EMED Mining completed an updated Technical Report

18 Feb 2013 07:30

RNS Number : 0528Y
EMED Mining Public Limited
18 February 2013
 



 

AIM: EMED

TSX: EMD

18 February 2013

 

EMED Mining has completed an updated NI 43-101 Technical Report

 

EMED Mining Public Limited (the "Company" or "EMED Mining"), the Europe-based minerals development and exploration company, is pleased to announce that independent technical expert Behre Dolbear has completed an updated NI 43-101 Technical Report on the Company's Rio Tinto Copper Project.

 

The report entitled "NI 43-101 Technical Report on EMED's Rio Tinto Copper Project, Huelva Province, Spain dated February 15, 2013" (the "NI 43-101 Report") endorsed the Company's planned base case annual production of existing ore reserves at 9.0Mtpa over 14 years from the Cerro Colorado deposit, being the first mine EMED Mining plans to bring into production. Behre Dolbear also noted that there is exploration potential peripheral to the Cerro Colorado deposit which is open to the east and at depth. This potentially provides scope to grow the resource and expand operations including the development of other mines within the existing permit areas.

 

Behre Dolbear supports the decision that the Company proceed with the restart of the Rio Tinto Copper Project as soon as the requisite project approvals, permits and project financing have been secured on the basis that in their view the project is viable and appears to be robust and well analysed in geological, engineering and financial terms.

 

Highlights from the NI 43-101 Report include EMED's redevelopment plan for the Rio Tinto Copper Project which includes processing 9 Mt of ore per year to produce some 37,000 t of copper-in-concentrate, based on the following assumptions:

• An average waste-to-ore ratio of about 1.1:1;

• Employment of 400 to 450 employees and contractors at full production;

• Potential to extend the 14-year mine life by conversion of known mineral resources to reserves;

• Pre-production capital cost estimates of approximately $200M, pre-production escrow funds of approximately $29M (for social security environmental and rehabilitation costs) and post start up capital cost estimates of approximately $75M; and

• Operating Cost estimates over the life of the project:

§ $1,223M for Site Operating Costs

§ $468M for Freight, Selling, Refining and Smelting

§ $171M for Other Cash Operating Costs

§ $148M for Non Operating Costs (acquisition costs)

 

The project cash flows and return calculations have conservatively deducted project acquisition costs to be paid to the project vendor and marketing agent as well as costs for site development and environmental management

 

For the base case, which assumes a copper price of $3.50/lb, pre-tax cash flows would pay back the Project's capital costs by the end of Year 4. After taxes and after deducting the costs of project acquisition and closure, the net cash flows total $1.138 billion and generate an NPV of $427M at a 10% discount rate and an IRR of 32%.

 

The updated NI 43-101 Report has been filed on SEDAR and is available on the Company's website, along with an updated investor presentation. A summary of other principal conclusions and recommendations of Behre Dolbear is as follows:

 

·; The Rio Tinto Copper Project is viable on the basis of parameters described in the NI 43-101 Report, in spite of the substantial increase in the capital cost estimate and environmental costs since the 2010 technical report;

·; The financial forecast contains potential operating cost improvements which, although feasible, require verification;

·; EMED Mining needs to refine its contingency provision as it completes its bonding and procurement arrangements, to ensure capital adequacy;

·; The Project has been well analysed in geological, engineering and financial terms

·; A review of the infrastructure and related engineering requirements has identified items which need to be addressed before start-up, but none that involve additional major capital expenditure or obstacles for successful operations;

·; The infrastructure and environmental aspects, as discussed in the NI 43-101 Report, are expected to be manageable;

·; The preparatory work on restarting the open-pit mine operation and the plans for contract mining appear to be satisfactory;

·; EMED Mining's personnel involved in the project are suitable and competent;

·; All aspects of Environment, Health and Safety, together with Social and Community Impact have been addressed by EMED Mining with competent personnel;

·; The annual rate of 9.0Mtpa should be achieved with a recovery of 85 % to a concentrate grading 21% to 23% Cu, on a dry basis and containing 10% moisture.

·; The timetable for this programme is challenging, but appears to be realistic; and

·; There is exploration potential peripheral to the Cerro Colorado deposit which is open to the east and at depth:

• By exploring the full lateral and vertical extent of the mineralisation within the existing Cerro Colorado open pit area;

• From Cerro Colorado West to Filon Sur West;

• At Cerro Colorado, west of the existing highway, notably the San Dionisio deposit under the Corta Atalya open pit;

• From Cerro Colorado East towards San Antonio; and

• At the Southern waste dump.

Behre Dolbear also recommended:

• Additional geological modelling to better understand the controls on mineralisation including the silver;

• Further delineation drilling to determine the limits of the orebody, both laterally and at depth;

• Additional drilling to upgrade the Inferred Resource and Indicated Resource material to Measured Resource category;

• Evaluation of nearby deposits as satellite operations; and

• Evaluation of the retreatment of the historical gossan tailings.

 

Harry Anagnostaras Adams, Managing Director of EMED Mining, commented: "The updated NI 43-101 is another important step in our move towards production. We are excited about re-establishing Rio Tinto as a mining field with initial production to commence at Cerro Colorado. There is huge scope to create a large scale operation and we are delighted that this independent technical report has validated our plans."

The scientific and technical information in this press release has been reviewed and approved by R. Cunneen, Group Exploration Manager, who is a "qualified person" within the meaning of National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

Enquiries

EMED Mining

Harry Anagnostaras-Adams

+357 9945 7843

RFC Ambrian

Stuart Laing

+61 8 9480 2500

Fox-Davies Capital

Simon Leathers

+44 203 463 5022

Bishopsgate Communications

Nick Rome

+44 207 562 3350

Proconsul Capital

Andreas Curkovic

+1 416 577 9927

 

For further information on the Company's activities, visit www.emed-mining.com or www.emed.tv

 

Cautionary Notes

This announcement contains "forward looking information" within the meaning of applicable Canadian securities legislation. "Forward looking information" may also include statements with respect to the future financial or operating performance of the Company, its subsidiaries and its projects, the future price of metals, the estimation of ore reserves and resources, the conversion of estimated resources into reserves, the realisation of ore reserve estimates, the timing and amount of estimated future production, costs of production, capital, operating and exploration expenditures, costs and timing of the development of new deposits, costs and timing of future exploration, requirements for additional capital, government regulation of mining operations, environmental risks, reclamation expenses, title disputes or claims, limitations of insurance coverage and the timing and possible outcome of pending litigation and regulatory matters. Often, but not always, forward looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. Accordingly, readers should not place undue reliance on forward looking statements.

Forward looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward looking statements. Such factors include, among others, general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; actual results of reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of metals; the future costs of capital to the Company; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; political instability, terrorist attacks, insurrection or war; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, as well as those factors discussed in the section entitled "Risk Factors" in the Company's annual information form.

Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward looking statements contained herein are made as of the date of this announcement and the Company disclaims any obligation to update any forward looking statements, whether as a result of new information, future events or results or otherwise. There can be no assurance that forward looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward looking statements.

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGMGMZFNFGFZZ
Date   Source Headline
13th Jun 20138:51 amRNSFunding Update
3rd Jun 20137:00 amRNSPermitting Update
30th May 20137:00 amRNSInvestor Briefing
23rd May 20137:00 amRNSPermitting Update
17th May 20133:00 pmRNSNotice of AGM
14th May 20133:03 pmRNSQuarterly Financial Report
23rd Apr 20137:00 amRNSEMED Mining at Master Investor
17th Apr 20137:00 amRNSQuarterly Operational Update
16th Apr 20137:00 amRNSTailings Project Update
15th Apr 20137:00 amRNSPermitting Update
4th Apr 201310:59 amRNSExercise of Options
2nd Apr 20137:00 amRNSExposure to Cyprus Bank Restructuring
25th Mar 20135:47 pmRNSAmendment of Option Agreements
25th Mar 20137:00 amRNSFinal Results
21st Mar 20133:38 pmRNSRio Tinto Copper Project Update
18th Mar 20131:05 pmRNSProposed Levy on Deposits in Cyprus
18th Feb 20137:30 amRNSEMED Mining completed an updated Technical Report
16th Jan 20137:00 amRNSQUARTERLY OPERATIONAL UPDATE
9th Jan 20137:00 amRNSShareholder Briefing
19th Dec 20129:27 amRNSResult of GM and Rio Tinto Project Update
11th Dec 20127:00 amRNSInvestor Briefing
28th Nov 201210:00 amRNSDespatch of Circular and EGM
22nd Nov 20122:00 pmRNSApproval of Interim Mining Lease Area in Slovakia
15th Nov 201210:21 amRNSRio Tinto Site Visit
14th Nov 20123:00 pmRNSQuarterly Financial Results
14th Nov 20127:00 amRNSEMED Arranges a US$50 Million Funding Package
18th Oct 20127:00 amRNSUpdate of Progress at Rio Tinto Copper Project
2nd Oct 20124:35 pmRNSReceipt of AAU public comments report
1st Oct 20127:00 amRNSAppointment of Non-Executive Director
27th Sep 20129:10 amRNSQUARTERLY OPERATIONAL UPDATE
19th Sep 20127:00 amRNSSlovakia Update
4th Sep 20127:00 amRNSEMED Mining progresses towards production
31st Aug 20121:00 pmRNSCompletion of acquisitions of remaining land
20th Aug 20121:30 pmRNSCompletion of US$5m Equity Subscription by XGC
7th Aug 20127:00 amRNS2012 Interim Results
3rd Aug 20127:00 amRNSLand Acquisition
16th Jul 20127:00 amRNSEMED MINING QUARTERLY OPERATIONAL UPDATE
9th Jul 20127:00 amRNSAgreement With Owner of Lands
26th Jun 20127:00 amRNSInvestor Briefing
21st Jun 20121:30 pmRNSIssue of equity following warrant exercise
18th Jun 20127:00 amRNSInvestors Briefing Update
13th Jun 20121:31 pmRNSResult of AGM
13th Jun 20121:30 pmRNSAGM Statement
18th May 201212:30 pmRNSNotice of AGM
14th May 20127:00 amRNSEMED Mining Quarterly Financial Report
10th May 20127:00 amRNSEMED Mining Report Detva Gold Project Progress
19th Apr 20121:09 pmRNSExercise of Employee Share Options
11th Apr 20127:00 amRNSNominated Adviser to Change Name
3rd Apr 20127:00 amRNSEMED Quarterly Update
27th Mar 20127:00 amRNSFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.