Corporate and Operations Update

29 Oct 2013 09:14

RNS Number : 6202R
Bushveld Minerals Limited
29 October 2013
 



29 October 2013

 

Bushveld Minerals Ltd

("Bushveld" or the "Company")

Corporate and Operations Update

 

 

Bushveld Minerals Limited (AIM: BMN), a mineral development company focused on iron and tin projects in southern Africa, is pleased to provide an operations and corporate update on its Bushveld Iron Ore and Marble Hall Tin Projects in Limpopo Province, South Africa. 

 

Highlights:

1. Corporate Update

1.1. Obtala & Blackrock Share disposal

· Obtala and Blackrock reduce their shareholding to below the disclosable levels of 5%

· Increase in the Company's shareholder base leading from the Obtala and BlackRock disposals and acceptances by Lemur shareholders of the Bushveld bid for Lemur

1.2. Lemur Bid

· Bushveld's all share bid for Lemur Resources Limited will close finally on 01 November, 05:00 PM (Australian WST)with no extension

· Bushveld has to date acquired a controlling interest in Lemur, with a shareholding of 54.16% and allotted shares in Bushveld to Lemur shareholders that accepted the Bushveld offer

2. Bushveld Iron Ore Project: Increase in strike of P-Q Zone Deposit

· Strike of the mineralisation of the P-Q Zone increased by 3.7 km onto the adjoining farms Schoonoord 786 LR and Bellevue 808 LR. (an increase of 67% in the total strike length)

- Drilling on southern extensions of the P-Q mineralisation confirms mineralisation (grade and extent) for an additional 2.3 km

- Assays of the BV-1 borehole (dating from drilling in 1991) extend known strike of the P-Q Zone by a further 1.4 km southwards

· Assays being incorporated into a resource model to upgrade the resource and to be published by 30 November 2013

3. Greenhills Resources: Initial drilling for Marble Hall Tin Project confirms tin presence

· Initial drilling at the Marble Hall Tin Project confirms the presence of a mineralised breccia including an intersection of 1.39% tin (Sn) over 1.75 m.and 0.88% Sn over 1.00 m

 

1. Corporate Update

1.1. Obtala and Blackrock reduce respective shareholdings in Bushveld

Subsequent to the RNS released by the Company on 10 October 2013 regarding a share price movement, the Company established that the substantial share trading volumes were triggered by the sale of shares held by Obtala Resources Limited and Blackrock.

Notwithstanding the impact of these share trades on the Company's share price, the Company now benefits from increased liquidity and a much wider share ownership. Shareholders above the disclosure threshold of 5% now hold an aggregate 56% of the company, while the ten largest shareholders hold 77.99% of the Company compared to more than 95% prior to the Share disposal.

Commenting on this Fortune Mojapelo, the Company CEO, said, "While disappointed by the manner of the on-market share disposal of the last few weeks, particularly considering the existing orderly market agreement that Obtala signed with the Company, we nonetheless welcome the resultant more diverse and active shareholder base and believe that this will lead to improved liquidity, ensuring a Bushveld share that is more responsive to the positive developments in the Company's projects."

1.2. Bushveld bid for Lemur Resources Limited

The Bushveld all-share bid for Lemur Resources Limited is set to finally close on 01 November 2013 at 5:00 PM (Australian WST). To date Bushveld has acquired a shareholding of 54.17% in Lemur Resources Limited in the now unconditional bid.

Following the closing of the bid, the Company intends to promptly complete a comprehensive strategic review on Lemur in the coming weeks and will update the market accordingly.

Fortune Mojapelo commented, "Again, we welcome all the Lemur shareholders that accepted the Offer onto the Bushveld register and look forward to working with and for them as we grow our Company into a successful diversified portfolio of attractive assets."

2. Bushveld Iron Ore Project: P-Q Deposit

Results of drilling of the P-Q Zone on the farms Schoonoord and Bellevue

The assay results received for four boreholes drilled on the recently acquired farms Schoonoord 786 LR and Bellevue 808 LR, confirm the continuity of the P-Q mineralisation for an additional 2.3 km to the south. In addition results from the Company's logging of the borehole BV-1, drilled in 1991 on the farm Bellevue 808 LR by the Council for Geoscience and located 1.4 km further south of borehole SN003 drilled on Schoonoord confirm the continuity of the same mineralisation for a further 1.4 km resulting in an aggregate strike extension of 3.7 km. This represents a 67% increase to the existing strike of 5.5 km on which the current resource of 718 mt is based.

In the BV-1 borehole, the P-Q Zone was intersected at a depth of ~600 m.

All the above boreholes intersected the P-Q mineralisation. These intersections show strong similarities to the previously drilled boreholes on which the current Mineral Resource Estimate is based, thereby reinforcing management's belief in the continuity of the P-Q Zone. These results are expected to be incorporated into an updated Mineral Resource Estimate for the P-Q Zone. Summaries of the intersections are presented below.

BHID

BH

Depth

Top of P-Q

Base of P-Q

P-Q width* (m)

Avg Fe

%

Avg

Fe2O3

%

Avg

V2O5

%

Avg

TiO2

%

Avg

P2O5

%

Avg

SiO2

%

Avg

Al2O3

%

SN01

210.14

137.23

171.74

32.82

30.89

44.19

0.18

10.85

0.07

25.67

10.19

SN02

200.00

113.22

152.00

36.88

27.21

38.92

0.16

9.69

0.06

28.56

12.66

SN03

175.47

109.55

151.65

28.60

33.48

47.89

0.20

9.91

0.06

23.75

10.92

BV-1

2949.5

581.36

618.50

35.32

35.59

46.63

0.19

9.41

0.04

21.33

9.71

\* True widths after correcting for a dip of 18˚, and excluding any granite sills.

Note: Average grades exclude granite sills, but include the Ti-magnetite barren parting between the P and Q Ti-magnetite layers. The SN boreholes are numbered from north (SN01) to south (SN03) along strike on the farm Schoonoord, with a spacing of ~500 m between them.

Fortune Mojapelo elaborated on these results, saying: "The results validate our belief in the potential of the Bushveld Iron Ore project to host more than 1 billion tonnes. The significance of the anticipated resource increase lies in the opportunity to grow the scale of the project without increasing the stripping ratios and thus cost of mining. It also presents the opportunity to maintain the current scale of operations envisaged in the scoping study released in April 2013, while lowering the overall costs by mining to shallower depths along longer strike and thereby reducing the stripping ratio."

 

3. Greenhills Resources: Marble Hall Tin Project

Results of initial drilling at the Marble Hall Tin Project

Following the acquisition of 50% of the Marble Hall Tin Project (update 26 September 2013), the Company has completed the drilling of three initial boreholes. Two of these boreholes intersected breccia zones (known to host tin mineralisation in the area), and assay results confirm the presence of zones of significant tin mineralisation, with borehole VLK2 containing three mineralised breccia zones. Owing to poor drilling conditions, a third borehole had to be abandoned and did not reach the breccia zone. A summary of the intersections is presented below.

BHID BH Depth From (m) To (m) Width* (m) Avg Sn (%)

VLK1 60.00 27.00 28.06 1.06 0.12

VLK2 85.30 51.76 53.00 1.24 0.17

VLK2 85.30 58.30 59.30 1.00 0.88

VLK2 85.30 64.35 66.10 1.75 1.39

* The breccia is subhorizontal in orientation and thus the intersections represent true widths.

The presence of two intersections bearing significant tin grades (0.88% Sn and 1.39% Sn) in borehole VLK2 increases confidence in the historic data available for the deposit. These historical data showed grades in excess of 1% Sn over as much as 5 m. The Company is awaiting approval of a Section 102 application to include additional farms into the licence area. Following this approval, the Company plans to commence further drilling with the aim of defining a maiden Mineral Resource Estimate for the deposit.

Fortune Mojapelo said: "The Marble Hall project presents an opportunity for Bushveld to further grow its tin resource inventory and puts the 50,000 ton contained tin resource inventory well within sights. Being a brownfields project with a historical Pre-Feasibility study completed by Gold Fields in the 1980's already provided us confidence in the project. The above results add to this confidence by confirming the mineralisation levels reported historically. We now look forward to firming these results with further drilling into a JORC-compliant resource and advancing this project along with the Mokopane Tin Project."

 

Enquiries: info@bushveldminerals.com

Bushveld Minerals

Fortune Mojapelo

+27 (0) 11 268 6555

Fox Davies

Jonathan Evans

+44 (0) 20 3463 5000

Tavistock Communications

Jos Simson/ Nuala Gallagher

+44 (0) 20 7920 3150

Tielle Communications

Stéphanie Leclercq

+27 (0) 83 307 7587

This information is provided by RNS

The company news service from the London Stock Exchange

- ENDS -

 

 

Notes to the editor

 

Bushveld Minerals Limited is a mineral development company with a portfolio of iron, tin and coal assets in Southern Africa. The Company owns the Bushveld Iron Ore Project and Mokopane Tin Project, both located on the northern limb of the Bushveld Complex, South Africa. In addition, Bushveld has a controlling 53.67% interest in ASX Lemur Resources that owns the Imaloto coal project in Madagascar.

 

Bushveld was admitted to the AIM Market of the London Stock Exchange in March 2012.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUKAKROAARURA
Date   Source Headline
16th May 20257:00 amRNSCancellation - Bushveld Minerals Limited
15th Apr 20254:28 pmRNSAppointment of Liquidators & Resignation of Nomad
11th Apr 20257:57 amRNSNotice of appointment of liquidators
15th Jan 20256:00 pmRNSBushveld Minerals
16th Dec 20247:15 amRNSBusiness Rescue and Operations Update
4th Dec 20247:00 amRNSResignation of Directors
29th Nov 20247:00 amRNSDefault on Shareholder Loan Repayment by Vanchem
19th Nov 202410:01 amRNSAppointment of Business Rescue Practitioners
18th Nov 20247:30 amRNSSuspension - Bushveld Minerals Limited
18th Nov 20247:00 amRNSTrading Suspension
8th Nov 20249:25 amRNSQ3 and 9M 2024 Operational Update
1st Nov 20243:05 pmRNSVanchem Sale Update
25th Oct 20242:21 pmRNSOperational Update
18th Oct 20249:18 amRNSDisposal of Interests in Lemur Holdings Limited
17th Sep 20247:00 amRNSInterim Results for Six Months ended 30 June 2024
10th Sep 20247:00 amRNSTurnaround Initiatives Underway
2nd Sep 20244:22 pmRNSOrion Matched Funding Received
14th Aug 20246:00 pmRNSSARB Approval for Orion US$10M Matched Funding
12th Aug 20244:13 pmRNSUS$2 million SPR Debt Funding Received
9th Aug 20249:55 amRNSAgreement re Settlement of SPR Subscription Funds
7th Aug 20244:25 pmRNSAnnual General Meeting Results
7th Aug 20247:00 amRNSDirector/PDMR Shareholding
6th Aug 20247:00 amRNSAnnual General Meeting Statement
31st Jul 20247:00 amRNSQ2 and H1 2024 Operational Update
24th Jul 20244:46 pmRNSHolding(s) in Company - Correction
15th Jul 202412:39 pmRNSDirector/PDMR Shareholding
12th Jul 20244:57 pmRNSDirector/PDMR Shareholding
11th Jul 20245:04 pmRNSPosting of Accounts & Notice of General Meeting
28th Jun 20245:30 pmRNSFinal Results for Year Ended 31 December 2023
28th Jun 20243:29 pmRNSFinancing Update: Orion matched funding of US$10m
28th Jun 20241:17 pmRNSHolding(s) in Company
26th Jun 202412:13 pmRNSHolding(s) in Company
24th Jun 20241:50 pmRNSSPR Funding & Orion 2024 Financing Package Update
31st May 20244:07 pmRNSCCSA Approval for sale of 64% interest in Mokopane
31st May 20241:07 pmRNSResult of Meeting
24th May 20245:53 pmRNSShareholder Correspondence and Questions & Answers
13th May 20247:00 amRNSPosting of Circular and Notice of General Meeting
7th May 20247:00 amRNSProposed conditional disposal of Vanchem
23rd Apr 20247:01 amRNSQ1 2024 Operational & Corporate Update
23rd Apr 20247:00 amRNSMineral Resources and Reserves Annual Update
14th Mar 20249:32 amRNSFurther Update on Outstanding Funds
14th Mar 20247:00 amRNSTR-1 Notification of Major Holdings
7th Mar 20243:00 pmRNSTR-1 Notification of Major Holdings
29th Feb 20245:30 pmRNSFurther Update on Outstanding Funds
16th Feb 20247:08 amRNSFurther update on Outstanding Funds
5th Feb 20247:08 amRNSFull year 2023 Operational Update
2nd Feb 20242:30 pmRNSForm 8.3 of the Takeover Code
1st Feb 20247:00 amRNSCompletion of Convertible Loan Note Refinancing
29th Jan 20244:25 pmRNSResignation of Finance Director
19th Jan 20244:32 pmRNSFurther Update on Outstanding Funds

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.