The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 430.50
Bid: 430.50
Ask: 432.50
Change: 0.00 (0.00%)
Spread: 2.00 (0.465%)
Open: 0.00
High: 0.00
Low: 0.00
Prev. Close: 430.50
ATYM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Second Quarter 2018 Operations Update

16 Jul 2018 07:00

RNS Number : 6117U
Atalaya Mining PLC
16 July 2018
 

16 July 2018

Atalaya Mining Plc

("Atalaya" or the "Company")

Second Quarter 2018 Operations Update

 

Atalaya Mining Plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the second quarter of 2018.

 

PROYECTO RIOTINTO

 

 

Second quarter

First quarter

Full year guidance

2018

2017

2018

2018

Ore mined

(M tonnes)

2.6

2.3

2.6

9.7

Waste mined

(M tonnes)

4.8

4.6

5.4

16.5

Ore milled

(M tonnes)

2.5

2.2

2.2

9.6

Cu grade

(%)

0.48

0.49

0.48

0.48

Cu recovery

(%)

87.31

85.09

88.47

84 - 86

Cu production

(tonnes)

10,446

9,058

9,441

37,000 - 40,000

 

Copper production at Proyecto Riotinto for Q2 2018 has increased to 10,446 tonnes from 9,058 tonnes reported in Q2 2017, and 9,441 tonnes in Q1 2018, representing an increase of 15% and 11% respectively. This quarter's copper production replaces Q1 2018's as the second highest quarterly production on record.

 

In terms of ore milled, 2.5 million tonnes were processed in the quarter, the highest ever quarterly throughput. Copper head grade was in line with expectations. The increase in copper production during the quarter is mainly attributable to the high volume of ore milled with above-budgeted metallurgical recovery rates, averaging 87.31%. Processing throughput was better than expected mainly due to high utilisation rates.

 

The Company maintains its previously stated copper production guidance for 2018 of 37,000 - 40,000 tonnes.

 

Mining operations are progressing to plan and at similar levels to previous quarters. On a combined basis, ore, waste and marginal ore amounted to 2.6 million m3 in Q2 2018 versus 3.0 million m3 in Q1 2018. After the heavy rains in March, mining operations returned to the original mining plan from May onwards.

 

As part of the Company's continuous improvements programme, a cone crusher has been installed and it will operate as a secondary crusher. It is expected to become operational during Q3 2018. As previously reported, modifications to current screening and crushing arrangements are under evaluation as part of a de-bottlenecking exercise. Structural steel fabrication of the dome to cover the coarse ore stockpile has been completed and fully delivered to site. Construction is expected to be completed before the end of Q3 2018.

 

Dewatering of the Atalaya pit is ongoing as previously reported. Dewatering of Cerro Colorado pit after heavy rains in March was completed in mid-May 2018 with pumping systems now on standby.

 

On-site concentrate inventories at the end of the quarter were approximately 2,089 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva. 

 

Copper prices increased during the quarter with an average realised price per pound of copper payable, including the QPs closed in the period, of $3.12/lb compared with $3.03/lb in Q1 2018. The average spot copper price during the quarter was $3.12/lb. The realised price during the quarter excluding QPs was approximately $3.14/lb.

 

Cash operating costs and all-in sustaining costs ("AISC") for Q2 2018 are expected to be within the 2018 cost guidance ranges previously provided. Further details on costs will be provided with the Q2 Financial Statements to be reported in September 2018.

 

A NI 43-101 compliant technical report on an updated resources and reserves estimate for Proyecto Riotinto was released on 9 July 2018. Highlights of the report include a 29% increase in open pit proven and probable mineral reserves at Cerro Colorado and a 21% increase in contained copper, with a reduction of the average strip ratio from 1.95:1 to 1.43:1.

 

Exploration focus has now turned to the underground potential of the remaining massive sulphides below Atalaya pit. A drilling campaign is now underway and is expected to last until June 2019.

 

EXPANSION TO 15 Mtpa AT PROYECTO RIOTINTO

 

The expansion project to 15 Mtpa is progressing according to schedule with engineering heading to completion and site construction activities picking up. Overall progress completion at the end of the reporting quarter was 41%. Procurement has progressed to 38% completed and engineering to 82% completed. Earthworks are well advanced and are expected to be completed by mid-Q3 2018. Civil engineering works are progressing with main activities now concentrated on the new SAG mill area. Structural steel works are ongoing in the flotation area. Installation of mechanical equipment has started in the concentrate handling area. The milling area is the critical path to completion. The expansion project is scheduled for mechanical completion at the end of Q2 2019.

 

PROYECTO TOURO

 

Permitting of Proyecto Touro continues as anticipated with good progress made on addressing additional studies from the regional administration. During the quarter, efforts were concentrated on progressing detailed reports to address certain project improvements and recommendations from the public hearing process. These reports, including those received recently, are now expected to be submitted to the authorities before the end of Q3 2018.

 

During the quarter, the Company announced the completion of a pre-feasibility study ("PFS") for the proposed open pit mine and concentrator at Proyecto Touro. The PFS report was prepared using the headings of, and guidance set out in the NI 43-101 report. Highlights of the PFS report are:

· 392,000 tonnes of contained copper in P&P reserves;

· Average yearly production of 30,000 tonnes copper and 70,000 ounces of silver in concentrate;

· Pre-production capital expenditure of $165 million;

· All-in sustaining costs of US$1.85/lb of payable Cu net of silver credits; and

· NPV post-tax at 8% discount rate of $180 million using long term copper price of US3.00/lb.

 

Alberto Lavandeira, CEO commented:

"This has been an operationally productive quarter which has delivered copper production above 10,000 tonnes, providing an excellent run-rate for the quarter. The efforts resulted in excellent throughput rates at the plant with better-than-budget recovery rates. The Company has completed two NI 43-101 technical reports, which are fully supportive of our growth plans and reinforce our projects' long-term potential. The expansion to 15Mtpa is progressing at full speed with site activities picking up and we remain well on track for mechanical completion at the end of Q2 2019." 

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

Newgate Communications

Elisabeth Cowell / James Ash / James Browne

+44 20 7680 6550

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch / Neil Haycock / Tom Rider

+44 20 7236 1010

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDBXLFFVDFXBBZ
Date   Source Headline
10th May 20127:00 amRNSEMED Mining Report Detva Gold Project Progress
19th Apr 20121:09 pmRNSExercise of Employee Share Options
11th Apr 20127:00 amRNSNominated Adviser to Change Name
3rd Apr 20127:00 amRNSEMED Quarterly Update
27th Mar 20127:00 amRNSFinal Results
19th Mar 201211:00 amRNSIssue of Equity
16th Mar 201212:14 pmRNSIssue of Equity
12th Mar 201212:00 pmRNSPassing of Resolutions
5th Mar 20127:00 amRNSMandate of Goldman Sachs for $175 million finance
21st Feb 20121:59 pmRNSIssue of Equity
17th Feb 20122:04 pmRNSDespatch of Circular and Notice of EGM
9th Feb 201212:00 pmRNSAPPOINTMENT OF NON-EXECUTIVE DIRECTOR
6th Feb 20128:14 amRNSProposed Subscription, Support and Arrangements
16th Jan 20127:00 amRNSQuarterly Operational Update
9th Jan 201212:15 pmRNSCorrecting Announcement re RCF and RMB
3rd Jan 201210:00 amRNSNon-Exercise of Option over Regua Tungsten Deposit
30th Dec 20117:00 amRNSIssue of Share Options
28th Dec 20112:57 pmRNSConversion of Loans
5th Dec 20117:00 amRNSProject Rio Tinto Update
1st Dec 20117:00 amRNSAppointment Of Non Executive Director
23rd Nov 20117:00 amRNSProject Rio Tinto Update
10th Nov 20117:00 amRNSQuarterly Financial Results
7th Nov 20117:00 amRNSFinancing Proposals Received for Rio Tinto Mine
27th Oct 20117:00 amRNSProject Rio Tinto Update
12th Oct 20117:00 amRNSPolitical Support for Rio Tinto Mine
6th Oct 20117:00 amRNSQuarterly Operational Update
5th Oct 20117:00 amRNSQuarterly Investor Briefing
4th Oct 20117:00 amRNSStatement Regarding First Private Clients Ltd
23rd Sep 20117:00 amRNSIssue of Shares
6th Sep 20112:05 pmRNSPermitting Update
11th Aug 20117:00 amRNSHalf Yearly Report
18th Jul 20114:12 pmRNSQuarterly Operational Update
21st Jun 20117:00 amRNSDirectors Dealings
16th Jun 20115:29 pmRNSResult of AGM
16th Jun 20114:00 pmRNSAGM Statement
7th Jun 20117:00 amRNSUnderground Potential at Proyecto Rio Tinto
2nd Jun 20117:00 amRNSPermitting Update
24th May 20117:30 amRNSIssue of Shares
24th May 20117:00 amRNSPermitting Milestone Achieved
18th May 20117:00 amRNSNotice of AGM
10th May 20117:00 amRNSExercise of Options
4th May 20117:00 amRNSQuarterly Financial Report
28th Apr 20117:00 amRNSIssue of Shares
19th Apr 20117:00 amRNSGovernment Departments Respond to PRT Submissions
11th Apr 20117:00 amRNSQuarterly Operational Update
6th Apr 20117:00 amRNSIssue of Shares
31st Mar 20117:00 amRNSFinal Results
15th Mar 20117:00 amRNSFurther Progress at Proyecto Rio Tinto
24th Jan 20119:01 amRNSQuarterly Report
21st Jan 20112:15 pmRNSIssue of shares

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.