Ben Richardson, CEO at SulNOx, confident they can cost-effectively decarbonise commercial shipping. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAntofagasta Regulatory News (ANTO)

Share Price Information for Antofagasta (ANTO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2,282.00
Bid: 2,269.00
Ask: 2,271.00
Change: 27.00 (1.20%)
Spread: 2.00 (0.088%)
Open: 2,275.00
High: 2,282.00
Low: 2,250.00
Prev. Close: 2,255.00
ANTO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q3 2019 PRODUCTION REPORT

23 Oct 2019 07:00

RNS Number : 7814Q
Antofagasta PLC
23 October 2019
 

NEWS RELEASE, 23 OCTOBER 2019

Q3 2019 PRODUCTION REPORT

CONTINUED STRONG COPPER PRODUCTION AND LOWER COSTS

 

Antofagasta plc CEO, Iván Arriagada said: "We delivered another quarter of strong production underpinned by a consistent operating performance, which together with higher grades at some of our operations, contributed to year to date copper volumes of 584,200 tonnes which are 16% higher than the same period in 2018.

"Costs continued to decrease over the quarter with net cash costs falling to $1.12/lb and $1.17/lb for the year to date. For the full year we expect to deliver production growth in line with our annual guidance."

 

HIGHLIGHTS

PRODUCTION

·; Group copper production in Q3 2019 was 197,000 tonnes, 0.8% lower than the previous quarter

·; Group copper production for the first nine months of the year was 584,200 tonnes, 15.6% higher than in the same period last year on continued higher throughput and grades

·; Gold production for the year to date was 226,600 ounces, 88.7% higher than in the same period last year on higher grades and for the quarter was 77,600 ounces, 10.7% lower than the previous quarter as grades declined at Centinela

·; Molybdenum production in the quarter was 2,900 tonnes, some 100 tonnes lower than the previous quarter. For the year to date, production was 9,300 tonnes, 1,000 tonnes lower than in the same period last year on lower grades

CASH COSTS

·; Cash costs before by-product credits in Q3 2019 were $1.60/lb and for the first nine months of the year were $1.64/lb, 1.2% lower than in Q2 2019 and 11.4% lower than in the year to date last year. This improvement in unit costs during the year is due to the increased production, costs savings arising from the Cost and Competitiveness Programme and a weaker Chilean Peso

·; Net cash costs were $1.12/lb in Q3 2019 and $1.17/lb for the year to date, a 1.8% decrease compared with the previous quarter and 17.6% lower than the same period last year, primarily due to lower cash costs before by-product credits and higher by-product credits

GUIDANCE

·; Guidance for 2019 is maintained at 750-790,000 tonnes of copper with costs expected to be below $1.25/lb

·; In 2020 production is expected to be to 725-755,000 tonnes of copper as grades decline at Centinela Concentrates before rising again in 2021

OTHER

·; Progress on the Los Pelambres expansion project reached 24% as at the end of the quarter and the rate of expenditure is accelerating as expected

·; Recent civil unrest in Chile could potentially disrupt the delivery of supplies and the transport of employees and contractors to our operations, with the impact on production expected to be approximately 5,000 tonnes

·; Labour negotiations were successfully concluded with the supervisors at Zaldívar during the quarter and with the supervisors at Los Pelambres this month. At Antucoya the workers declared a strike on 15 October and negotiations are continuing

·; Labour negotiations with a new supervisors union at Antucoya have recently commenced and are expected to be concluded by the end of the year

GROUP PRODUCTION AND CASH COSTS

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

Copper production

kt

584.2

505.5

15.6

197.0

198.6

(0.8)

Copper sales

kt

578.6

499.3

15.9

197.3

202.5

(2.6)

Gold production

koz

226.6

120.1

88.7

77.6

86.9

(10.7)

Molybdenum production

kt

9.3

10.3

(9.7)

2.9

3.0

(3.3)

Cash costs before by-product credits (1)

$/lb

1.64

1.85

(11.4)

1.60

1.62

(1.2)

Net cash costs (1)

$/lb

1.17

1.42

(17.6)

1.12

1.14

(1.8)

(1) Cash cost is a non-GAAP measure used by the mining industry to express the cost of production in US dollars per pound of copper produced.

 

 

 

Investors - London Media - London

Andrew Lindsay alindsay@antofagasta.co.uk Carole Cable antofagasta@brunswickgroup.com

Telephone +44 20 7808 0988 Telephone +44 20 7404 5959

Andres Vergara avergara@antofagasta.co.uk Will Medvei antofagasta@brunswickgroup.com

Telephone +44 20 7808 0988 Telephone +44 20 7404 5959

 

Media - Santiago

Pablo Orozco porozco@aminerals.cl

Carolina Pica cpica@aminerals.cl

Telephone +56 2 2798 7000

 

 

Register on our website to receive our email alerts http://www.antofagasta.co.uk/investors/email-alerts/ 

 

 

MINING OPERATIONS

Los Pelambres

Production at Los Pelambres was 90,600 tonnes of copper in Q3 2019, 0.7% lower than in the previous quarter as higher throughput and recoveries were partially offset by expected lower ore grades.

In the first nine months of 2019, copper production was 271,000 tonnes, 5.1% higher than in the same period last year primarily due to higher throughput and grades.

Molybdenum production was 2,800 tonnes in Q3 2019, slightly down from the previous quarter and for the year to date was 9,000 tonnes, 10.0% lower than the same period last year as a result of lower molybdenum grades.

Cash costs before by-product credits in Q3 were $1.38/lb, 4.2% lower than in previous quarter and for the first nine months of the year were $1.42/lb, 11.3% lower than same period last year. Higher throughput and ore grades, productivity improvements and the weakening of the Chilean Peso have all contributed to reducing unit costs which are lower than the $1.50/lb expected for the full year.

Net cash costs for the quarter were $0.86/lb, and for the year to date were $0.88/lb, 8.3% lower than the same period last year despite by-product credits being 10c/lb less than last year.

Shortly after the end of the period labour negotiations with the supervisors union were successfully concluded for a period of three years.

LOS PELAMBRES

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

Daily ore throughput

kt

169.6

165.3

2.6

171.6

165.1

3.9

Copper grade

%

0.69

0.67

3.0

0.67

0.72

(6.9)

Copper recovery

%

87.7

88.2

(0.6)

88.7

87.6

1.3

Copper production

kt

271.0

257.8

5.1

90.6

91.2

(0.7)

Copper sales

kt

259.4

255.2

1.6

88.5

96.0

(7.8)

Molybdenum grade

%

0.021

0.027

(22.2)

0.022

0.022

0.0

Molybdenum recovery

%

85.5

84.0

1.8

86.3

86.0

0.3

Molybdenum production

kt

9.0

10.0

(10.0)

2.8

2.9

(3.4)

Molybdenum sales

kt

9.5

9.6

(1.0)

3.1

3.1

0.0

Gold production

koz

44.8

46.0

(2.6)

15.0

14.2

5.6

Gold sales

koz

38.0

45.8

(17.0)

13.1

14.3

(8.4)

Cash costs before by-product credits (1)

$/lb

1.42

1.60

(11.3)

1.38

1.44

(4.2)

Net cash costs (1)

$/lb

0.88

0.96

(8.3)

0.86

0.93

(7.5)

(1) Includes tolling charges of $0.21lb in Q3 2019, $0.23/lb in Q2 2019, $0.23/lb YTD 2019 and $0.25/lb YTD 2018

 

Centinela

Total copper production at Centinela during the quarter was 73,200 tonnes, 0.1% lower in than in the previous quarter as grades declined. Production for the year to date was 215,200 tonnes, 33.2% higher than in the same period last year, primarily as a result of higher grades at Centinela Concentrates but also with higher throughput at both the concentrate and oxide plants.

Production of copper in concentrate was 56,700 tonnes in Q3 2019, 2.2% higher than in the previous quarter. For the first nine months of the year, copper in concentrate production was 156,800 tonnes, compared with 95,300 tonnes in the same period last year, reflecting higher throughput, grades and recoveries.

Major maintenance of the SAG mill at the concentrate plant is expected to be completed during October.

Copper cathode production during the quarter was 16,500 tonnes, 6.3% lower than Q2 2019 as throughput reduced by 6.6%. For the year to date, copper cathode production was 58,400 tonnes, 12.0% lower than in the same period last year primarily due to lower grades and recoveries.

Gold production was 62,600 ounces in the quarter, 13.9% lower than the previous quarter on lower grades, and for the first nine months was 181,900 ounces, 146% higher than same period last year, due to higher throughput, grades and recoveries.

Cash costs before by-product credits were $1.72/lb, 4.2% higher than in the previous quarter. Cash costs before by-product credits for the first nine months of 2019 were $1.74/lb, 18.7% lower than the same period in 2018 as a result of higher copper production and a weaker Chilean Peso.

By-product credits decreased from $0.67/lb in Q2 to $0.64/lb in Q3 due to lower gold production. For the first nine months of 2019, by-product credits were $0.60/lb, $0.30/lb higher than in the same period last year due to increased gold production and a higher realised gold price.

Net cash costs in Q3 2019 were $1.08/lb, 10.0% higher than the previous quarter.

During the first nine months of the year net cash costs were $1.14/lb, 38.0% lower than in same period in 2018 due to lower cash costs before by-product credits and higher by-product credits.

 

CENTINELA

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

CONCENTRATES

 

 

 

 

 

 

 

Daily ore throughput

kt

95.3

91.9

3.7

92.3

92.2

0.1

Copper grade

%

0.73

0.50

46.0

0.78

0.81

(3.7)

Copper recovery

%

85.6

81.1

5.5

87.7

86.5

1.4

Copper production

kt

156.8

95.3

64.5

56.7

55.5

2.2

Copper sales

kt

161.9

97.8

65.5

60.1

52.2

15.1

Molybdenum grade (1)

%

0.007

0.011

(36.4)

0.007

0.004

75.0

Molybdenum recovery (1)

%

76.1

82.4

(7.6)

78.7

66.1

19.1

Molybdenum production (1)

kt

0.3

0.3

0.0

0.1

0.1

0.0

Molybdenum sales (1)

kt

0.3

0.3

0.0

0.1

0.1

0.0

Gold grade

g/t

0.32

0.16

100.0

0.33

0.39

(15.4)

Gold recovery

%

69.7

62.9

10.8

69.5

72.4

(4.0)

Gold production

koz

181.9

74.1

145.5

62.6

72.7

(13.9)

Gold sales

koz

190.4

74.6

155.2

67.0

72.4

(7.5)

 

 

 

 

 

 

 

 

Daily ore throughput

kt

46.1

43.7

5.5

42.8

45.8

(6.6)

Copper grade

%

0.58

0.71

(18.3)

0.57

0.55

3.6

Copper recovery

%

70.0

72.7

(3.7)

68.8

67.0

2.7

Copper production - heap leach

kt

54.0

61.6

(12.3)

15.3

16.1

(5.0)

Copper production - total (2)

kt

58.4

66.4

(12.0)

16.5

17.6

(6.3)

Copper sales

kt

63.5

66.5

(4.5)

18.1

20.6

(12.1)

Total copper production

kt

215.2

161.6

33.2

73.2

73.1

0.1

Cash costs before by-product credits (3)

$/lb

1.74

2.14

(18.7)

1.72

1.65

4.2

Net cash costs (3)

$/lb

1.14

1.84

(38.0)

1.08

0.98

10.2

(1) Molybdenum production started in Q3 2018

(2) Includes production from ROM material

(3) Includes tolling charges of $0.18/lb in Q3 2019, $0.18/lb in Q2 2019, $0.18/lb YTD 2019 and $0.16/lb YTD 2018

 

 

Antucoya

Copper production at Antucoya was 18,700 tonnes in Q3 2019, 4.1% lower than in the previous quarter due to lower throughput, partially offset by higher recoveries with work being completed during the quarter to reduce the dust being produced at the secondary and tertiary crushers. Production in the first nine months of 2019 was 56,100 tonnes, 7.7% higher than the same period last year on higher copper grades and recoveries. 

During the quarter, cash costs were $2.08/lb compared to $2.29/lb in Q2 2019. For the first nine months, cash costs were $2.20/lb, 5.3% higher than same period last year mainly due to higher acid prices and higher maintenance costs, partially offset by lower energy prices and a weaker Chilean Peso.

On 15 October the workers union declared a strike having rejected the company's last offer on salary increases, bonuses and other benefits. Only essential operations will be conducted at the mine while the strike continues.

ANTUCOYA

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

Daily ore throughput

kt

72.2

75.3

(4.1)

67.6

73.3

(7.8)

Copper grade

%

0.39

0.36

8.3

0.41

0.40

2.5

Copper recovery

%

73.7

70.0

5.3

78.7

71.2

10.5

Copper production

kt

56.1

52.1

7.7

18.7

19.5

(4.1)

Copper sales

kt

55.4

47.0

17.9

19.0

19.4

(2.1)

Cash costs

$/lb

2.20

2.09

5.3

2.08

2.29

(9.2)

 

Zaldívar

Copper production at Zaldívar was 14,500 tonnes, 2.0% lower than previous quarter on lower throughput, grades and recoveries partially offset by increased production from secondary leaching.

Production for the year to date was 41,900 tonnes, 23.2% higher compared with the same period last year due to significantly improved ore grades and higher throughput, partially offset by lower recoveries.

Cash costs during the quarter were $1.77/lb, 4.7% higher than in Q2 2019, and cash costs for the first nine months of the year were $1.78/lb, 9.2% lower compared with $1.96/lb in the same period in 2018, primarily due to higher production. Higher acid prices have been partially offset by weaker local currency.

Labour negotiations with the supervisors were successfully concluded during the quarter.

ZALDÍVAR

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

Daily ore throughput

kt

38.4

36.5

5.2

40.4

45.4

(11.0)

Copper grade

%

1.15

0.78

47.4

1.00

1.21

(17.4)

Copper recovery (1)

%

61.7

66.7

(7.5)

61.3

62.6

(2.1)

Copper production - heap leach (2)

kt

34.5

26.4

30.7

11.4

13.7

(16.8)

Copper production - total (2,3)

kt

41.9

34.0

23.2

14.5

14.8

(2.0)

Copper sales (2)

kt

38.4

32.8

17.1

11.6

14.3

(18.9)

Cash costs

$/lb

1.78

1.96

(9.2)

1.77

1.69

4.7

(1) Average over full leach cycle

(2) Group's 50% share

(3) Includes production from secondary leaching

Transport Division

Total transport volumes in Q3 2019 were 1.8 million tonnes, 4.7% higher than in the previous quarter and for the first nine months of the year, transport volumes increased by 9.6% to 4.9 million tonnes, as a new transport contracts that came into effect during the period as well as higher tonnages from existing customers.

In addition to the seven new locomotives that were brought into operation during 2018, seven new locomotives have arrived in 2019 and are currently operating and five more are expecting to be delivered by the end of the year. These purchases are part of the Division's programme to replace older rolling stock and increase the fleet's haulage capacity with a more efficient fleet to meet growing demand and complete new contracts.

TRANSPORT DIVISION

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2018

%

Rail

kt

3,770

3,654

3.2%

1,346

1,279

5.2%

Road

kt

1,156

839

37.8%

430

418

3.0%

Total tonnage transported

kt

4,926

4,493

9.6%

1,776

1,697

4.7%

 

Commodity prices and exchange rates

 

Year to Date

Q3

Q2

 

 

 

2019

2018

%

2019

2019

%

Copper

 

 

 

 

 

 

 

Market price

$/lb

2.74

3.01

(9.0)

2.63

2.77

(5.2)

Realised price

$/lb

2.71

2.87

(5.7)

2.51

2.61

(4.0)

Gold

 

 

 

 

 

 

 

Market price

$/oz

1,364

1,283

6.3

1,474

1,310

12.6

Realised price

$/oz

1,388

1,258

10.3

1,501

1,338

12.2

Molybdenum

 

 

 

 

 

 

 

Market price

$/lb

11.9

11.9

0.3

11.8

12.2

(2.9)

Realised price

$/lb

11.9

12.5

(5.0)

11.4

12.1

(5.6)

Exchange rates

 

 

 

 

 

 

 

Chilean peso

per $

685

628

9.1

707

684

3.4

 

Spot commodity prices for copper, gold and molybdenum as at 30 September 2019 were $2.60/lb, $1,473/oz and $11.8/lb respectively, compared with $2.72/lb, $1,410/oz and $11.9/lb as at 30 June 2019 and $2.70/lb, $1,282/oz and $11.3/lb as at 31 December 2018.

The provisional pricing adjustments for copper, gold and molybdenum for the quarter were negative $56.8 million, positive $2.4 million and negative $3.0 million respectively.

The provisional pricing adjustments for copper, gold and molybdenum for the first nine months of the year were negative $51.3 million, positive $4.4 million and negative $1.2 million respectively.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLMTBBTMBATTPL
Date   Source Headline
15th Mar 20167:00 amRNSPreliminary Results Announcement
9th Mar 20165:40 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
5th Feb 20169:50 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
27th Jan 20167:00 amRNSQ4 2015 PRODUCTION REPORT
1st Dec 20155:30 pmRNSCOMPLETION OF ZALDIVAR TRANSACTION
10th Nov 201512:52 pmRNSRETRACTION OF TR1 NOTIFICATION
28th Oct 20157:00 amRNSQ3 2015 PRODUCTION REPORT
24th Sep 20155:53 pmRNSDIVIDEND NO 41 AMOUNT PAYABLE IN STERLING AND EURO
1st Sep 201510:31 amRNSNOTIFICATION OF CLASS 2 TRANSACTION
25th Aug 20157:00 amRNSHalf Yearly Financial Report
18th Aug 20152:14 pmRNSAntofagasta Board Committee Changes
31st Jul 20157:00 amRNSACQUISITION OF 50% INTEREST IN ZALDIVAR
29th Jul 20157:00 amRNSQ2 2015 PRODUCTION REPORT
25th Jun 20151:44 pmRNSChanges to Board Committees
3rd Jun 20159:30 amRNSCompletion of sale of water division
20th May 20153:53 pmRNSResults of Annual General Meeting
20th May 20157:00 amRNSCHAIRMAN'S COMMENTS AT THE 2015 AGM
30th Apr 20151:09 pmRNS2014 FINAL DIVIDEND
29th Apr 20157:00 amRNSQ1 2015 PRODUCTION REPORT
23rd Apr 20152:34 pmRNSSale of Water Division
14th Apr 201512:00 pmRNS2014 ANNUAL REPORT AND FINANCIAL STATEMENTS
1st Apr 201510:30 amRNSNORMAL OPERATIONS RESUMED FOLLOWING HEAVY RAINS
27th Mar 20157:00 amRNSHEAVY RAINS IN THE ATACAMA
26th Mar 20153:11 pmRNSLong Term Incentive Plan
17th Mar 20157:00 amRNS2014 PRELIMINARY RESULTS
12th Mar 20157:00 amRNSRESOLUTION OF LOS PELAMBRES PROTEST
10th Mar 20157:02 amRNSCOURT RULING AGAINST LOS PELAMBRES
9th Mar 20157:00 amRNSPROTEST AT LOS PELAMBRES
23rd Feb 20157:00 amRNSAntofagasta plc expects lower cash costs in 2015
6th Feb 20159:00 amRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
28th Jan 20157:00 amRNSQ4 2014 PRODUCTION REPORT
22nd Jan 20159:16 amRNSNOTIFICATION OF DIRECTORS INTERESTS
21st Jan 20152:24 pmRNSCOMPLETION OF DULUTH ACQUISITION
13th Jan 20159:00 amRNSNOTIFICATION OF DIRECTORS INTERESTS
18th Dec 201412:00 pmRNSAPPOINTMENT OF NON-EXECUTIVE DIRECTOR
3rd Dec 20147:00 amRNSAppointment of CEO of Antofagasta Minerals
3rd Nov 20141:16 pmRNSAcquisition of Duluth Metals Limited
29th Oct 20147:00 amRNSQ3 2014 PRODUCTION REPORT
25th Sep 201410:57 amRNS2014 Interim Dividend Update
26th Aug 20147:00 amRNSHALF YEARLY FINANCIAL REPORT
21st Aug 20147:00 amRNSChanges to Board Committees
20th Aug 20147:00 amRNSCHANGE IN ROLE OF CHAIRMAN & APPOINTMENT OF CEO
13th Aug 201411:14 amRNSDIRECTORATE CHANGE
30th Jul 20147:00 amRNSQ2 2014 PRODUCTION REPORT
3rd Jul 20143:13 pmRNSTWIN METALS PROJECT
21st May 20141:15 pmRNSResults of Annual General Meeting
21st May 20149:00 amRNSCHAIRMAN'S COMMENTS AT THE 2014 AGM
1st May 201412:00 pmRNSFINAL DIVIDEND OF 86.1 US CENTS PER ORDINARY SHARE
30th Apr 20147:00 amRNSQ1 2014 PRODUCTION REPORT
11th Apr 201412:00 pmRNS2013 ANNUAL REPORT AND FINANCIAL STATEMENTS

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.