Watch the latest episode of focusIR Fireside Chats: Why Edinburgh Investment Trust Is Backing Turnaround Stocks for 2026 Growth. View here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBezant Resources PLC Regulatory News (BZT)

Share Price Information for Bezant Resources PLC (BZT)

Share Price is delayed by 15 minutes
Get Live Data
0.1405    0.00 (0.00%)
Bid:
0.00
Ask:
0.00
Spread: 0.02 (14.286%)
Market Cap: £31.39m
BZT Live PriceLast checked at - London Stock Exchange

Intraday Bezant Resources PLC Share Chart

EIA Baseline Study Completed, Mankayan Cu Project

15 Jul 2019 09:15

RNS Number : 5141F
Bezant Resources PLC
15 July 2019
 

15 July 2019

Bezant Resources Plc

("Bezant" or the "Company")

EIA Baseline Study Completed, Mankayan Cu Project, Luzon, Philippines

Bezant (AIM: BZT), the copper-gold exploration and development company, is pleased to announce that it has completed a key component of the Environmental Impact Assessment ("EIA") baseline study required for the successful future completion of a pre-feasibility study. The dry season water quality baseline study at the Company's Mankayan copper-gold project, located in Luzon in the Philippines, has been undertaken in order to establish the monitoring levels for the potential development of a sustainable mining project. GHD Group Pty. Ltd ("GHD") were engaged to undertake the independent environmental survey work over the Mankayan Project's site covering an area of 533.4 hectares under the Mineral Production Sharing Agreement ("MPSA") Number 057-96-CAR.

The baseline water quality assessment comprised the following scope of work:

· Review of previous water quality baseline report and related documents

· Site reconnaissance, interview of personnel and documentation of the existing conditions of the 12 established sampling stations within and outside the MPSA area

· Surface and ground water quality sampling in the 12 abovementioned established stations

· Analytical testing (i.e. physico-chemical, microbiological and metals) of the collected surface and groundwater samples through a Department of Environment and Natural Resources ("DENR") recognised laboratory

· Analysis of in situ, physio-chemical, microbiological, and metal parameters based on laboratory results

· Preparation and submission of a report

A total of 12 sampling stations comprised of nine surface water and three groundwater-sampling stations were established for the baseline study. Water samples were analysed for physico-chemical (i.e. pH, total suspended solids, total dissolved solids, biological oxygen demand, chemical oxygen demand, oil and grease, nitrates and phosphates), microbiological (i.e. total coliform and faecal coliform) and metals (i.e. arsenic, cadmium, copper, chromium, lead, iron, mercury and zinc) parameters. The analytical results of the freshwater samples were compared to the prescribed criteria of the DENR Administrative Order No. 2016-08 (DAO 2016-08) Water Quality Guidelines (WQG) for Class A waters, while the analytical results for groundwater were compared to the Philippine National Standard for Drinking Water (PNSDW) 2017 values.

Summary

All baseline conditions for dry season water measurement have now been collected and processed within the independent July 2019 report submitted to the Company by GHD. Alongside further environmental studies required for the EIA in due course, the baseline study will allow informed development decisions to be made, working closely with local stakeholders and in full compliance with the laws and regulations of the Philippines. The findings of GHD's report will be communicated to local stakeholders through community engagement. This baseline component has been concluded to a level compliant with local and global reporting standards.

Laurence Read, CEO of Bezant, commented:

"Ensuring the correct environmental baseline studies are in place for a major copper-gold development project, especially in respect to water, is essential. The results of this independent study will be communicated to local and governmental stakeholders and form a key part of the pre-feasibility study programme to ensure that informed, sustainable decisions are made in the future potential construction, consultation and planning stages of Mankayan. Operating within an existing mining area our intention is to support the potential future development of an underground, modern mining operation where ongoing environmental monitoring is in place at all stages in the project's lifespan."

 

For further information, please contact:

Bezant Resources plc

Laurence Read

Chief Executive Officer

 

Colin Bird

Executive Chairman

 

Strand Hanson Limited (Nomad)

James Harris / Matthew Chandler / James Dance

 

Novum Securities Limited (Broker)

Jon Belliss

 

or visit http://www.bezantresources.com

 

Tel: +44 (0)20 3289 9923

 

 

 

 

 

 

Tel: +44 (0)20 7409 3494

 

 

Tel: +44 (0)20 7399 9400 

 

 

 

Qualified Person's Statement

In accordance with the AIM Note for Mining and Oil & Gas Companies, June 2009 (the "Guidance Note"), Colin Bird, CEng, FIMMM, a South African and UK Certified Mine Manager and Executive Chairman of Bezant, with more than 40 years relevant experience, is the qualified person who has reviewed and approved the technical information contained herein.

 

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No. 596/2014.

 

 

Notes to Editors:

 

Mankayan Cu-Au Project, Philippines

Fly-through videos for the Company's Mankayan copper-gold project located north of Manilla on Luzon island are hosted on "Youku" in both Standard Chinese and English.

菲律Mankayan铜金矿生产开拓计划

The Chinese version can be accessed via the following link: https://v.youku.com/v_show/id_XNDIyNTAwNTc0OA==.html

 

The English version and can be accessed via the following link: https://v.youku.com/v_show/id_XNDIyNTM2MjA3Ng==.html

 

Mankayan has a copper-gold resource estimate completed by Snowden Mining Industry Pty Limited ("Snowden") in 2009 under JORC (2004) which defined an indicated resource of 1.1 million tonnes of contained copper and 3.7 million ounces of contained gold and an inferred resource of 0.2 million tonnes of contained copper and 0.6 million ounces of contained gold.

 

Following the Mining Plus Pty Limited independent economic study completed in February 2019, the Mankayan copper-gold porphyry supports different robust routes for potential future development, including, a Sub-Level Caving ("SLC") 'stepping stone' scenario, with two main Block Caving ("BC") routes identified for progression, from a total of 11 scenarios assessed, with both supporting an average production grade in excess of 0.64% copper equivalent ("CuEq"). 

 

5 year lead time to production: Under all four of the representative options selected for further analysis in the study, the time to initial production was approximately five years and the first five years of production are sequenced in order to deliver production from the higher grade areas of the deposit, in some cases demonstrating average grades achievable of up to 0.77% CuEq* during this initial period.

 

The three main representative options summarised below, taken from the 11 modelled scenarios, comprise two BC scenarios and one SLC 'stepping stone' scenario (the option numbers being those used in the study)

 

The two preferred BC scenarios

Option 4: medium production rate with lower start-up costs than those associated with higher production rate models

US$1,181m net present value ("NPV")*, US$11,647m total revenue, US$19.1/t average cost, 27% internal rate of return before tax and royalty ("IRR"), US$896m start-up Capex

 

Option 8: lower start-up costs, coupled with a good overall project value maintained by ramping-up the production rate after the first footprint

US$797m NPV*, US$11,473m total revenue, US$19.7/t average cost, 21% IRR, US$633m start-up Capex

 

SLC intermediary route

Option 9: a more flexible/low start-up cost SLC method has been determined as an intermediary step towards full block caving scenarios, with start-up Capex of US$529m, a slightly reduced time to first production, a first phase period into higher grade core and US$19.9/t average cost

 

Note:

* The NPV calculated is for comparative purposes only, as full financial analysis was not undertaken for the study. A mean copper price scenario of US$3/lb was used and all costs are mine and processing combined. Due to the current uncertainty surrounding the Philippine tax/royalty rates, neither have been included in the comparison. Inclusion of tax and royalty would reduce the NPV and IRR, but it is expected that the relative economic merits of each scenario would not change significantly.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLEAPXSFELNEEF
Date   Source Headline
19th Jun 20264:02 pmRNSExercise of Warrants, Total Voting Rights
18th Jun 20263:20 pmRNSExercise of Warrants, Total Voting Rights
11th Jun 20268:00 amRNSExercise of Warrants, Total Voting Rights
11th Jun 20267:00 amRNSHope & Gorob Project Financing & Offtake Agreement
1st May 202612:14 pmRNSTotal Voting Rights
8th Apr 20267:00 amRNSHope & Gorob Project-New Mineral Resource Estimate
31st Mar 20267:00 amRNSFundraising, Directors' Dealing and TVR
30th Mar 20269:31 amRNSHope & Gorob Copper-Gold - Mine Development Update
30th Mar 20267:00 amRNSExercise of Warrants, Total Voting Rights
24th Mar 20261:24 pmRNSAdditional 20% interest in Hope and Gorob
11th Mar 202611:00 amRNSAppointment of mining and logistics contractor
11th Mar 202611:00 amRNSAppointment of mining and logistics contractor
10th Mar 20267:00 amRNSNLZM Mining Licence Renewed, Warrants Exercise TVR
10th Mar 20267:00 amRNSNLZM Mining Licence Renewed, Warrants Exercise TVR
3rd Mar 20262:11 pmRNSGrant of Options and Director/PDMR Shareholding
23rd Jan 202610:47 amRNSExercise of Warrants and TVR
14th Jan 202610:34 amRNSExercise of Warrants, Total Voting Rights
8th Jan 202610:53 amRNSExercise of Warrants, Total Voting Rights
29th Dec 20255:00 pmRNSDirector/PDMR Shareholding
29th Dec 20255:00 pmRNSDirector/PDMR Shareholding
24th Dec 20259:23 amRNSDirector/PDMR Shareholding
24th Dec 20259:23 amRNSDirector/PDMR Shareholding
17th Dec 20257:00 amRNSCompletion of NLZM Processing Plant Acquisition
8th Dec 20253:08 pmRNSResult of General Meeting
8th Dec 202510:23 amRNSExercise of Warrants, Total Voting Rights
4th Dec 20257:00 amRNSExercise of Warrants, Total Voting Rights
2nd Dec 202511:08 amRNS-RGeneral Meeting Presentation
19th Nov 20257:00 amRNSCircular re Proposed Acquisition and Notice of GM
12th Nov 202512:36 pmRNSHolding(s) in Company
6th Nov 20252:04 pmRNSExercise of Warrants and TVR
3rd Nov 20257:00 amRNSExercise of Warrants and Total Voting Rights
31st Oct 202512:37 pmRNSTotal Voting Rights
31st Oct 202511:37 amRNSPrepayment Facility and concentrate offtake agreed
30th Oct 20257:00 amRNSHope and Gorob Project Study Report
29th Oct 20252:39 pmRNSHope and Gorob Project Update
24th Oct 20257:00 amRNSExercise of Warrants, Total Voting Rights
16th Oct 20259:44 amRNSExercise of Warrants, Total Voting Rights
10th Oct 20259:01 amRNSBlackstone Investment - Mankayan Project Update
10th Oct 20257:00 amRNSExercise of Warrants, Total Voting Rights
2nd Oct 20259:21 amRNSHolding(s) in Company
2nd Oct 20257:00 amRNSUpdate on Blackstone Minerals Investment
30th Sep 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
17th Sep 202510:14 amRNSBlackstone Minerals - Mankayan Project Update
11th Sep 20251:03 pmRNSExercise of Warrants, Total Voting Rights
14th Aug 20257:00 amRNSProposed Acquisition of Processing Plant
29th Jul 20257:07 amRNSBlackstone Investment - Mankayan Project Update
25th Jul 202511:57 amRNSResult of AGM
14th Jul 202512:23 pmRNSBlackstone Investment - Mankayan Project Update
11th Jul 20252:46 pmRNSExercise of Warrants, Total Voting Rights
9th Jul 20252:50 pmRNSExercise of Warrants, Total Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.