Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBellzone Mining Regulatory News (BZM)

  • There is currently no data for BZM

Forecariah Mining Update

31 May 2012 07:00

RNS Number : 4737E
Bellzone Mining PLC
31 May 2012
 



7am: 31 May 2012

Bellzone Mining plc

("Bellzone" or the "Company")

 

Forécariah Mining Update

 

·; First ore transported from Forecariah to the port of Konta

·; First sales expected Q3 2012

 

Bellzone Mining plc (AIM: BZM) is pleased to announce a progress update at its Forécariah JV iron ore mine in the Republic of Guinea, West Africa.

Following receipt of authorisation to commence production on 21 May 2012, the operations have commenced stockpiling the first fines material for wet processing and transported the first lump production via haul trucks to the transhipping port at Konta.

The lump ore will be stockpiled at Konta before being transported by barge to the transhipping Panamax vessel, FGM Iron. First sold ore is expected to be loaded into a Cape size (circa 170,000 tonne) vessel for sailing in Q3 2012.

Off-take negotiations are progressing well and the Company will update the market as and when appropriate.

 Nik Zuks, Chief Executive Officer of Bellzone, commented: "I am pleased to provide an update on commissioning following authorisation to commence production last week. The JV is now in production, and loading of the transhipping vessel from the port will commence soon with first sales expected in Q3 2012.

The conditions attached to the authorisation to proceed were not unexpected and were in the main a codification of previous undertakings that were already contained in Bellzone and CIF's business plan as well as some administrative work."

Updated images and video footage of the processing plant has today been published on the website. For more information please visit www.bellzone.com.au

 

Enquiries:

 

Bellzone Mining plc

Terry Larkan/Graham Fyfe +61 (0) 8 9420 8900

 

Canaccord Genuity Limited

Nominated Adviser and Joint Broker to Bellzone +44 (0)20 7523 8000

Andrew Chubb/Tarica Mpinga

 

Renaissance Capital Limited

Joint Broker to Bellzone +44 (0)20 7367 7777

Rob Edwards

 

Tavistock (UK)

Jos Simson/Paul Youens +44 (0)20 7920 3150 / +44 (0)7899 870 450

 

PPR (Australia)

David Ikin

+61 (0) 8 9388 0944 / +61 (0) 408 438 772

 

 

About Bellzone Mining Plc

 

Bellzone Mining plc is a publicly listed company on the London Stock Exchange and was admitted to the Alternative Investment Market (AIM: BZM) on 1st April 2010. Bellzone Mining plc ("Bellzone" or "the Company") is an exploration and resource development company with iron ore and nickel / copper permits in the Republic of Guinea, West Africa.

 

Kalia Mine

The Company's flagship project, the Kalia Mine Project, is planned to commence production in 2015 and be producing iron ore and iron ore concentrate at a rate of 50 million tonnes per annum. The Kalia Mine Project has 1.46 billion tonnes of contained iron in JORC resources in 6.16 billion tonnes of magnetite, 193 million tonnes of oxide and 92.5 million tonnes of supergene BIF. The oxide and Supergene BIF resources have been established from just 10.5% of the 55km2 of the mapped surface oxides on the Kalia permit while the magnetite has been established over 7km of the 19km Kalia I strike. Drilling results and internal estimates indicate that the Kalia Mine Project has the potential to host more than 10 billion tonnes of magnetite.

 

Forécariah JV

Bellzone and CIF have fully funded a joint venture to undertake the accelerated exploration and development programme at CIF's Forécariah iron permits that lie between 30 and 80 kilometres from the Guinea coast. The Forécariah permits are held in a CIF subsidiary, Guinea Development Corporation ("GDC") and will be transferred to the JV operations company, Forécariah Guinea Mining SA as per the terms of the definitive and JV shareholder agreements. Commissioning production commenced in Q1 2012 and production will ramp up to an initial rate of 3‐4 mtpa.

 

Other activities

Bellzone has completed a mapping and surface sampling programme identifying highly prospective targets at its Sadeka Nickel/Copper Project. A VTEM aerial survey has been completed and prospective targets have been identified and a drilling programme has commenced.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
NRASDMEESFESELI
Date   Source Headline
28th Dec 201610:47 amRNS2017 Funding and Business Update
1st Nov 20164:40 pmRNSSecond Price Monitoring Extn
1st Nov 20164:35 pmRNSPrice Monitoring Extension
12th Sep 20167:00 amRNSUnaudited Interim Results
25th Aug 20167:00 amRNSKalia Project - Ferronickel Study Results
1st Jul 20163:47 pmRNSAGM Result and Board Change
13th Jun 20165:11 pmRNSNotice of AGM
13th Jun 20165:01 pmRNSFull Year Results
21st Jan 20167:00 amRNSResults of Placing
15th Jan 20165:12 pmRNSBellzone Mining plc Non Pre-emptive Placing
12th Jan 20164:35 pmRNSPrice Monitoring Extension
24th Dec 20157:00 amRNSFinancing Update and 2016 Business Plan
6th Nov 20154:40 pmRNSSecond Price Monitoring Extn
6th Nov 20154:35 pmRNSPrice Monitoring Extension
28th Oct 201510:41 amRNSDirectorate Change
15th Oct 201511:32 amRNSKalia Mine Project Update
2nd Oct 20154:35 pmRNSPrice Monitoring Extension
25th Sep 20157:00 amRNSHalf Yearly Report
19th Aug 20155:25 pmRNSBoard Change
4th Aug 20154:41 pmRNSChange in Significant Shareholding
15th Jul 20157:00 amRNSKalia Project Update
23rd Jun 20153:08 pmRNSResult of AGM
8th Jun 20154:40 pmRNSSecond Price Monitoring Extn
8th Jun 20154:35 pmRNSPrice Monitoring Extension
2nd Jun 20154:35 pmRNSNotice of AGM
2nd Jun 20152:18 pmRNSFull Year Results
1st May 20158:57 amRNSBoard Change
6th Mar 20154:40 pmRNSSecond Price Monitoring Extn
6th Mar 20154:35 pmRNSPrice Monitoring Extension
6th Mar 20157:30 amRNSRestoration - Bellzone Mining Plc
5th Mar 20155:00 pmRNSFinancing Update and Restoration of Trading
30th Jan 20158:47 amRNSBoard Change
28th Jan 20151:31 pmRNSFinancing Update
8th Dec 20147:00 amRNSAdviser Appointments
3rd Dec 20144:27 pmRNSFinancing Update
28th Nov 20142:30 pmRNSFinancing Update
18th Nov 20144:54 pmRNSDirectorate Change
28th Oct 201411:16 amRNSResult of Extraordinary General Meeting
17th Oct 20147:00 amRNSChange of Registered Office
10th Oct 20145:03 pmRNSNotice of Extraordinary General Meeting
10th Oct 201410:34 amRNSPlacing to raise up to approximately £1.7 million
30th Sep 20149:49 amRNSUnaudited Interim Results
22nd Sep 20147:30 amRNSSuspension - Bellzone Mining plc
22nd Sep 20147:30 amRNSFunding update and suspension of securities
17th Sep 20147:00 amRNSFunding Update
1st Sep 20147:00 amRNSFunding Update
18th Aug 20143:25 pmRNSShort Term Finance Update
11th Aug 20147:00 amRNSFinancing Update
25th Jul 201410:14 amRNSResult of AGM
30th Jun 20147:00 amRNSNotice of AGM and Posting of Annual Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.