm 8.3 - LGO Energy PLC
14th Dec 201511:57 amRNSForm 8.3 - [LGO Energy PLC]
14th Dec 20157:00 amRNSIssue of Equity, TVR and Rule 2.10 Announcement
11th Dec 20153:03 pmRNSForm 8 (OPD) LGO Energy plc
8th Dec 20152:46 pmRNSShares Issued and Rule 2.10 Announcement
7th Dec 20158:00 amRNSStrategic review and commencement of Offer Period
7th Dec 20157:00 amRNSTabaquite Block, Trinidad
4th Dec 201510:09 amRNSSettlements with Various Creditors
26th Nov 201512:20 pmRNSBanking update and board change
3rd Nov 20157:00 amRNSCorporate and Operational Update
19th Oct 20157:00 amRNSUpdate Goudron Field well GY-678, Trinidad
12th Oct 20157:00 amRNSAcquisition of 25% stake in Bolt
5th Oct 20157:00 amRNS£1 million raised for further Goudron investment
24th Sep 20157:00 amRNSGoudron Sandstone oil production
22nd Sep 20152:42 pmRNSPresentation at First Energy Conference

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.