Operations Update and 2019 Guidance

15 Jan 2019 07:00

RNS Number : 0671N
Atalaya Mining PLC
15 January 2019
 

15 January 2019

Atalaya Mining Plc. ("Atalaya" or the "Company")

 Fourth Quarter 2018 Operations Update and 2019 Guidance

New records established at Proyecto Riotinto

 

Atalaya Mining Plc. (AIM:ATYM, TSX:AYM), the European mining and development company, is pleased to announce its operations update for the fourth quarter of 2018 and to provide guidance for 2019.

 

Notably, 2018 copper production at Proyecto Riotinto was 42,114 tonnes, up 13% from 37,164 tonnes produced in 2017 and in the upper range of the revised and increased guidance provided to the market on 22 November 2018. Copper production of 11,172 tonnes during Q4 2018 once again represents a new quarterly record.

 

Proyecto Riotinto

Q4

Q3

Full year

2018

2017

2018

2018

2017

2019 Guidance

Ore mined

(M tonnes)

2.8

2.5

2.8

10.8

9.3

11.4

Waste mined

(M tonnes)

4.3

5.7

3.2

17.7

19.8

17.8

Ore milled

(M tonnes)

2.6

2.3

2.5

9.8

8.8

11.4

Cu grade

(%)

0.48

0.44

0.50

0.49

0.49

0.47

Cu recovery

(%)

88.99

86.11

88.40

88.30

85.45

85 - 87

Cu production

(tonnes)

11,172

8,622

11,055

42,114

37,164

45,000 - 46,500

 

During 2018 the plant processed 9.8 Mt of ore with an average copper head grade of 0.49% and a recovery rate of 88.30%. In comparison to the rates for 2017, throughput and metallurgical recoveries have increased as a result of continuous improvements. Throughput has increased from 8.8 Mtpa in 2017 to 9.8 Mtpa in 2018 and recoveries have improved from 85.45% in 2017 to 88.30% in 2018. Copper head grade was consistent with estimates. On a quarterly basis, throughput, recoveries and copper grade have improved compared with Q4 2017 and Q3 2018.

 

Guidance for copper production in 2019 is estimated to be in the range of 45,000 to 46,500 tonnes. This year is anticipated to be a transitional one given the commissioning of the plant expansion in mid-2019, which will increase production within the range of 50,000 to 55,000 tonnes in 2020.

 

In terms of ore milled, 2.6 million tonnes were processed during the quarter, reporting a slight increase from previous quarters. Copper head grade was in line with plans. The increase in copper production during the quarter is mainly attributable to the increase in ore milled and improved metallurgical recoveries.

 

Mining operations are progressing according to plan and at similar levels to previous quarters. On a combined basis, ore, waste and marginal ore amounted to 2.5 million m3 in Q4 2018 versus 2.2 million m3 in Q3 2018. Additional mining equipment is available on site in anticipation of the increase in production scheduled for H2 2019.

 

On-site concentrate inventories at the end of the quarter were approximately 4,667 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva.

 

Copper prices slightly decreased during the quarter compared with the previous quarter, with an average realised price per pound of copper payable, including the QPs closed in the period, of $2.85/lb compared with $2.89/lb in Q3 2018. The average copper spot price during the quarter was $2.80/lb. The realised price during the quarter, excluding QPs, was approximately $2.79/lb.

 

Cash operating costs for Q4 2018 are expected to be lower than the 2018 cost guidance ranges previously provided of $2.15-2.30/lb. Further details on costs will be provided with the 2018 Financial Statements to be reported in March 2019.

 

Exploration is progressing well at the Atalaya pit where massive sulphides and stockwork mineralisation are being targeted. The first 2,900 m of a 19,000 m drilling campaign have already been drilled with positive preliminary results received. Geological modelling of the upper and lower sections of the orebody is in progress. Drilling around the high-grade underground workings in Filon Sur is also ongoing with 9,900 m drilled out of a programme of 17,400 m.

 

Expansion to 15Mtpa at Proyecto Riotinto

 

The 15Mtpa expansion project is progressing according to schedule. Engineering and procurement are now completed with equipment delivered to site. All efforts are now concentrated around site construction activities. Overall progress completion at the end of December 2018 was over 80%. Earthworks are completed while civil engineering works are being finalised. Installation of mechanical equipment is completed in the flotation and concentrate handling areas. Structural steel works have been finalised in the flotation area with piping installation underway. Piping is completed in the concentrate handling area with electrical installation well advanced. The milling area is the critical path of the expansion project that is scheduled for mechanical completion at the end of Q2 2019.

 

Proyecto Touro

 

The environmental impact assessment process was completed during the quarter. Since submission of the latest studies and reports during the previous quarter, a number of queries have been addressed and cleared as part of the consultation and permitting process. The next step in the permitting process is the evaluation of the project from a regulatory perspective.

 

Legal Update

 

On 26 September 2018, Atalaya released the receipt of ruling from the Tribunal Superior de Justicia de la Junta de Andalucia ("Receipt of Ruling of EeA Claim"), where the Company announced that the Court had ruled in favour of certain claims made by an environmental group against the government of Andalucia and Atalaya. Whilst the ruling invalidates the granting of the AAU (Authorization Ambiental Unificada) on procedural grounds, it does not suspend it and the ruling is still subject to appeal and therefore not currently enforceable.

 

As noted in the Receipt of Ruling of EeA Claim, both the Junta de Andalucia and Atalaya as co-defendant decided to and have filed an appeal with the Supreme Court in Spain. The Company will update the market with the result of the appeal in due course.

 

Alberto Lavandeira, CEO commented:

"2018 was characterised by continuous copper production increases and we are delighted once again to announce new quarterly and annual copper production records in this update. This confirms the success of the ongoing improvement measures that have been implemented by our operating teams at Proyecto Riotinto in recent years, giving us full confidence that value creation for the Company will continue as we expand and modernise operations at Riotinto in 2019. This will be further aided by the development of new projects like Touro in the near future."

 

About Atalaya Mining Plc

Atalaya is an AIM and TSX-listed mining and development group. It produces copper concentrates and silver by-product at its wholly owned Proyecto Riotinto site in southwest Spain, which is also undergoing a brownfield expansion. In addition, the Group has a phased, earn-in agreement for up to 80% ownership of Proyecto Touro, a brownfield copper project in the northwest of Spain which is currently in the permitting stage. For further information, visit www.atalayamining.com

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

Contacts:

Newgate Communications

Elisabeth Cowell / Adam Lloyd / Tom Carnegie

+ 44 20 7680 6550

4C Communications

Carina Corbett

+44 20 3170 7973

Canaccord Genuity (NOMAD and Joint Broker)

Martin Davison / Henry Fitzgerald-O'Connor / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch / Tom Rider / Michael Rechsteiner

+44 20 7236 1010

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
TSTSFUFWLFUSEIF
Date   Source Headline
11th Nov 20227:00 amRNSHolding(s) in Company
9th Nov 20222:40 pmRNSPDMR Share Dealing
9th Nov 20227:00 amRNSQ3 and YTD 2022 Financial Results
1st Nov 20227:00 amRNSEstablishment of Sustainability Committee
25th Oct 20227:00 amRNSNotice of Q3 2022 Results
17th Oct 20227:00 amRNSQ3 2022 Operations Upate
17th Oct 20227:00 amRNSQ3 2022 Operations Update
14th Oct 202212:43 pmRNSHolding(s) in Company
5th Oct 20227:00 amRNSFiling of Proyecto Riotinto Technical Report
29th Sep 20227:00 amRNSHolding(s) in Company
13th Sep 20227:00 amRNSChange in Dividend Payment Date
6th Sep 20227:00 amRNSInterim Dividend Foreign Exchange Rates andPayment
25th Aug 202210:45 amRNSDirector/PDMR Shareholding
23rd Aug 202211:54 amRNSHolding(s) in Company
10th Aug 20227:00 amRNSQ2 and H1 2022 Financial Results
18th Jul 20227:00 amRNSNotice of Q2 2022 and Interim Results
14th Jul 202211:06 amRNSSecond Price Monitoring Extn
14th Jul 202211:00 amRNSPrice Monitoring Extension
14th Jul 20227:00 amRNSQ2 2022 Operations Update
5th Jul 20227:00 amRNSPositive Drilling Results from Campanario Trend
24th Jun 20227:00 amRNSGrant of Share Options and PDMR Shareholding
23rd Jun 202212:15 pmRNS2022.06.23 - ATYM RNS - Options Executed
22nd Jun 202212:55 pmRNSResults of the 2022 Annual General Meeting
22nd Jun 20227:00 amRNS2022 Annual General Meeting Statement
26th May 20227:00 amRNSNotice of Annual General Meeting
20th May 20227:20 amRNSPDMR Share Purchase and Shareholding
19th May 20227:00 amRNSQ1 2022 Financial Results
18th May 20224:11 pmRNSAppointment of Director
18th May 20227:00 amRNSFiling of Proyecto Masa Valverde Technical Report
11th May 20227:00 amRNSNotice of Unaudited Q1 2022 Results
3rd May 20225:15 pmRNSHolding(s) in Company
27th Apr 20227:00 amRNSPublication of Site Visit Presentation
25th Apr 20227:00 amRNSPublication of Inaugural Sustainability Report
13th Apr 20227:00 amRNSNew Resource Estimates: San Dionisio & San Antonio
13th Apr 20227:00 amRNSFirst Quarter 2022 Operations Update
7th Apr 20227:00 amRNSShareholder Update
6th Apr 20228:07 amRNSHolding(s) in Company
5th Apr 20222:00 pmRNSHolding(s) in Company
5th Apr 20227:00 amRNSIncrease in Mineral Resources at Masa Valverde
1st Apr 20229:05 amRNSSecond Price Monitoring Extn
1st Apr 20229:00 amRNSPrice Monitoring Extension
31st Mar 20224:48 pmRNSProposed placing in Atalaya Mining Plc
24th Mar 20222:16 pmRNSDirectorate Change
24th Mar 20227:00 amRNSAudited Full Year Results 2021
21st Mar 202211:50 amRNSConclusion of Astor Management AG litigation
22nd Feb 20227:00 amRNSDirector/PDMR Shareholding
3rd Feb 20227:00 amRNSBest copper intercept to date at Masa Valverde
27th Jan 20227:00 amRNSGranting of share options and PDMR Notification
26th Jan 20227:00 amRNSIssue of Equity
25th Jan 20227:00 amRNSSummary re. Approach to Sustainability

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.