Second quarter operations update

31 Jul 2017 07:00

RNS Number : 5068M
Atalaya Mining PLC
31 July 2017
 

31 July 2017

Atalaya Mining Plc

("Atalaya" or the "Company")

Second Quarter 2017 Operations Update

 

Atalaya Mining plc (AIM:ATYM, TSX:AYM), the European mining and development company, announces its operations update for the three months ended June 30, 2017.

 

PROYECTO RIOTINTO

 

Second Quarter

First Quarter

Full year forecast

2017

2016

2017

2017

Ore mined

(M tonnes)

2.3

1.3

2.3

9.5 - 9.8

Waste mined

(M tonnes)

4.6

3.8

4.3

18.1 - 18.2

Ore milled

(M tonnes)

2.2

1.3

2.2

9.5

Cu grade

(%)

0.49

0.44

0.48

0.49 - 0.51

Cu recovery

(%)

85.09

79.80

84.63

79 - 82

Cu production

(tonnes)

9,058

4,442

8,805

34,000 - 40,000

 

Production results at Proyecto Riotinto have improved compared to the previous quarter and were in line with targets for the quarter ended June 30, 2017. The operation reports throughput rate of 2.2 million tonnes of ore processed, similar to the previous quarter with an improvement in the recovery rate to a record of 85.09%. The overall tonnage processed was affected negatively by the replacement of one of the main transformers to improve energy efficiencies. Full year forecasts for copper production remain as previously guided at 34,000 - 40,000 tonnes.

 

Mining operations are running at an increasing rate quarter-on-quarter, as a result of adjusted drilling and blasting parameters. On a combined basis, ore, waste and marginal ore amounted to 2.8 Mm3 in Q2 2017 versus 2.5 Mm3 in Q1 2017. The mining contractor has launched a replacement programme for the mining fleet. New loaders and trucks are expected to be delivered to site over the next two quarters in anticipation of a potential increase in mining rates. Additionally, modifications to the primary milling circuit, which includes a pebble crusher in closed circuit with the primary mill, have already reported better milling efficiencies.

 

The Company continues to implement initiatives to reduce operating costs of the mine such as adding additional rougher flotation capacity in order to increase plant recoveries and installing a partial plastic lining to parts of the tailings pond to improve water recycle management.

 

A number of dust emission mitigation measures have been developed over the last two quarters with positive results reported. Dust emissions were significantly reduced compared with previous indicators. This initiative will be complete at the end of the year with the installation of a dome covering the coarse ore stockpile. At the end of the quarter, the Cerro Colorado pit was nearly dewatered with only 92,000 m3 of water remaining.

 

On-site concentrate inventories at the end of the quarter were reduced to minimum levels. All concentrate in stock at the beginning of the quarter and produced during the quarter were delivered to the port at Huelva. Concentrate sales were not affected by disruptions reported at other ports across Spain.

 

Copper prices continued to rise during the quarter with an average realised price per pound of copper payable of $2.61/lb compared with $2.27/lb in Q4 2016 and $2.41/lb in Q1 2017 and average market copper price in the quarter of $2.57/lb.

 

Management expect AISC to be in line with previous quarters with the full year forecast as previously guided in the range of $1.90/lb to $2.10/lb.

 

The good performance of the operations and stable copper prices allowed the company to continue to reduce its working capital deficit. This cash generation allowed the full payment of the old Social Security debt (€16.9m) that had been inherited with the mining concession. The Company filed a formal claim in the Administrative Court, relating to the previously announced government grant of €8.8m and has fully written off the amount in its financial statements.

 

Near-mine exploration drilling continued from the previous quarter with a programme to test the lateral extension of Filon Sur. With the programme now essentially complete the exploration block model has been updated with results to be part of the resources and reserves update that will form part of the studies related to the Expansion to 15 Mtpa Project. The in-fill drilling campaign at Cerro Colorado was mainly centred in the north-western extension of the pit where better than anticipated mineralised intervals and grades have been discovered. This campaign is targeting inferred resources with the objective of increasing confidence levels and potential reclassification.

 

As part of the Company's Corporate Social Responsibility initiatives a significant archaeological programme was launched in June 2017 to study a number of archaeological sites including Cortalago, a Roman mining settlement of relevance. The programme is expected to last for 12 months.

 

PROYECTO TOURO

 

The Company has signed an option agreement to acquire exploration concessions that cover 122.7 km2 immediately surrounding Proyecto Touro, where mineralised copper occurrences are documented. An ambitious exploration programme and budget are under consideration for Board approval.

 

Permitting of Proyecto Touro is progressing according to schedule. Studies and applications were submitted at the end of the quarter to the regional authorities for review and evaluation. Consultations with different administrative bodies have been held and local and regional stakeholders have been engaged in the process, with positive feedback received.

 

As previously reported, two important milestones have been achieved at Proyecto Touro: the first was the successful completion of metallurgical test-work which has demonstrated that high grade clean concentrates and high recovery rates can be achieved. The second was the completion of 26,557 m of exploration and in-fill drilling which will provide the basis of an NI 43-101 technical report.

 

The technical report is progressing ahead of schedule and is at an advanced stage of development. It is expected to be at a pre-feasibility level of detail in the near future, with completion brought forward to the beginning of Q4 from the original estimate of the end of FY 2017.

 

Alberto Lavandeira, CEO commented:

"I am pleased to be able to report on a successful quarter for the business. Copper production levels at Proyecto Riotinto have increased and we remain confident in our full year production target of 34,000-40,000 tonnes. Ongoing upgrades and developments at Proyecto Riotinto are producing encouraging results, as the Company continues to expand its operations and commercial production capabilities. The progress made during the quarter with Proyecto Touro also gives us increased confidence in the viability and scope of a potential second operating mine. We look forward to further improvements with both projects during the course of the second half of the year."

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

 

 

Contacts:

Newgate Communications

Charles Chichester / James Ash / James Browne

+44 20 7680 6550

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch / Neil Haycock / Tom Rider

+44 20 7236 1010

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDRMMPTMBJJBPR
Date   Source Headline
13th Jun 20138:51 amRNSFunding Update
3rd Jun 20137:00 amRNSPermitting Update
30th May 20137:00 amRNSInvestor Briefing
23rd May 20137:00 amRNSPermitting Update
17th May 20133:00 pmRNSNotice of AGM
14th May 20133:03 pmRNSQuarterly Financial Report
23rd Apr 20137:00 amRNSEMED Mining at Master Investor
17th Apr 20137:00 amRNSQuarterly Operational Update
16th Apr 20137:00 amRNSTailings Project Update
15th Apr 20137:00 amRNSPermitting Update
4th Apr 201310:59 amRNSExercise of Options
2nd Apr 20137:00 amRNSExposure to Cyprus Bank Restructuring
25th Mar 20135:47 pmRNSAmendment of Option Agreements
25th Mar 20137:00 amRNSFinal Results
21st Mar 20133:38 pmRNSRio Tinto Copper Project Update
18th Mar 20131:05 pmRNSProposed Levy on Deposits in Cyprus
18th Feb 20137:30 amRNSEMED Mining completed an updated Technical Report
16th Jan 20137:00 amRNSQUARTERLY OPERATIONAL UPDATE
9th Jan 20137:00 amRNSShareholder Briefing
19th Dec 20129:27 amRNSResult of GM and Rio Tinto Project Update
11th Dec 20127:00 amRNSInvestor Briefing
28th Nov 201210:00 amRNSDespatch of Circular and EGM
22nd Nov 20122:00 pmRNSApproval of Interim Mining Lease Area in Slovakia
15th Nov 201210:21 amRNSRio Tinto Site Visit
14th Nov 20123:00 pmRNSQuarterly Financial Results
14th Nov 20127:00 amRNSEMED Arranges a US$50 Million Funding Package
18th Oct 20127:00 amRNSUpdate of Progress at Rio Tinto Copper Project
2nd Oct 20124:35 pmRNSReceipt of AAU public comments report
1st Oct 20127:00 amRNSAppointment of Non-Executive Director
27th Sep 20129:10 amRNSQUARTERLY OPERATIONAL UPDATE
19th Sep 20127:00 amRNSSlovakia Update
4th Sep 20127:00 amRNSEMED Mining progresses towards production
31st Aug 20121:00 pmRNSCompletion of acquisitions of remaining land
20th Aug 20121:30 pmRNSCompletion of US$5m Equity Subscription by XGC
7th Aug 20127:00 amRNS2012 Interim Results
3rd Aug 20127:00 amRNSLand Acquisition
16th Jul 20127:00 amRNSEMED MINING QUARTERLY OPERATIONAL UPDATE
9th Jul 20127:00 amRNSAgreement With Owner of Lands
26th Jun 20127:00 amRNSInvestor Briefing
21st Jun 20121:30 pmRNSIssue of equity following warrant exercise
18th Jun 20127:00 amRNSInvestors Briefing Update
13th Jun 20121:31 pmRNSResult of AGM
13th Jun 20121:30 pmRNSAGM Statement
18th May 201212:30 pmRNSNotice of AGM
14th May 20127:00 amRNSEMED Mining Quarterly Financial Report
10th May 20127:00 amRNSEMED Mining Report Detva Gold Project Progress
19th Apr 20121:09 pmRNSExercise of Employee Share Options
11th Apr 20127:00 amRNSNominated Adviser to Change Name
3rd Apr 20127:00 amRNSEMED Quarterly Update
27th Mar 20127:00 amRNSFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.