Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBezant Resources PLC Regulatory News (BZT)

Share Price Information for Bezant Resources PLC (BZT)

Share Price is delayed by 15 minutes
Get Live Data
0.095    -0.0075 (-7.32%)
Bid:
0.09
Ask:
0.10
Spread: 0.01 (11.111%)
Market Cap: £20.77m
BZT Live PriceLast checked at - London Stock Exchange

Intraday Bezant Resources PLC Share Chart

Scoping Study for Choco Gold-Platinum Project

8 Mar 2017 07:00

RNS Number : 7816Y
Bezant Resources PLC
08 March 2017
 

8 March 2017

Bezant Resources Plc

("Bezant" or the "Company")

 

Independent scoping study completed for Choco alluvial

gold-platinum project, Colombia

Bezant (AIM: BZT), the AIM quoted mineral exploration and development company, announces that, further to its announcement of 24 January 2017, it has received from INGEX Grupo Minero SAS ("INGEX") their scoping study on the cost estimates and financial model for the Company's Choco alluvial gold-platinum project in Western Colombia (the "Choco Project").

 

Highlights:

 

· Study confirms the technical and economic feasibility of alluvial platinum (Pt) and gold (Au) production at the Choco Project based on historical data and drilling results

· Financial modelling based on stage 1 production using a single plant operation with a plant processing rate of 1,800m3/day ("Stage 1 Production")

· Comprehensive cost analysis and financial model has enabled, inter alia, the calculation of the following key estimated parameters for Stage 1 Production over a 12 month operational period:

o US$768 per ounce total cost of production for platinum and gold recoveries

o US$6.01/m3 (US$4.29/tonne) total average mining and processing cost

o 0.17 grammes per tonne (238mg/m3) break-even grade for combined Pt and Au; and

o annual platinum and gold production of 2,200 ounces and 1,467 ounces, respectively

 

· Principal underlying assumptions applied in the financial model include:

o combined Pt and Au grade of 300mg/m3 for processed material based on an assessment of historic third party mining operations and drilling data;

o current metals prices (US$965 per ounce of platinum and US$1,176 per ounce of gold); and

o a discount rate of 10%

· Estimated post tax profit, NPV, IRR and costs per ounce for both a 12 month and 5 year single plant operation are summarised below:

 

Duration

Post tax profit

US$m

NPV

US$m

IRR%

Cost per oz in US$

12 months

0.343

0.323

29%

768

5 years

3.57

2.8

32%

693

· Financial model did not incorporate any projections for future expansion via a possible multiple plant growth strategy

 

 

Commenting today, Ed Nealon, Chairman of Bezant, said:

"The scoping study, with its sensitised cost analysis and financial model, confirms the low-cost platinum and gold potential for the Choco Project via a staged development approach. I believe that through this staged approach Bezant can become a significant platinum and gold producer. The estimated 5-year average production costs of approximately US$700 per ounce for both platinum and gold produced, was better than anticipated and we believe represents some of the lowest platinum production costs in the world. The study only modelled stage 1 of the project, being a single plant operation and the planned staged addition of other plants will greatly enhance our production profile."

 

Introduction

As announced on 24 January 2017, Bezant commissioned INGEX to prepare a scoping study, incorporating a financial model and cost analysis associated with the development of an alluvial platinum and gold mining project in the Choco Province, Colombia, based on both new and historic information on the FKJ-083 licence area and comparative alluvial operations in Colombia. INGEX (www.ingexgrupominero.com) is an independent Colombian based mining consultancy with expertise over a wide range of mining related fields including, geology, exploration, mine engineering, occupational health and safety as well as environmental aspects. The cost estimates were primarily based on the verification of data and assumptions provided by the Company's mining contract partner in Colombia, Exumax SAS.

 

INGEX's study assumed a single plant alluvial mining operation and incorporated cost models from comparative historic and current exploration operations in the Choco Province. Accordingly, it did not take into account any planned future expansion of the Choco Project via a future multiple-plant growth strategy.

 

The study focused on a 12 month Stage 1 Production operation but also developed a financial model for 2 year and 5 year scenarios for a single plant production operation based on the Company's strategy to further develop the areas it can mine through the exercise of existing options and development of its pending mining title application.

 

Summary cost analysis

The study included a comprehensive cost analysis for Stage 1 Production based on a static single plant operation, with the following main cost categories:

- Labour

- Fuel

- Machinery

- Camp site

- Equipment

- Security

- Mobilisation

- Taxes

- Maintenance

- Government royalties

- Materials

 

 

The study calculated an estimated total annual production of 2,200 recoverable ounces of platinum and 1,467 recoverable ounces of gold and a processing rate of 1,800 m3/day.

The study also detailed the mining, processing and rehabilitation processes and transport distances. A 50 per cent. stripping and processing ratio and combined Pt and Au grade of 300mg/m3 for processed material were calculated for the project. The combined grade was based on an assessment of historic third party mining and drilling data from more than 1.3 million cubic metres of material and the sampling of 70 boreholes located in the area of direct influence for the FKJ-083 licence area.

Summary of Financial Analysis

The study focused primarily on the FKJ-083 mining licence area due to the abovementioned historical mining information and drilling data available in respect of the licence, which facilitated the modelling process and assumptions applied. However, Bezant and Exumax are confident that the results of the study can be applied to similar gravels on similar areas outside of the FKJ-083 licence area. INGEX's sensitised financial model was centred around a single near-surface dry mining plant with a processing rate of 1,800m3/day.

The key modelling parameters were:

Parameter

Unit

Value

Platinum price

USD/ounce

965

Gold price

USD/ounce

1,176

Exchange rate

COP:USD

2,993

Government royalties for platinum

%

6

Government royalties for gold

%

4

Effective tax rate

%

34

NPV discount rate

%

10

Plant operation

m3/h

100

Plant operational time

%

90

Hours per shift

Hrs

10

Shifts per day

No.

2

Working days per month

days

24

Stripping ratio*

%

50

Mining depth

m

30

Swell factor m3 to tonnes

n.a.

1.4

* Price per troy ounce of metal (Pt+Au) where there is a concentration of 300 mg/m3 and the relationship of Pt:Au is 60:40

Summary outputs from the financial model were:

Duration

Post tax profit

US$m

NPV

US$m

IRR%

Cut-off grade

mg/m3

Cost per oz in US$*

Mining & processing cost in US$/m3

12 months

0.343

0.323

29%

238

768

6.01

2 years

1.14

1.0

32%

222

718

5.58

5 years

3.57

2.8

32%

213

693

5.37

 

Further to the findings of the scoping study, Bezant believes that an initial production plant can be mobilised, brought into production and be capable of achieving initial operational profits within twelve months of commencing operations. Whilst awaiting further gold and platinum sampling results, which will be announced in due course, the Company is currently in discussions with Exumax over potential viable development sequences for H1 2017. With hard rock platinum producers operating in locations such as the Bushveld complex in South Africa at a break even point of around US$1,000/oz for platinum group metals, the Board believes that the Choco Project, with its near-surface, free metal can viably host low capex production expansion with sustainable margins.

 

Dr Bernard Olivier has reviewed and approved the technical information contained within this announcement in his capacity as a qualified person, as required under the AIM rules. Dr Olivier is Chief Executive Officer of the Company and a Member of the Australasian Institute of Mining and Metallurgy.

 

For further information, please contact:

Bezant Resources plc

Bernard Olivier

Chief Executive Officer

 

Laurence Read

Executive Director / Communications Officer

 

Strand Hanson Limited (Nomad)

James Harris / Matthew Chandler / James Dance

 

Beaufort Securities Limited (Broker)

Elliot Hance

 

or visit http://www.bezantresources.com

 

Tel: +61 40 894 8182

 

 

Tel: +44 (0)20 3289 9923

 

 

 

Tel: +44 (0)20 7409 3494

 

Tel: +44 (0)20 7382 8300

 

 

 

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No. 596/2014.

 

Note to Editors:

Exumax (www.exumax.co) is a Colombian based mine operating Company with over 6 years mine operating experience in Colombia and has a well-established Colombian based team that can provide turnkey exploration solutions to Bezant's wholly owned Colombian subsidiary, Ulloa Recursos Naturales SAS. The principals of Exumax have over 50 years' of combined operating experience in the mining and construction industry in South America and in this period have developed extensive proprietary mining expertise. Exumax own and have imported special purpose alluvial mining equipment from New Zealand, where such operations are common, for use in low-cost alluvial extraction projects focused on precious metals. Exumax have operated a series of alluvial projects in Colombia and prioritise community relations and environmental management work as key components to building successful mining operations in-country.

 

 

Glossary of technical terms:

 

"Au"

gold

"g"

grammes

"g/m3"

grammes per cubic metre

"IRR"

internal rate of return

"m"

metre

"m3"

cubic metre

"mg"

milligramme

"mg/m3"

milligramme per cubic metre

"NPV"

net present value

"oz"

troy ounce (=31.103477 grammes)

"Pt"

platinum

"t"

tonne (=1 million grammes)

"US$"

United States dollars

"US$/ounce"

United States dollars per ounce

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEDLFBDXFZBBX
Date   Source Headline
1st May 202612:14 pmRNSTotal Voting Rights
8th Apr 20267:00 amRNSHope & Gorob Project-New Mineral Resource Estimate
31st Mar 20267:00 amRNSFundraising, Directors' Dealing and TVR
30th Mar 20269:31 amRNSHope & Gorob Copper-Gold - Mine Development Update
30th Mar 20267:00 amRNSExercise of Warrants, Total Voting Rights
24th Mar 20261:24 pmRNSAdditional 20% interest in Hope and Gorob
11th Mar 202611:00 amRNSAppointment of mining and logistics contractor
11th Mar 202611:00 amRNSAppointment of mining and logistics contractor
10th Mar 20267:00 amRNSNLZM Mining Licence Renewed, Warrants Exercise TVR
10th Mar 20267:00 amRNSNLZM Mining Licence Renewed, Warrants Exercise TVR
3rd Mar 20262:11 pmRNSGrant of Options and Director/PDMR Shareholding
23rd Jan 202610:47 amRNSExercise of Warrants and TVR
14th Jan 202610:34 amRNSExercise of Warrants, Total Voting Rights
8th Jan 202610:53 amRNSExercise of Warrants, Total Voting Rights
29th Dec 20255:00 pmRNSDirector/PDMR Shareholding
29th Dec 20255:00 pmRNSDirector/PDMR Shareholding
24th Dec 20259:23 amRNSDirector/PDMR Shareholding
24th Dec 20259:23 amRNSDirector/PDMR Shareholding
17th Dec 20257:00 amRNSCompletion of NLZM Processing Plant Acquisition
8th Dec 20253:08 pmRNSResult of General Meeting
8th Dec 202510:23 amRNSExercise of Warrants, Total Voting Rights
4th Dec 20257:00 amRNSExercise of Warrants, Total Voting Rights
2nd Dec 202511:08 amRNS-RGeneral Meeting Presentation
19th Nov 20257:00 amRNSCircular re Proposed Acquisition and Notice of GM
12th Nov 202512:36 pmRNSHolding(s) in Company
6th Nov 20252:04 pmRNSExercise of Warrants and TVR
3rd Nov 20257:00 amRNSExercise of Warrants and Total Voting Rights
31st Oct 202512:37 pmRNSTotal Voting Rights
31st Oct 202511:37 amRNSPrepayment Facility and concentrate offtake agreed
30th Oct 20257:00 amRNSHope and Gorob Project Study Report
29th Oct 20252:39 pmRNSHope and Gorob Project Update
24th Oct 20257:00 amRNSExercise of Warrants, Total Voting Rights
16th Oct 20259:44 amRNSExercise of Warrants, Total Voting Rights
10th Oct 20259:01 amRNSBlackstone Investment - Mankayan Project Update
10th Oct 20257:00 amRNSExercise of Warrants, Total Voting Rights
2nd Oct 20259:21 amRNSHolding(s) in Company
2nd Oct 20257:00 amRNSUpdate on Blackstone Minerals Investment
30th Sep 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
17th Sep 202510:14 amRNSBlackstone Minerals - Mankayan Project Update
11th Sep 20251:03 pmRNSExercise of Warrants, Total Voting Rights
14th Aug 20257:00 amRNSProposed Acquisition of Processing Plant
29th Jul 20257:07 amRNSBlackstone Investment - Mankayan Project Update
25th Jul 202511:57 amRNSResult of AGM
14th Jul 202512:23 pmRNSBlackstone Investment - Mankayan Project Update
11th Jul 20252:46 pmRNSExercise of Warrants, Total Voting Rights
9th Jul 20252:50 pmRNSExercise of Warrants, Total Voting Rights
9th Jul 202511:14 amRNSMankayan Project Update
8th Jul 20258:03 amRNSHolding(s) in Company
2nd Jul 202511:08 amRNSMankayan Project Update
2nd Jul 20257:00 amRNSNotice of AGM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.