Sonora Lithium Project Update

11 Nov 2019 07:00

RNS Number : 8817S
Bacanora Lithium PLC
11 November 2019
 

Bacanora Lithium plc / Index: AIM / Epic: BCN / Sector: Natural Resources

 

11 November 2019

Bacanora Lithium plc ("Bacanora" or the "Company")

Sonora Lithium Project Update

 

Bacanora Lithium plc (AIM: BCN), the London traded lithium company, is pleased to provide an update on its activities at the Sonora Lithium Project in Mexico ('Sonora' or the 'Project') following the recent completion of the Strategic Investment by leading global lithium company Ganfeng Lithium Co., Ltd. ('Ganfeng').

 

Ganfeng Review and Process Testwork

The Bacanora project team in Mexico continues to progress the final design work for the mine site, infrastructure, concentrator and kiln sections of the processing plant. Representative samples have been sent to Ganfeng in China. Ganfeng's technical review of the hydrometallurgical circuit has commenced with a view to potentially sourcing key sections of the lithium production equipment from their current equipment suppliers in China. This work is expected to be completed in H1 2020. As part of this technical review, both Bacanora and Ganfeng continue to develop testwork programmes for the potential production of other downstream high value lithium products in addition to the battery-grade lithium carbonate used in the Company's feasibility study. The results of this work will be reviewed over the next few months. 

 

The feasibility study indicated highly favourable economic indicators for a battery grade lithium carbonate operation at Sonora, including US$1.25 billion NPV, 26% IRR and operating costs among the lowest in the industry at around US$4,000/t of lithium carbonate (see announcement of 13 December 2017 for further details).

 

Detailed Engineering Design

As previously noted, the Company intends that the three primary parts to its production circuit will be delivered in the following timeframe under individual contracts with associated process guarantees from experienced engineering groups:

·; Engineering and flow sheet testwork for the design of the front-end ore concentrator and mechanical processing is underway for completion in H1 2020

·; Pyrometallurgical engineering, primarily for the kiln designs, is being engineered by Nutec Bickley and final detailed design and process guarantees to be completed in H1 2020

·; The hydrometallurgical plant, including the production of the final battery grade lithium product, will be engineered by Ganfeng themselves due to their proven expertise in this field, with completion in H1 2020

 

Financing

Once Ganfeng completes its review, the Company will deliver final engineering costs for Stage 1 of the Project, following which the Company will look to finalise the funding package for the Project. At this stage, the Company believes that the engineering costs will remain in line with the 2018 Feasibility Study forecast of approximately US$420 million. 

 

The recent 29.99% equity investment by Ganfeng Lithium and their 22.5% investment at the project level, in combination with a combined 100% off-take held by Ganfeng and Hanwa Corporation ('Hanwa') for Stage 1 production of 17,500 tonnes per annum of lithium products at the Project demonstrates the strong support that both these cornerstone investors have shown in Sonora. Combined, Ganfeng and Hanwa have a see-through ownership of more than 50% of Sonora. In the last 18 months, Bacanora has already secured a US$150 million debt facility with RK Mine Finance and continues to explore additional sources of project funding. The 22.5% project investment and 29.99% equity investment from Ganfeng, in addition to ongoing support from Bacanora's other shareholders and off-takers, ensures a very solid position for finalising the project funding stage of the Sonora development.

 

The Company had US$40 million of cash at the end of October 2019, which will enable Bacanora to commence the bulk earthworks on site in H1 2020 and start to upgrade the primary access road to site. The Company will also be able to use part of these funds to place the initial orders for some of the longest lead-time items in the concentrator, pyrometallurgy and hydrometallurgy sections of the lithium plant.

 

General Market Conditions

There have been a number of media reports over the past few months highlighting the impact of an over-supply of lower grade bulk spodumene concentrates from Australia into the Asian lithium converter markets. Recently a number of these projects have been delayed, closed, reported decreased production or put on care and maintenance. With the majority of these concentrate operations being at the higher cost level, this supports the Bacanora strategy of developing a fully integrated lithium project that produces a final battery grade lithium product at much lower costs rather than an intermediate concentrate.

 

Bacanora CEO Peter Secker said "Recent research reports predict the lithium industry would need US$30 billion in investment in upstream capacity to meet its forecast of 1 million tonnes of supply by 2025 (a threefold increase on current levels). In order to secure funding, any new lithium project needs to be low on the operational cost-curve, without having to rely on by-product credits to artificially lower that cost per tonne. A project also needs to have reliable engineering cost estimates. A project needs to be of sufficient scale, in a location with a favourable environmental and political climate and deliver a high-grade end product. The Sonora Lithium Project is one of the very few projects globally that can deliver on all of these factors."

 

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014.

 

**ENDS**

For further information please visit www.bacanoralithium.com or contact:

 

Bacanora Lithium plc

Peter Secker, CEO

Janet Blas, CFO

info@bacanoralithium.com

Cairn Financial Advisers LLP, Nomad

 

Sandy Jamieson / Liam Murray

 

+44 (0) 20 7213 0880

Citigroup Global Markets, Broker

Tom Reid / Patrick Evans / Matthew Kenney

+44 (0) 20 7986 4000

Canaccord Genuity, Broker

 

James Asensio

 

+44 (0) 20 7523 8000

St Brides Partners, Financial PR Adviser

Frank Buhagiar / Megan Dennison

+44 (0) 20 7236 1177

 

ABOUT BACANORA LITHIUM:

Bacanora owns ten mining concession areas covering approximately 100 thousand hectares in the northeast of Sonora State in Mexico. Seven of these ten mining concessions (the 'Sonora Lithium Project'1) were included in the Feasibility Study announced 12 December 2017. The Company, through drilling and exploration work to date, has established a Measured plus Indicated Mineral Resource estimate of over 5 Mt (comprising 1.9Mt of Measured Resources and 3.1Mt of Indicated Resources) of LCE2 and an additional Inferred Mineral Resource of 3.7 Mt of LCE. The Company's Feasibility Study has established Proven Mineral Reserves (in accordance with NI 43-101) of 1.67 Mt and Probable Mineral Reserves of 2.85 Mt LCE and confirmed the economics associated with becoming a 35,000 tpa lithium carbonate and 30,000 tpa SOP producer in Mexico. In addition to the Sonora Lithium Project, the Company also has a 50% interest in the Zinnwald Lithium Project and the Falkenhain Licence in southern Saxony, Germany. Each of the Zinnwald Lithium Project and the Falkenhain Licence are located in a granite hosted Sn/W/Li belt that has been mined historically for tin, tungsten and lithium at different times over the past 300 years. The strategic location of the Zinnwald Lithium Project and the Falkenhain Licence provides close geographical proximity to the German automotive and downstream lithium chemical industries.

 

1. Sonora Lithium ltd ("SLL") is the operational holding company for the Sonora Lithium Project and owns 100% of the La Ventana concession. The La Ventana concession accounts for 88% of the mined ore feed in the Sonora Feasibility Study which covers the initial 19 years of the project mine life. SLL is owned 77.5% by Bacanora and 22.5% by Ganfeng Lithium Ltd. SLL also owns 70% of the El Sauz and Fleur concessions, which are held by Mexilit S.A. de C.V. ('Mexilit').

2. LCE = lithium carbonate (Li2CO3) equivalent; determined by multiplying Li value in percent by 5.323 to get an equivalent Li2CO3 value in per cent. Use of LCE is to provide data comparable with industry reports and assumes complete conversion of lithium in clays with no recovery or process losses.

 

IMPORTANT NOTICE

The contents of this announcement have been prepared by and are the sole responsibility of Bacanora.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDURSRRKUAAAAA
Date   Source Headline
8th Oct 20207:00 amRNSConditional Sale of interest in Deutsche Lithium
6th Oct 20202:05 pmRNSSecond Price Monitoring Extn
6th Oct 20202:00 pmRNSPrice Monitoring Extension
6th Oct 202011:06 amRNSSecond Price Monitoring Extn
6th Oct 202011:00 amRNSPrice Monitoring Extension
2nd Oct 20207:00 amRNSIssuance of Options, RSUs & Historic RSUs Vesting
30th Sep 20207:01 amRNSInterim Report
30th Sep 20207:00 amRNSProposed sale of holding in Zinnwald
10th Sep 20207:00 amRNSSonora Operational Update
18th Jun 20203:15 pmRNSTransaction Notification
11th Jun 202011:46 amRNSResult of AGM
28th May 20207:00 amRNSSonora Lithium Project and Covid-19 Update
18th May 20207:00 amRNSNotice of AGM
28th Apr 202011:05 amRNSSecond Price Monitoring Extn
28th Apr 202011:00 amRNSPrice Monitoring Extension
20th Apr 20207:00 amRNSAppointment of Non-Executive Director
20th Apr 20207:00 amRNSCEO appointed as NED of Bacanora Lithium plc
8th Apr 202011:00 amRNSPrice Monitoring Extension
25th Mar 202011:05 amRNSSecond Price Monitoring Extn
25th Mar 202011:00 amRNSPrice Monitoring Extension
24th Mar 20202:06 pmRNSSecond Price Monitoring Extn
24th Mar 20202:01 pmRNSPrice Monitoring Extension
23rd Mar 20207:00 amRNSSonora Lithium Project and Covid-19 Update
20th Mar 20204:43 pmRNSSecond Price Monitoring Extn
20th Mar 20204:36 pmRNSPrice Monitoring Extension
18th Mar 20202:06 pmRNSSecond Price Monitoring Extn
18th Mar 20202:01 pmRNSPrice Monitoring Extension
2nd Mar 20207:00 amRNSFinal Results
17th Feb 20207:00 amRNSAmendment to JV for the Zinnwald Lithium Project
12th Dec 201912:19 pmRNSResult of AGM
12th Dec 20197:00 amRNSAGM Update
2nd Dec 20195:15 pmRNSHolding(s) in Company
2nd Dec 20195:12 pmRNSHolding(s) in Company
25th Nov 20197:00 amRNSIssue of Equity to Cornerstone Shareholder
18th Nov 201911:00 amRNSPrice Monitoring Extension
18th Nov 20197:00 amRNSNotice of AGM
11th Nov 20197:00 amRNSSonora Lithium Project Update
28th Oct 20197:00 amRNSGrant of Options and Restricted Share Units
22nd Oct 20194:50 pmRNSHolding(s) in Company
22nd Oct 20194:50 pmRNSHolding(s) in Company
21st Oct 201911:41 amRNSHolding(s) in Company
21st Oct 20197:00 amRNSFinal Results
14th Oct 20197:00 amRNSCompletion of Strategic Investment by Ganfeng
13th Sep 20197:00 amRNSDirectorate Change
20th Aug 20197:00 amRNSUpdate on Strategic Investment by Ganfeng Lithium
9th Aug 20194:35 pmRNSPrice Monitoring Extension
1st Aug 20197:00 amRNSUpdate on Strategic Investment by Ganfeng
28th Jun 20194:41 pmRNSSecond Price Monitoring Extn
28th Jun 20194:35 pmRNSPrice Monitoring Extension
28th Jun 20193:58 pmRNSInvestment & Offtake Agreement Signed with Ganfeng

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.