Joint venture with BMR Group PLC

23 Oct 2017 07:00

RNS Number : 2659U
Jubilee Platinum PLC
23 October 2017
 

Jubilee Platinum PLC

Registration number (4459850)

AltX share code: JBL

AIM share code: JLP

ISIN: GB0031852162

("Jubilee" or "Company")

 

Jubilee forms joint venture with BMR Group PLC ("BMR") to recover zinc, lead and vanadium at the Kabwe Project in Zambia

Highlights

· Jubilee expands its surface processing footprint into Zambia to recover lead, zinc and vanadium from historical surface deposits

· Jubilee partners with BMR to target the recovery of lead, zinc and vanadium from an estimated 6,4 million tonnes (3,2 million JORC compliant) of surface assets at Kabwe located in Zambia

· All historical mine activities have been suspended offering the project unencumbered access to existing infrastructure

· The partnership pools resources of both companies to bring the project to account

· The joint venture formed between Jubilee and BMR will finance and execute the approved works programme with commercial production expected of lead and zinc in 2018

· Jubilee has the option to provide staged financing towards the execution of the project secured against the shareholding of the Kabwe project as well as preferred income from the project

 

Leon Coetzer, Chief Executive Officer, says:

 

"I am delighted to announce that we have successfully secured access to this exciting surface project that extends our reach beyond the South African bushveld complex and into other commodities. This transaction is in line with our mission to take our brand and expertise across country borders and commodities.

 

This project is meaningful in scope, diversity and potential contribution to the Company's earnings. The Kabwe project offers immediate unencumbered access to a large surface stock rich in lead, zinc and vanadium created from historical mining and processing activities. The project benefits from existing infrastructure including power, water and building infrastructure, which significantly reduces the required project capital and shortens the implementation time line.

 

The Jubilee team's expertise and ability is perfectly suited to the project and strongly complements the existing BMR project team to extract maximum value from the metals contained in the various surface discards and I look forward to working with the BMR team to bring this project into being.

 

In entering into this agreement, we are acutely aware of the significant further opportunities presented within Zambia and will be actively exploring these opportunities."

 

Transaction Overview

Jubilee has executed a binding agreement (the "Transaction") to form a joint venture with AIM-quoted BMR to target the recovery of lead, zinc and vanadium from historical surface mine tailings and discards ("the Project").

 

Under the Transaction, a joint venture company will be established ("Kabwe Operations") which will be assigned all intellectual property developed for the execution of the Project as well as the right to fund and execute the Project on behalf of BMR.

 

Kabwe Operations will be appointed operator of the Project, with responsibility for commissioning, funding, construction and operations of the Project. Kabwe Operations will sub-contract operator responsibilities to Jubilee.

 

In terms of the Transaction Jubilee is offered the right to earn into Kabwe Operations through staged debt funding ("Debt Finance") as set out below. Jubilee's earn-in interest in Kabwe Operations will be through preferred shares issued in Kabwe Operations ("Preferred Shares"), which will have equal voting rights to ordinary shares of Kabwe Operations and will have the preferred right to receive 100% of distributed profits from Kabwe Operations until the preferred Debt Finance plus a 30% interest component is fully paid, where after the Preferred Shares will convert into ordinary shares of Kabwe Operations.

 

Jubilee Key Earn-in Terms for Kabwe Operations

(a) Phase 1 - Jubilee will provide access to funding for Kabwe Operations to the value of £300,000 to secure a 15% equity interest in Kabwe Operations held as a Preferred Share. The funding will be towards the confirmation by Jubilee of the initial design, work programme and budget for construction of the Project ("Approved Works Programme") to be prepared by Jubilee by 28 February 2018. At the completion of Phase 1 Jubilee will confirm its decision at its full discretion to proceed with the Project and further farm-in of Kabwe Operations ("Approval Notice").

(b) Phase 2 - Jubilee will provide access to a further £1,000,000 funding towards the implementation of the Approved Works Programme to secure a further 15% equity interest in Kabwe Operations taking the aggregate interest of Jubilee to 30% held as a Preferred Share. As security for the Jubilee Debt Finance, the BMR Group would grant security over the whole of its shareholding in the Kabwe project through its subsidiary Enviro Processing Limited.

(c) Phase 3 - Jubilee will provide access to a further £1,000,000 funding towards the implementation of the Approved Works Programme and targeting commercial production to secure a further 10% equity interest in Kabwe Operations taking the aggregate interest of Jubilee to 40% held as a Preferred Share.

In the event that the Joint Venture Agreement is deemed to be a fundamental change of business to BMR, in accordance with Rule 15 of the AIM Rules for Companies, and is not approved by shareholders of BMR at a General Meeting, Kabwe Operations (guaranteed by BMR) shall immediately repay the £300,000 of Jubilee Debt Finance together with 100 per cent interest thereon. Jubilee shall retain its interest in 15% of Kabwe Operations's voting share capital and shall have a pre-emptive right to participate in any future equity issue or joint venture relating to BMR's Kabwe project and the right to realise its interest in Kabwe Operations at the future equity issue price or joint venture implied value, as appropriate.

 

Andrew Sarosi, Director of Jubilee, who holds a B.Sc. Metallurgy and M.Sc. Engineering, University of Witwatersrand and is a member of the Institute of Materials, Minerals and Mining, is a "qualified person" as defined under the AIM Rules for Companies and a competent person under the reporting standards. The technical parts of this announcement have been prepared under Andrew's supervision and he has approved the release of this announcement. 

 

About Kabwe Mine

Information containing resource statements are based on the information as provided by BMR to Jubilee which is also referenced on the BMR website at www.bmrplc.com.

 

Mining History

 

The Kabwe mine was discovered during 1902 and commenced operations in 1904, reaching full-scale production in 1906. It officially closed down on 3 June 1994 due to its operations becoming uneconomic at that time. The site was placed under care and maintenance by the national mining company, The Zambian Consolidated Copper Mines ("ZCCM").

 

For 88 years of continuous operation until final closure in 1994, Kabwe was regarded as one of the famous mines in Africa and held a key position of national economic importance. During its life time the mine produced the following:

 

· Zinc (Zn) 1,800,000 tonnes

· Lead (Pb) 800,000 tonnes

· Vanadium Oxide (V2O) 7,816 tonnes

· Silver (Ag) 80,000kg

· Cadmium (Cd) 235,000kg

 

Importantly, the above-ground dumps of mineral-rich tailings, slag and waste left onsite during the mining years are still in place.

 

A large project conducted by the World Bank and the Nordic Development Fund commenced in 2005 for the environmental rehabilitation of the Kabwe mine area and is still ongoing.

 

On closure of the operations in 1994, much of the site area and plant infrastructure was sold in discrete lots to private investors, with the overall responsibility for decommissioning and rehabilitation of the sites retained by ZCCM. In recent years, the ownership of the Kabwe complex has been rationalised and since 2008 has been steadily acquired by BMR which now owns all the surface rights over the 705 hectares site.

 

The Kabwe Tailings Stockpiles

Enviro Processing Ltd holds the Small Scale Licence 7081-HQ-SML in respect of the Tailings Stockpiles on and the Large Scale Licence 6990-HQ-LML (applying to the whole 703 hectares of the BMR Kabwe site.

 

BMR has acquired all the stockpiles of tailings at the Kabwe mine complex. These assets are held by Enviro Mining Ltd, which is a wholly-owned subsidiary of BMR, and its two Zambian-registered subsidiaries, Enviro Processing Ltd and Enviro Props Ltd.

 

 

 

Stockpile 1 The Wash Plant Tailings Dump

 

The wash plant tailings dumps include process residue historically produced at Kabwe prior to its closure through the washing of newly mined and crushed ore. These have a high combined grade of Lead and Zinc at 17.87%.

 

JORC Mineral Resource estimates on Zinc (Zn) and Lead (Pb) for the Kabwe wash plant tailings are:

 

Mineral Resource Class

Volume(m3)

Dry Bulk Density (t/m3)

Zn(%)

Pb(%)

Dry Tonnage

Contained Tonnes of Metal - Zinc

Contained Tonnes of Metal - Lead

Measured

304,771

1.92

10.66

7.21

573,458

61,147

41,345

 

 

Stockpile 2 The Leach Plant Residue

 

JORC Mineral Resource estimates on Zinc (Zn) and Lead (Pb) for the central section of the leach plant tailings are:

 

Mineral Resource Classification

Zn (%)

Pb(%)

Dry Tonnage

Contained Tonnes of Metal - Zinc

Contained Tonnes of Metal - Lead

Measured

3.88

8.71

2,648,920

102,690

230,810

 

Metallurgical Testwork on the Tailings Stockpile

Following intensive and wide ranging metallurgical investigative testwork, BMR achieved the following extraction efficiencies;

 

Lead and Zinc extractions for the Wash Plant Tailings of 90% Pb and 79% Zn have been achieved. Recoveries for the Leach Plant Residue are in the region of 80% Pb and 50% Zn.

 

Further testwork will focus on finalising the flow sheet, the process design and establishing the quality of the products

 

Other Above Ground Dumps

 

In addition to the aforementioned stockpiles, further aggregate stockpiles from previous mine operations including all surface materials at the Kabwe site, totals an approximate 6,4 million tonnes containing an estimated 356 843 tonnes of zinc and 351 386 tonnes of lead.

 

 This announcement contains inside information for the purposes of Article 7 of Regulation 596/2014

 

23 October 2017

Contacts

Jubilee Platinum plc

Colin Bird/Leon CoetzerTel +44 (0) 20 7584 2155 / Tel +27 (0) 11 465 1913Andrew SarosiTel +44 (0)1752 221937

JSE Sponsor

Sasfin Capital, (a member of the Sasfin group)

Sharon OwensTel +27 (0)11 809 7500

Nominated Adviser

SPARK Advisory Partners LimitedSean Wyndham-Quin/Mark BradyTel: +44 (0)203 368 3555

Broker

Beaufort Securities LimitedJon BellissTel: +44 (0) 20 7382 8300

 

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
JVEOKBDKFBDDDKB
Date   Source Headline
26th Nov 20099:07 amRNSFinal Results
10th Nov 20097:00 amRNSPlacing
14th Oct 20097:00 amRNSDirector Shareholding
13th Oct 20097:00 amRNSFurther grant of mining rights
6th Oct 20099:00 amRNSDirector Shareholding
1st Oct 20097:00 amRNSKabwe Dumps Acquisition Update
31st Mar 20092:00 pmRNSInterim Results
30th Jan 200912:14 pmRNSAGM Statement
30th Dec 200812:00 pmRNSFinal Results
16th Dec 20087:00 amRNSPositive Assay Results
24th Jul 20081:36 pmRNSTotal Voting Rights
8th Jul 20087:00 amRNSZambian Mining & Processing R
27th Jun 20085:00 pmRNSStatement re: Share Price Mov
28th Mar 20087:01 amRNSInterim Results
6th Mar 200812:53 pmRNSChange of Name
13th Feb 20082:24 pmRNSGeneral Meeting
21st Dec 20073:22 pmRNSFinal Results
20th Nov 20072:04 pmRNSDirector/PDMR Shareholding
19th Nov 200710:22 amRNSHolding(s) in Company
9th Nov 20073:00 pmRNSHolding(s) in Company
9th Nov 20077:01 amRNSNew Activity / Funds raised
26th Oct 200710:35 amRNSHolding(s) in Company
5th Sep 20071:55 pmRNSHolding(s) in Company
20th Aug 20077:01 amRNSAIM Rule 26
30th Jul 200711:25 amRNSCompany Update
4th May 20071:57 pmRNSBoard Change
29th Mar 20071:14 pmRNSInterim Results
27th Mar 20071:50 pmRNSVoice Quality Software Stack
29th Dec 200611:25 amRNSPreliminary Results
22nd Dec 20069:59 amRNSTotal Voting Rights
24th Nov 20067:00 amRNSProduct Launch
23rd Nov 20067:00 amRNSConference Attendance
11th Sep 20067:01 amRNSVoice Quality Software
5th Jul 20068:00 amRNSICB Reclassification
31st Mar 20064:09 pmRNSInterim Results
6th Mar 200612:40 pmRNSSale of shareholding
21st Feb 20067:00 amRNSRe: Licensing Agreement
27th Jan 200611:12 amRNSAGM Statement
27th Jan 200611:09 amRNSRe: Placement of shares
23rd Dec 200512:03 pmRNSAnnual Report and Accounts
22nd Dec 200512:00 pmRNSFinal Results
29th Nov 20057:00 amRNSRe Joint Venture
3rd Oct 20057:00 amRNSContract Update
3rd Oct 20057:00 amRNSRe Contract
25th Jul 20054:02 pmRNSHolding(s) in Company
11th Jul 20057:00 amRNSIssue of Equity
27th Jun 20057:00 amRNSNew Contract Awarded
16th Jun 20057:00 amRNSC3 Product Delivery completed
10th Jun 200512:30 pmRNSGrant of Share Options
31st May 20059:00 amRNSTechnology Supply Agreement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.