Mining update

7 Nov 2022 07:00

RNS Number : 4527F
Bens Creek Group PLC
07 November 2022
 

7 November 2022

 

Bens Creek Group plc

 

("Bens Creek" or "Company" or the "Group")

 

Mining update

 

Bens Creek Group plc (AIM:BEN), the owner of a metallurgical coal mine in North America supplying the steel industry, is pleased to announce that preliminary production from the new permit area has been encouraging following commencement of mining on this area at the end of October 2022.

 

The Company was able to produce 2,500 tons of run of mine coal in a single day with a higher clean coal recovery of 62%. Furthermore, the Company can confirm that initial analysis suggests that the coal seam being mined under the new permit is approximately 50 inches which is greater than the coal seam on the Company's original permitted site, which had a coal seam thickness of 38 inches.

 

To accommodate the additional capacity of future production on the new permit area and to attain the optimum recovery levels, Ben's Creek has started to reduce cost and manpower by accelerating the process plant facility upgrades. This will be achieved by the Company modifying the truck dump belt infrastructure and through the integration of an additional dryer into the existing processing plant, which is expected to provide elevated coal recovery and raw throughput capacity of the processing plant facility.

 

As of 7 November 2022, the Company has introduced a second shift on its first highwall miner which will allow the Company to double daily production. The Company can also confirm that the creation of the required benches to support the second highwall miner are progressing quickly. As such the Company will soon be requesting the second highwall miner. The Company has previously stated, in the mine plan agreement with Mega Highwall Mining LLC, that it will then be ready for further production by the end of December 2022. Once the second highwall miner is fully mobilised and operational, the Company intends to introduce a two-shift production schedule on this highwall miner as well.

 

The Company is still reviewing its options with regards to its own highwall miner and it has recently received offers in excess of the purchase price which are currently under consideration.

 

The Company has largely completed the acquisition or rental of all the necessary ancillary mobile equipment with all equipment now being on site except for the highwall miner. This has allowed the Company to move away from contractors to an owner operator model and progress towards full production as a result.

 

The Company is getting ready to initiate an aggressive core drilling program with the objective of improving its metallurgical coal reserve base and expand its recoverable and mineable tons. The Company will be utilising the results from this drilling program to build into the already started third permit application for the surface/highwall miner, as well as two additional underground operations at the same time with this third permit. These advances are important for the Company's future operations at the Bens Creek mine as they are expected to allow the Company to increase productivity and maintain the operational momentum that has been built by the Ben's Creek team.

 

Adam Wilson, Chief Executive Officer of Bens Creek, commented:

 

"The set up to allow us to move from a contracted fleet to an owner operated fleet with two highwall miners is nearly completed. This, together with the remediation of the infrastructure (from what was a previously idle mine) and the commencement on the underground mine for the creation of a first walking super section, is nearing completion. An update on resources and the issue of a new mining permit have taken place at an expedited pace over the last twelve months and we remain confident that 2023 will be a good year for Bens Creek. The regular train deliveries and inventory build are now expected to commence alongside the increased production. As with all mining projects, more production spreads the cost across more tonnage and thus reduces the average unit cost per ton, thereby increasing margins."

 

 

For further information please contact:

Bens Creek Group plc

Adam Wilson, CEO

Murat Erden, CFO

 

+44 (0) 204 558 2300

Allenby Capital Limited (Nominated Adviser and Joint Broker)

Nick Athanas / Nick Naylor / George Payne (Corporate Finance)

Kelly Gardiner (Sales and Corporate Broking)

+44 (0) 203 328 5656

 

Optiva Securities Limited (Joint Broker)

Christian Dennis / Mariela Jaho / Daniel Ingram

+44 (0) 203 137 1902

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCFSSFAMEESEIF
Date   Source Headline
30th Jun 20227:00 amRNSHolding(s) in Company
29th Jun 20222:06 pmRNSSecond Price Monitoring Extn
29th Jun 20222:00 pmRNSPrice Monitoring Extension
29th Jun 202212:46 pmRNSStatement re. share price movement
29th Jun 202211:05 amRNSSecond Price Monitoring Extn
29th Jun 202211:00 amRNSPrice Monitoring Extension
28th Jun 20222:06 pmRNSSecond Price Monitoring Extn
28th Jun 20222:00 pmRNSPrice Monitoring Extension
27th Jun 20227:00 amRNSUpdate on highwall miners
16th Jun 20224:41 pmRNSSecond Price Monitoring Extn
16th Jun 20224:36 pmRNSPrice Monitoring Extension
16th Jun 20227:00 amRNSReserve Base Evaluation
8th Jun 20229:15 amRNSFurther rail delivery
6th Jun 20227:00 amRNSCommencement of rail delivery & loan facility
31st May 20225:00 pmRNSTotal Voting Rights
26th May 20227:00 amRNSUpdate on commencement of underground mining
13th May 20227:00 amRNSExercise of warrants and change to TVR
11th May 20229:01 amRNSDirector/PDMR Shareholding
6th May 20225:35 pmRNSDirector/PDMR Shareholding
6th May 20227:00 amRNSBusiness update, directorate change & option grant
29th Apr 20225:30 pmRNSTotal voting rights and warrants in issue
14th Apr 20227:00 amRNSEntry into coal sub-lease agreement
6th Apr 20227:00 amRNSExercise of warrants and change to TVR
31st Mar 20225:00 pmRNSTotal Voting Rights
21st Mar 20227:00 amRNSExercise of warrants and change to TVR
14th Mar 20225:30 pmRNSStatement regarding Rule 7 lock-in
14th Mar 20227:00 amRNSCoal production and delivery update
28th Feb 20225:00 pmRNSTotal Voting Rights
28th Feb 20224:42 pmRNSSecond Price Monitoring Extn
28th Feb 20224:37 pmRNSPrice Monitoring Extension
28th Feb 20222:05 pmRNSSecond Price Monitoring Extn
28th Feb 20222:00 pmRNSPrice Monitoring Extension
25th Feb 20227:00 amRNSUpdate on wash plant and the second highwall miner
21st Feb 20224:41 pmRNSSecond Price Monitoring Extn
21st Feb 20224:35 pmRNSPrice Monitoring Extension
18th Feb 20227:00 amRNSIssue of a second CLN to raise US$6.0 million
18th Feb 20227:00 amRNSExercise of warrants and change to TVR
7th Feb 20227:00 amRNSExercise of warrants and change to TVR
31st Jan 20225:00 pmRNSTotal Voting Rights
31st Jan 20227:00 amRNSFirst income
28th Jan 20223:19 pmRNSHolding(s) in Company
24th Jan 20227:00 amRNSHolding(s) in Company
18th Jan 20227:00 amRNSPurchase of a second highwall miner for Bens Creek
17th Jan 20224:41 pmRNSSecond Price Monitoring Extn
17th Jan 20224:36 pmRNSPrice Monitoring Extension
17th Jan 20222:05 pmRNSSecond Price Monitoring Extn
17th Jan 20222:00 pmRNSPrice Monitoring Extension
17th Jan 20227:00 amRNSFirst deliveries - Hi Vol B product
14th Jan 20227:00 amRNSExercise of warrants and change to TVR
10th Jan 20227:00 amRNSResult of coal quality analysis - Hi Vol B product

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.