Vanadium Update

20 Jan 2017 07:00

RNS Number : 6664U
BMR Group PLC
20 January 2017
 

BMR Group PLC ("BMR" or the "Company")

Vanadium Update

BMR is pleased to report encouraging news concerning the potential recovery of Vanadium and production of Vanadium Pentoxide from its tailings at Kabwe which further bolsters its asset base.

Following the Company's announcement on 6 December 2016, the Board is pleased to report on the progress of its metallurgical test work currently being undertaken in collaboration with its partners, Kupfermelt and Alfred H Knight Laboratories, Kitwe for the recovery of Vanadium ("V") and the production of Vanadium Pentoxide (V2O5) from BMR's Kabwe tailings dumps.

The Board also announces the potential financial implications for the Company in respect of the current trading price of V2O5, and the historic V grades declared by Zambian Consolidated Copper Mines in their Mine Closure report

a) Vanadium Recovery Factors and Upgrading to Vanadium Pentoxide

The Board is pleased to report that the metallurgical test work to date has shown that no modifications should be required to the acid brine leach section at the Kabwe plant to recover the V from tailings and take it into solution as a by-product. Selective recovery of the V in solution has been successfully achieved during the Zinc re-leach phase, requiring only minimal changes to the current flowsheet design.

Preliminary test work results suggest an overall V2O5 recovery factor of approximately 65% (discounted 5% from actual test work results). Test work continues to optimise the V2O5 recovery factor, to establish final product quality and the design of the process circuit to produce V2O5. This will enable CAPEX and OPEX costs to be established, of which the former will be at an additional construction cost to the Company. An announcement will be made as soon as practicable concerning this additional cost, although at this stage the Company does not believe that it will be substantial. New technology will not be required for the production of V2O5.

b) Vanadium Pentoxide, Zinc and Lead Tailings Grades

Prior to the closure of the Kabwe mine in June 1994, each of the mine's tailings dumps were assayed by Zambian Consolidated Copper Mines (ZCCM), the results of which were disclosed in the Kabwe Mine Closure Report.

Although Mineral Consultancy Corporation (MCC) did not report V grades in their March 2012 JORC report, with one exception, the Zn and Pb grades for the WPT, LPR and ISFS tailings dumps mostly correlate closely with those published in the Mine Closure Report, as follows:-

Comparison of grades, MCC Report to Closure Report

 

 

 

 

 

MCC (Resource) Report

Mine Closure Report

% Deviation

 

Zn

Pb

Zn

Pb

Zn

Pb

WPT (JORC)

10.66%

7.21%

10.22%

6.72%

4.13%

6.80%

LPR (JORC)

3.88%

8.71%

4.33%

7.50%

11.60%

13.89%

ISFS (Non JORC)

8.07%

1.22%

8.55%

2.03%

5.95%

66.39%

 

MCC's QA/QC assaying protocols have classified as acceptable, a ±10% grade deviation for Certified Reference Materials (CRMs). The close correlation in the two reports of the Zn/Pb grades (JORC only, WPT and LPR), suggests in the Board's opinion that the Mine Closure Report's stated V grades can be considered as a fair guide to those V grades carried in the WPT, LPR and ISFS dumps as illustrated below:

Kabwe Mine Closure Report

 

 

Indicative V2O5 Grades

 

 

 

 

MCC

V2O5

Mine Closure

 

Tonnage

Av. Grade

Samples

Leach Plant Residue (LPR)

2,725,318

1.11%

46 samples

Wash Plant Tailings (WPT)

585,160

1.61%

10 samples

Imperial Smelting Furnace Slag (ISFS)

1,481,563

1.87%

8 samples

V Grades have been converted to V2O5 using a stoichiometric factor. Based on a recovery factor of 65% and this estimated tonnage, in theory the Plant could extract approximately 45,000 tonnes of V2O5.

The V tonnages and grades presented herein are non JORC and should not be construed as recoverable reserves or resources.

c) Upgrading Vanadium to a JORC Compliant Resource

Current metallurgical test work by the accredited laboratory, Alfred H Knight in Kitwe, is intended to confirm the process for the economic recovery of V based on work already carried out by the Company for all three tailings dumps and to produce V2O5. It is expected that this will be completed during February 2017, whereupon the Company will commission MCC to prepare an upgrade of V in the three tailings dumps to a JORC Compliant Resource.

d) Vanadium Price Rise and Financial Implications for the Company

Metal Bulletin's website is reporting December 2016 trades (Rotterdam, Europe) for V2O5 at circa US$23/kg (earlier estimated at US$15/Kg) and as a consequence the Company has revised upwards the potential long term contribution of V2O5 production to the Company's income stream.

After discounting the current V2O5 price by 10%, illustrated below by gross sales value is its potential contribution to the Company when compared to the theoretical production of Zinc cathodes, Lead Sponge and Zinc Sulphate Heptahydrate over the projected mine life currently estimated at 19 years.

LIFE OF MINE INDICATIVE PRODUCTION TONNAGES AND GROSS SALES VALUES

PRODUCT

TONNES

 PRICE, US/t

VALUE $M

Lead Sponge

276,364

$2,267

$626.5

Zinc Cathodes

144,853

$2,693

$390.1

Zinc Sulphate Heptahydrate

570,000

$750

$427.5

Vanadium pentoxide, V2O5

45,000

$21,000

$952.2

TOTAL

 

 

$2,396.3

Note. 18th Jan 2017 LME Zn and Pb cash sale prices.

The calculated production values of metals are indicative and should not be construed as likely revenues to the Company.

e) ZEMA Approval

The Company has been advised by its consultant J A Consultancy that based on ZEMA's existing approval to build the Plant, approval to operate a V2O5 processing circuit should only require an Environmental Project Brief (EPB) which the Company intends to lodge in February 2017 with approval generally expected within 4 to 6 months.

Note: This announcement has been reviewed by Geoff Casson, B.Sc. (Hons), PhD, R Eng (Zambia), Member Engineering Institute of Zambia (Metallurgy), General Manager of the Company's Zambian subsidiary, Enviro Processing Ltd, who is a Qualified Person in accordance with the guidance note for Mining, Oil & Gas Companies issued by the London Stock Exchange in respect of AIM Companies.

This announcement contains inside information for the purposes of Article 7 of Regulation 596/2014.

 

Alex Borrelli, Chairman, commented: "This is encouraging news concerning the potential recovery of Vanadium and production of Vanadium Pentoxide from our tailings at Kabwe which further bolsters our asset base."

Ends

For further information:

BMR Group PLC 020 7734 7282

Alex Borrelli, CEO and Chairman

 

WH Ireland Limited 020 7220 1666

NOMAD and Joint Broker

Chris Fielding, Head of Corporate Finance

Nick Prowting, Manager

 

Peterhouse Corporate Finance 020 7469 0930

Joint Broker

Lucy Williams/ Duncan Vasey/ Heena Karani

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDGGUBWGUPMGMB
Date   Source Headline
28th May 20153:31 pmRNSDirectorate Changes
28th May 20153:30 pmRNSResult of AGM
13th May 20157:00 amRNSDirector/PDMR Dealing
1st May 20157:30 amRNSRestoration - Berkeley Mineral Resources Plc
1st May 20157:00 amRNSCorrection: Interim results
30th Apr 20155:51 pmRNSDirectorate
30th Apr 20155:50 pmRNSInterim results
29th Apr 20157:00 amRNSPosting of AGM notice and changes to the Board
14th Apr 20156:28 pmRNS2014 Final Results
2nd Apr 20157:00 amRNSLeach processing selected for pilot plant
31st Mar 20157:00 amRNSProgress Update
19th Feb 20157:00 amRNSGBP1.0 million Settlement Agreement
2nd Feb 20157:00 amRNSGeneral Update and Board Appointment
11th Dec 20147:00 amRNSUpdate on Investigation
4th Nov 201412:00 pmRNSSuspension - Berkeley Mineral Resources Plc
4th Nov 201412:00 pmRNSTemporary Suspension
23rd Oct 20147:00 amRNSAppointment Of Chairman
20th Oct 20149:15 amRNSBoard Changes
6th Oct 20147:00 amRNSKabwe Final Stage
20th Aug 20142:00 pmRNSShare Issue
19th Aug 20147:00 amRNSZEMA Approval Received
31st Jul 20142:00 pmRNSPlacing Update
7th Jul 20143:30 pmRNSShare Issue
1st Jul 20147:00 amRNSIssue of Equity
24th Jun 20141:30 pmRNSKabwe Update
20th Jun 20141:30 pmRNSKabwe Approval
11th Jun 201411:30 amRNSKabwe Update
5th Jun 20147:00 amRNSChange of Adviser
30th May 20141:00 pmRNSKabwe Update
25th Apr 20144:45 pmRNSExercise of Warrants
23rd Apr 20147:00 amRNSExercise of Warrants
15th Apr 20147:00 amRNSKabwe Update
14th Apr 20147:00 amRNSExercise of Warrants
2nd Apr 201412:00 pmRNSDirectors Dealings
28th Mar 20142:00 pmRNSDirectors Dealings
28th Mar 20147:01 amRNSInterim Results
3rd Feb 20143:39 pmRNSHolding(s) in Company
3rd Feb 20147:00 amRNSKabwe Update: 92% Copper Grade Achieved
27th Jan 20143:45 pmRNSExercise of Share Options
24th Jan 20147:00 amRNSWarrant Amendment
23rd Dec 201312:00 pmRNSResult of AGM
23rd Dec 20137:00 amRNSAGM Statement
19th Dec 20137:00 amRNSKabwe Copper Plant Completed
10th Dec 20137:00 amRNSStrategic Cooperation Agreement
2nd Dec 20137:00 amRNSPreliminary Results - Kabwe Update
11th Nov 20137:00 amRNSKabwe update -Initial Production at Kabwe
23rd Oct 20132:16 pmRNSWarrant Amendment
14th Oct 20137:00 amRNSKabwe Corporate Responsibility Programme
4th Oct 201310:48 amRNSHolding(s) in Company
26th Sep 20137:00 amRNSCopper Update: Kabwe Production Q4

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.