Goudron Pad 4 Testing and Infrastructure

17 Jun 2015 07:00

RNS Number : 3689Q
LGO Energy PLC
17 June 2015
 

For Immediate Release, 7 am

17 June 2015

 

LGO ENERGY PLC

("LGO" or the "Company")

 

Goudron Pad 4 Testing

and Infrastructure Update, Trinidad

 

 

LGO today announces its plans for the testing of the three recently drilled wells, GY-672, 673 and 674, on drilling Pad 4 at the Goudron Field, and provides an update on important infrastructure approvals and improvements that are designed to significantly increase oil sales capacity at the field from 2,750 barrels to over 12,000 barrels.

 

Well Testing:

The Company has now received final approval for the completion of all three wells recently drilled from Pad 4 as production wells. A combined total of 556 feet of perforations are planned across the prolific C-sand intervals in the three wells. The equipment required has been mobilised to the field and work is anticipated to start later this week.

 

As previously announced each of the new wells will be flow tested with the appropriate pressure build-up tests carried out over the coming weeks. Each well will be subject to a number of periods of flow testing up to 6 hours duration, followed by individual pressure build-up tests (pressure monitoring without flow) of approximately 24 hours. Once the test phase is complete, which may take up to 5 days per well, a stable flow rate will be selected to best manage the reservoir performance of the well in the short and medium term, and provide further information for the completion of further wells on the field. Oil produced from the wells during the test period will be sold.

 

Infrastructure:

LGO also confirms that it has now received the necessary approvals to construct two 5,000 barrel sales tanks to supplement the existing 2,000 barrel main sales tank and two smaller tanks at Battery #134. The Company is commencing construction of the first of these new 5,000 barrel tanks and the second tank will be added as and when it is required.

 

The installation of a lease area custody ("LACT") meter has therefore been rescheduled for no earlier than in the 4th quarter of this year. Petroleum Company of Trinidad and Tobago ("Petrotrin") has advised that the completion of the new 4-inch sales tie-in pipeline from Battery #134 to the main sales line and on to the Pointe-a-Pierre refinery remains outstanding pending a pipeline crossing agreement with a third party. In the interim additional pumping capacity has been installed on the existing 2 7/8-inch line, along with independent power generation, to eliminate any potential short term bottlenecks, with the additional production from new production wells.

 

Neil Ritson, LGO's Chief Executive, commented:

"As LGO looks towards the longer term production projections at Goudron, especially the potential of an EOR project, we need to acquire considerably more reservoir data than was historically collected. These new wells have excellent reservoir characteristics on logs and be believe can provide much of the information required as they are brought on to production. In the meantime drilling at GY-675 is continuing at over 360 feet."

 

Qualified Person's Statement:

 

The information contained in this announcement has been reviewed and approved by Neil Ritson, Chief Executive Officer and Director for LGO Energy plc, who has over 35 years of relevant experience in the oil industry. Mr. Ritson is a member of the Society of Petroleum Engineers (SPE), an Active Member of the American Association of Petroleum Geologists (AAPG) and is a Fellow of the Geological Society of London.

 

Enquiries:

LGO Energy plc

+44 (0) 203 794 9230

Neil Ritson

Fergus Jenkins

Beaumont Cornish Limited

+44(0) 20 7628 3396

Nomad

Rosalind Hill Abrahams

Roland Cornish

FirstEnergy Capital LLP

+44(0) 20 7448 0200

Joint Broker

Jonathan Wright

David van Erp

 

Bell Pottinger

+44 (0) 20 3772 2500

Financial PR

Henry Lerwill

 

Glossary:

C-sand

sandstone reservoirs below the pre-Mayaro unconformity and above the pre-Lower Cruse unconformity encompassing sandstones of equivalent age to both the Gros Morne and the Lower Cruse formations

EOR

enhanced oil recovery

LACT

lease area custody transfer

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLFFSLRIIRLIE
Date   Source Headline
22nd Jun 20202:17 pmRNSForm 8 (OPD) - Bahamas Petroleum Company PLC
22nd Jun 20202:02 pmRNSForm 8 (OPD) Columbus Energy Resources PLC
22nd Jun 202010:24 amGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
19th Jun 202010:41 amGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
19th Jun 202010:35 amRNSInterview on merger with Bahamas Petroleum
18th Jun 202010:15 amGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
17th Jun 20203:03 pmRNSForm 8.3 - [Columbus Energy Resources plc]
17th Jun 20209:33 amGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
17th Jun 20207:00 amRNSIssuance of Lind and Contractor Shares
16th Jun 20202:47 pmRNSForm 8.3 - [Columbus Energy Resources plc]
16th Jun 20209:52 amGNWForm 8.5 - Columbus Energy Resources Plc
15th Jun 202010:33 amGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
15th Jun 202010:08 amRNSInterview and Investor Presentation
12th Jun 20204:39 pmGNWForm 8.5 (EPT/RI) - Columbus Energy Resources Plc
12th Jun 20203:13 pmRNSForm 8.3 - [Columbus Energy Resources plc]
11th Jun 202011:58 amRNSRe 2.7 Recommended all-share merger
11th Jun 202011:49 amRNSRecommended all share merger - 2.7
3rd Jun 20202:05 pmRNSSecond Price Monitoring Extn
3rd Jun 20202:00 pmRNSPrice Monitoring Extension
1st Jun 20207:00 amRNSOperational Update - Phase 2 CO2 Trinity Inniss
29th May 20203:11 pmRNSTotal Voting Rights
28th May 20207:00 amRNSSaffron 2 - drilling application to Ministry
18th May 20201:21 pmRNSHolding(s) in Company
13th May 20207:00 amRNSUpdate and Total Voting Rights
11th May 20204:42 pmRNSSecond Price Monitoring Extn
11th May 20204:36 pmRNSPrice Monitoring Extension
7th May 202011:06 amRNSSecond Price Monitoring Extn
7th May 202011:00 amRNSPrice Monitoring Extension
5th May 202011:06 amRNSSecond Price Monitoring Extn
5th May 202011:00 amRNSPrice Monitoring Extension
5th May 20209:06 amRNSSecond Price Monitoring Extn
5th May 20209:00 amRNSPrice Monitoring Extension
4th May 202011:05 amRNSSecond Price Monitoring Extn
4th May 202011:00 amRNSPrice Monitoring Extension
4th May 20207:00 amRNSTotal Voting Rights
27th Apr 20204:40 pmRNSSecond Price Monitoring Extn
27th Apr 20204:36 pmRNSPrice Monitoring Extension
27th Apr 20207:00 amRNSSaffron Discoveries - Lower Cruse and Middle Cruse
15th Apr 20207:00 amRNSCorporate Update and response to COVID-19
14th Apr 20205:01 pmRNSHolding(s) in Company
6th Apr 20207:00 amRNSOperations Update - Goudron Renewal
31st Mar 20201:00 pmRNSUpdate on Inniss-Trinity CO2 Project
31st Mar 202011:06 amRNSSecond Price Monitoring Extn
31st Mar 202011:00 amRNSPrice Monitoring Extension
31st Mar 20207:00 amRNSOperations update - Goudron renewal
17th Mar 20207:00 amRNSCorporate Update
3rd Mar 20209:19 amRNSTotal Voting Rights
20th Feb 20207:00 amRNSDirector/PDMR Shareholding
20th Feb 20207:00 amRNSDirector/PDMR Shareholding
17th Feb 202011:18 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.