Operations Update

11 Feb 2026 07:00

Cadogan Energy Solutions Plc - Operations Update

Cadogan Energy Solutions Plc - Operations Update

PR Newswire

LONDON, United Kingdom, February 11

This announcement contains inside information as defined under the Market Abuse Regulations n. 596/2014

Cadogan Energy Solutions Plc

("Cadogan" or the "Company")

Cadogan Energy Solutions plc ("Cadogan") is pleased to provide the following operational update post year end.

2025 has been an important and challenging year for Cadogan. Like in the previous years, the Group's operations in Ukraine have been conducted under war time conditions with continued bombing against the Country's energy infrastructure and its subsequent consequences on the local economy. Despite the persistent challenges, Cadogan maintained safe operations throughout the year, and was able to overcome the obstacles to develop its power generation projects.

In the oil production activities, comprehensive hydrodynamic surveys of all wells at the Blazhiv field were completed. The results of these surveys led to update the hydrodynamic model and a refinement of production indicators. The net oil production amounted to 117,408 barrels, corresponding to an average production rate of 321 barrels per day. This represents a 9% decrease compared to the prior year, due to the temporary production shutdowns required to conduct these surveys, the short-term interruptions related to the equipment maintenance and disruptions in energy supplies. The average sales price dropped down and was around 47$ per bbl.

In 2025, Cadogan invested in the electricity sector and developed the new power generation projects, totalling 12.3 MW, including infrastructure equipment to connect to the grids (gas and electricity). The first tranche of 4.6 MW became operational on January 30th, 2026. This is a significant milestone in Cadogan's strategy shifting the business model to a multi-energy group and entering the power generation sector for the first time in the Company's history. The remaining 7.7 MW are in the final stages of completion and are expected to become operational in the coming weeks.

The gas-to-power project (0.85 MW), together with the associated gas infrastructure utilizing the non-commercial gas from oil production, has been fully completed and is awaiting final regulatory approval, after which operations will commence imminently. The project timeline was extended due to unforeseen administrative delays related to grid connection and permitting. This project will allow to drop significantly the CO2 emissions related to the oil production activities. In 2025, the use of purchased green certificates has allowed to reduce the intensity ratio by 4%. In 2026, the start of operations of the gas-to-power will contribute to reduce this ratio by over 70% for this activity.

In Italy, the Group has been granted two gas exploration licenses in Northern Italy. The preliminary studies necessary for the preparation of the exploration operations were started in 2025 and will be completed in 2026.

All the activities were executed without LTI or TRI, with a total of 1,874,000 manhours since the last incident. Besides, the Group has successfully passed ISO audit whereas ISO 14001 and 45001 certifications were re-validated by respective authority for the new term.

ENDS

About

Cadogan is an independent multi-energy group, listed on the Main Market of the London Stock Exchange, operating an exploration and production license in Ukraine, with two gas exploration licenses in Northern Italy. Cadogan is now an operator in the power generation sector. The Company's goal is to expand its investments across the energy value chain with a focus on energy solutions and services with a reduced environmental footprint.

For further information, please contact:

Cadogan Energy Solutions plc Fady Khallouf Chief Executive Officer f.khallouf@cadogan-es.comBen Harber Company Secretary +44 0207 264 4366



Date   Source Headline
15th Nov 20193:45 pmPRNResult of General Meeting, new CEO and new Chairman
4th Nov 20194:11 pmPRNOperations Update
1st Nov 20196:29 pmPRNExtension of the CEO mandate
21st Oct 20195:22 pmPRNGeneral Meeting
8th Oct 20197:00 amPRNTrading Update
2nd Oct 20199:51 amPRNReceipt of notice of requisition of general meeting
1st Oct 20194:29 pmPRNSale of Gazvydobuvannya
30th Sep 20197:00 amPRNIntention to requisition a general meeting
27th Aug 20197:00 amPRNHalf-year Report
20th Aug 201910:13 amPRNHolding(s) in Company
20th Aug 201910:07 amPRNHolding(s) in Company
29th Jul 20193:17 pmPRNProger Update
18th Jul 201910:00 amPRNDirectorate Change
3rd Jul 20192:56 pmPRNLicense Application
19th Jun 20192:00 pmPRNResult of AGM
30th May 20197:00 amPRNWell Update
21st May 20192:31 pmPRNReport on Payments to Governments
17th May 20192:38 pmPRNAnnual Financial Report and Notice of AGM
30th Apr 20199:36 amPRNWell Update
25th Apr 201912:05 pmPRNWell Update
24th Apr 20197:00 amPRNAnnual Financial Report
18th Apr 20192:05 pmRNSSecond Price Monitoring Extn
18th Apr 20192:00 pmRNSPrice Monitoring Extension
18th Apr 201911:05 amRNSSecond Price Monitoring Extn
18th Apr 201911:00 amRNSPrice Monitoring Extension
9th Apr 20194:09 pmPRNOperational Update
8th Apr 20194:41 pmRNSSecond Price Monitoring Extn
8th Apr 20194:35 pmRNSPrice Monitoring Extension
27th Feb 20199:05 amRNSSecond Price Monitoring Extn
27th Feb 20199:00 amRNSPrice Monitoring Extension
26th Feb 20194:34 pmPRNCorrection:Loan and related call-option agreement
26th Feb 201910:01 amPRNExecution of a loan and related call-option agreement
16th Jan 20197:00 amPRNOperational Update
16th Nov 20182:02 pmPRNOperational Update
12th Nov 20189:58 amPRNExit from the shale gas project in Ukraine
8th Nov 201810:48 amPRNWell Update
27th Sep 201810:02 amPRNOperational Update
21st Aug 20182:00 pmPRNHalf Yearly Report for the Six Months ended 30 June 2018
7th Aug 201810:01 amPRNCadogan Ukraine ISO Certification
21st Jun 20187:00 amPRNResult of AGM
30th May 20187:00 amPRNSuccessful Workover Campaign Increases Production
17th May 20183:30 pmPRNAnnual Financial Report and Notice of AGM
15th May 20184:48 pmPRNDelayed approval of the application to renew
8th May 20187:00 amPRNReport on Payments to Governments
26th Apr 20187:29 amPRNAnnual Financial Report
23rd Mar 201811:08 amPRNOperations Update
22nd Feb 201811:07 amPRNOperations Update
24th Jan 20189:58 amPRNOperational Update
18th Jan 20184:37 pmPRNHolding(s) in Company
18th Jan 20184:31 pmPRNHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.