Pin to quick picksAntofagasta Regulatory News (ANTO)

Share Price Information for Antofagasta (ANTO)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 2,198.00
Bid: 2,208.00
Ask: 2,210.00
Change: 6.00 (0.27%)
Spread: 2.00 (0.091%)
Open: 2,236.00
High: 2,241.00
Low: 2,194.00
Prev. Close: 2,192.00
ANTO Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q3 2017 PRODUCTION REPORT

25 Oct 2017 07:00

RNS Number : 5121U
Antofagasta PLC
25 October 2017
 

NEWS RELEASE, 25 OCTOBER, 2017

 

Q3 2017 PRODUCTION REPORT

 

Antofagasta plc CEO, Iván Arriagada said: "We have had a further quarter of improved production with tonnages increasing by 3% compared to the previous quarter and by 4.5% on a year to date basis. Unit costs have kept flat, despite increased cost pressures, with higher production at Centinela and Antucoya, and our continued focus on improving efficiencies. With these savings achieved to date we now expect our net cash costs to be below our original guidance for the full year of $1.30/lb.

"In 2018 we plan to increase production to 705-740,000 tonnes of copper as Encuentro Oxides ramps-up to full production."

 

HIGHLIGHTS

PRODUCTION

· Group copper production in Q3 2017 was 180,200 tonnes, 3.3% higher than in the previous quarter on increased production at Los Pelambres.

· Group copper production for the first nine months of the year was 526,500 tonnes, 4.5% higher than in the same period last year. This was primarily due to higher production at Centinela and Antucoya.

· Gold production during the quarter increased by 1.2% to 59,600 ounces and for the first nine months fell by 4.4% with lower production at Centinela and Los Pelambres.

· Molybdenum production at Los Pelambres increased in Q3 2017 to 2,700 tonnes and for the year to date was 38.5% higher than in the same period last year, due to higher molybdenum grades.

 

CASH COSTS

· Cash costs before by-product credits in Q3 2017 were $1.56/lb, 1.3% higher than in Q2 2017 as costs increased at Centinela after a strong performance in the previous quarter.

· Cash costs before by-product credits for the first nine months were $1.56/lb, 1.3% better than last year due to higher production and cost savings achieved from the Cost and Competitiveness Programme.

· Net cash costs were $1.18/lb in Q3 2017, a 1.7% improvement compared with the previous quarter, as the higher cash costs before by-product credits were offset by increased by-product volumes and realised prices.

· Net cash costs for the first nine months were $1.22/lb, 0.8% better than in the same period last year.

GUIDANCE

· Copper production guidance for 2017 remains unchanged at 685-720,000 tonnes, and production is expected to increase to 705-740,000 tonnes in 2018.

· Cash costs before by-product credits guidance for the full year is unchanged at $1.55/lb and net cash costs are now expected to be lower than the $1.30/lb guided at the beginning of the year reflecting stronger than expected by-product revenue.

· Total capital expenditure for the year is expected to be approximately $900 million, as previously guided.

 

OTHER

· Successfully concluded labour negotiations at Zaldívar during the quarter.

· Labour negotiations have commenced at Los Pelambres and are expected to be concluded before the deadline in February 2018.

 

GROUP PRODUCTION AND CASH COSTS

Year to Date

Q3

Q2

 

2017

2016

%

2017

2017

%

Copper production(1)

kt

526.5

503.9

4.5

180.2

174.4

3.3

Copper sales

kt

522.4

491.7

6.2

188.3

158.4

18.9

Gold production

koz

171.8

179.7

(4.4)

59.6

58.9

1.2

Molybdenum production

kt

7.2

5.2

38.5

2.7

2.4

12.5

Cash costs before by-product credits

$/lb

1.56

1.58

(1.3)

1.56

1.54

1.3

Net cash costs

$/lb

1.22

1.23

(0.8)

1.18

1.20

(1.7)

 

(1) Includes pre-commercial production at Antucoya of 12,700 tonnes in 2016, which are not included in unit cost calculations.

 

 

 

Investors - London

Media - London

Andrew Lindsay

alindsay@antofagasta.co.uk

Carole Cable

antofagasta@brunswickgroup.com

Paresh Bhanderi

pbhanderi@antofagasta.co.uk

Will Medvei

antofagasta@brunswickgroup.com

Telephone

+44 20 7808 0988

Telephone

+44 20 7404 5959

Investors - Santiago

Media - Santiago

Francisco Veloso

fveloso@aminerals.cl

Pablo Orozco

porozco@aminerals.cl

Carolina Pica

cpica@aminerals.cl

Telephone

+56 2 2798 7000

Telephone

+56 2 2798 7000

 

 

 

MINING OPERATIONS

Los Pelambres

Los Pelambres produced 86,800 tonnes of copper in Q3 2017, 6.6% higher than in the previous quarter as higher throughput was achieved due to softer ore and slightly higher grades. In the first nine months of 2017, copper production decreased slightly by 3.2% to 251,000 tonnes, compared with the same period last year. This decrease was primarily due to lower grades, despite increased throughput.

Sales of copper were 95,400 tonnes in Q3 2017, higher than production, as the stocks accumulated at the port as a result of poor sea conditions at the end of the previous quarter were shipped.

Molybdenum production was higher at 2,700 tonnes in Q3 2017 compared to the previous quarter, as the grade improved although recoveries fell. Production for the first nine months of the year was 7,200 tonnes, which was 38.5% higher than in the comparable period in 2016 as a result of higher grade.

Cash costs before by-product credits in Q3 2017 were $1.46/lb, compared with $1.50/lb in the previous quarter. This decrease was principally due to higher production, the reduced use of consumables and the continuation of the Cost and Competitiveness Programme. For the first nine months of the year, cash costs before by-product credits were $1.45/lb, 6.6% higher than in 2016 primarily due to lower production and higher consumables' prices.

Net cash costs during the quarter were $1.01/lb, 10.6% lower than in the previous quarter as a result of higher by-product production and realised prices. Net cash costs for the first nine months of the year were $1.06/lb, 1.9% higher than the same period last year as increased by-product credits were insufficient to offset the rise in cash costs before by-products.

 

 

LOS PELAMBRES

 

Year to Date

Q3 Q2

 

2017

2016

%

2017

2017

%

Daily ore throughput

kt

159.3

153.8

3.6

161.3

155.6

3.7

Copper grade

%

0.67

0.70

(4.3)

0.68

0.67

1.5

Copper recovery

%

89.0

89.1

(0.1)

89.5

89.9

(0.4)

Copper production

kt

251.0

259.3

(3.2)

86.8

81.4

6.6

Copper sales

kt

245.6

254.2

(3.4)

95.4

67.5

41.3

Molybdenum grade

%

0.021

0.016

31.3

0.022

0.021

4.8

Molybdenum recovery

%

79.2

78.6

0.8

80.9

81.9

(1.2)

Molybdenum production

kt

7.2

5.2

38.5

2.7

2.4

12.5

Molybdenum sales

kt

7.3

5.4

35.2

2.9

2.3

26.1

Gold production

koz

40.1

43.1

(7.0)

13.3

12.9

3.1

Gold sales

koz

38.4

47.1

(18.5)

14.4

10.4

38.5

Cash costs before by-product credits(1)

$/lb

1.45

1.36

6.6

1.46

1.50

(2.7)

Net cash costs(1)

$/lb

1.06

1.04

1.9

1.01

1.13

(10.6)

 

(1) Includes tolling charges of $0.25/lb in Q3 2017, $0.26/lb in Q2 2017, $0.26/lb YTD 2017 and $0.27/lb YTD 2016

 

Centinela

Total copper production at Centinela was 60,600 tonnes in Q3 2017, 1.0% lower than in the previous quarter due to lower production of copper cathodes, and copper in concentrates flat across the quarters. Total production for the first nine months of the year 2017 was 10.7% higher than in 2016 primarily as a result of higher grades.

Production of copper in concentrates was 47,300 tonnes in Q3 2017, unchanged compared with the previous quarter as higher grades and higher recoveries were offset by lower throughput as a result of harder ore, and scheduled maintenance during the quarter. 

Copper in concentrate production for the first nine months of the year was 10.5% higher than in the same period last year mainly reflecting higher grades.

Production of copper cathodes for the quarter was 13,300 tonnes, a 4.3% decrease from the previous quarter due to lower grades and recoveries which were slightly offset by higher throughput. For the first nine months of the year cathode production rose 10.9% to 43,600 tonnes as a result of higher grades and throughput offset slightly by lower recoveries.

Gold production in the quarter was 46,300 ounces as a result of higher grades and recoveries. During the first nine months of the year gold production was 3.5% lower than the same period last year due to lower recoveries.

Cash costs before by-product credits were $1.67/lb in the quarter, an increase of 7.1% compared to the previous quarter as spare parts and maintenance costs were higher as a result of the scheduled major maintenance in the quarter. In addition, a new labour agreement was reached with the supervisors' union during the quarter which increased cash costs by a one-off amount of 3.5 c/lb in the quarter and 1 c/lb for the full year. Cash costs before by-product credits for the first nine months of 2017 were 11.6% lower than in 2016 with higher copper production and cost savings from the Cost and Competitiveness Programme.

Net cash costs in Q3 2017 were $1.18/lb, 9.3% higher than in the previous quarter as higher gold prices were not able to offset the increase in cash costs before by-products. In the first nine months of the year, net cash costs were down 11.9% at $1.19/lb due to higher gold sales offset by a slightly lower realised gold price.

 

CENTINELA

 

Year to Date

Q3 Q2

 

 

2017

2016

%

2017

2017

%

CONCENTRATES

 

 

 

 

 

 

 

Daily ore throughput

kt

89.1

90.9

(2.0)

85.8

92.2

(6.9)

Copper grade

%

0.65

0.57

14.0

0.70

0.67

4.5

Copper recovery

%

87.2

87.2

-

88.4

88.0

0.5

Copper production

kt

133.6

120.9

10.5

47.3

47.3

-

Copper sales

kt

139.5

115.2

21.1

49.8

45.8

8.7

Gold grade

g/t

0.25

0.24

4.2

0.26

0.25

4.0

Gold recovery

%

71.1

72.7

(2.2)

72.2

70.3

2.7

Gold production

koz

131.8

136.6

(3.5)

46.3

46.0

0.7

Gold sales

koz

139.3

133.3

4.5

48.8

45.0

8.4

CATHODES

 

 

 

 

 

 

 

Daily ore throughput

kt

23.6

21.5

9.8

24.7

21.4

15.4

Copper grade

%

0.93

0.78

19.2

0.90

0.95

(5.3)

Copper recovery

%

66.3

69.8

(5.0)

58.7

65.5

(10.4)

Copper production - heap leach

kt

38.9

33.1

17.5

11.8

12.2

(3.3)

Copper production - total(1)

kt

43.6

39.3

10.9

13.3

13.9

(4.3)

Copper sales

kt

43.3

38.4

12.8

12.7

14.6

(13.0)

Total copper production

kt

177.3

160.2

10.7

60.6

61.2

(1.0)

Cash costs before by-product credits(2)

$/lb

1.67

1.89

(11.6)

1.67

1.56

7.1

Net cash costs(2)

$/lb

1.19

1.35

(11.9)

1.18

1.08

9.3

 

(1) Includes production from ROM material

(2) Includes tolling charges of $0.19/lb in Q3 2017, $0.20/lb in Q2 2017, $0.20/lb YTD 2017 and $0.22/lb YTD 2016

 

Antucoya

Copper production at Antucoya was 19,800 tonnes in Q3 2017, 3.1% higher than in the previous quarter as slightly improved grades were partly offset by lower recoveries. Compared to last year, production in the first nine months of 2017 was 28.0% higher than in the same period last year as significantly higher throughput and higher recoveries were only slightly offset by a decline in grade.

During the quarter the cash costs were $1.67/lb, almost unchanged compared to Q2 2017. For the first nine months cash costs were down by 2.3% to $1.70/lb compared to the same period last year.

 

ANTUCOYA

 

Year to Date

Q3 Q2

 

 

2017

2016

%

2017

2017

%

Daily ore throughput

kt

78.2

62.8

24.5

79.7

79.1

0.8

Copper grade

%

0.37

0.40

(7.5)

0.37

0.36

2.8

Copper recovery

%

73.9

70.3

5.1

71.2

74.5

(4.4)

Copper production

kt

59.4

46.4

28.0

19.8

19.2

3.1

Copper sales

kt

57.4

45.5

26.2

18.1

19.1

(5.2)

Cash costs(1)

$/lb

1.70

1.74

(2.3)

1.67

1.66

0.6

 

(1) Cash costs from Q2 2016 onwards following commercial production being reached on 1 April 2016

 

 

Zaldívar

 

Production for the quarter was 2.4% higher than in Q2 2017 at 12,900 tonnes. Throughput for the quarter fell compared to the previous quarter to close to the year-to-date average while the grade of the ore placed on the heap increased slightly. Copper production in the first nine months of the year was 38,800 tonnes, some 2.1% higher than in the same period last year, on higher grade and despite lower recoveries. Recoveries have decreased this year as a result of the significantly higher proportion of sulphide ores being processed, compared to 2016.

Cash costs increased by 1.3% to $1.57/lb in Q3 2017 compared to the previous quarter due to upgrading work on the stacking system and water pipeline. During the quarter a three-year labour agreement was successfully concluded with the union, increasing cash costs by 1c/lb. Cash costs for the first nine months of 2017 were $1.59/lb, almost unchanged compared with the same period in 2016.

ZALDÍVAR

 

Year to Date

Q3 Q2

 

 

2017

2016

%

2017

2017

%

Daily ore throughput

kt

47.7

46.5

2.6

47.3

53.6

(11.8)

Copper grade

%

0.79

0.60

31.7

0.77

0.76

1.3

Copper recovery(1)

%

60.9

67.5

(9.8)

58.9

59.4

(0.8)

Copper production - heap leach(2)

kt

28.6

26.7

7.1

9.3

9.1

2.2

Copper production - total(2,3)

kt

38.8

38.0

2.1

12.9

12.6

2.4

Copper sales(2)

kt

36.6

37.5

(2.4)

12.4

11.4

8.8

Cash costs

$/lb

1.59

1.58

0.6

1.57

1.55

1.3

 

(1) Average over full leach cycle

(2) Group's 50% share

(3) Includes production from secondary leaching

 

 

Transport

The total tonnage transported by the Division in Q3 2017 increased by 7.2% to 1.7 million tonnes as lower copper tonnages were offset by higher acid volumes, although tonnes transported for the year to date are still lower than in the same period last year following the disruptions at two of its customers in the first quarter.

TRANSPORT

 

Year to Date

Q3 Q2

 

 

2017

2016

%

2017

2017

%

Rail

Kt

 3,732

 4,043

(7.7)

 1,337

 1,250

7.0

Road

kt

 895

 907

(1.2)

 320

 296

8.0

Total tonnage transported

kt

 4,628

 4,949

(6.5)

 1,657

 1,547

7.2

 

 

Commodity prices and exchange rates

PRICES AND EXCHANGE RATES

 

Year to Date

Q3 Q2

 

 

2017

2016

%

2017

2017

%

Copper

Market price

$/lb

2.70

2.14

25.9

2.88

2.57

12.1

Realised price

$/lb

2.85

2.18

30.8

3.09

2.61

18.6

Gold

Market price

$/oz

1,252

1,258

(0.5)

1,278

1,257

1.6

Realised price

$/oz

1,281

1,300

(1.6)

1,295

1,267

2.2

Molybdenum

Market price

$/lb

8.0

6.4

24.5

8.1

8.1

0.5

Realised price

$/lb

8.6

7.3

18.5

9.6

7.7

24.9

Exchange rates

Chilean peso

per $

654

681

(3.9)

643

664

(3.2)

 

The spot commodity prices for copper, gold and molybdenum as at 30 September 2017 were $2.92/lb, $1,280/oz and $7.09/lb respectively compared with $2.69/lb, $1,242/oz and $7.12/lb as at 30 June 2017 and $2.20/lb, $1,316/oz and $6.71/lb as at 30 September 2016. 

The provisional pricing adjustments for copper, gold and molybdenum for the quarter were positive $96.3 million, $0.2 million and $10.4 million respectively.

The provisional pricing adjustments for copper, gold and molybdenum for the first nine months of the year were positive $173.6 million, $0.2 million and $9.3 million respectively.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCMIBFTMBTTBMR
Date   Source Headline
1st Jun 20187:00 amRNSREPORT ON PAYMENTS TO GOVERNMENTS
31st May 20187:00 amRNSDirector Declaration
23rd May 20184:15 pmRNSResults of Annual General Meeting
23rd May 201810:26 amRNSCHAIRMAN'S COMMENTS AT THE 2018 AGM
8th May 20187:00 amRNSLos Pelambres Update
4th May 201810:58 amRNSFinal Dividend Payable
30th Apr 201810:41 amRNSDirector Declaration
25th Apr 20182:18 pmRNSDirector Declaration
25th Apr 20187:00 amRNSQ1 2018 Production Report
16th Apr 201812:34 pmRNSPublication of 2017 Annual Report & Notice of AGM
3rd Apr 201811:24 amRNSNotification of Management Transactions
27th Mar 201811:33 amRNSNotification of Management Transactions
13th Mar 20187:00 amRNSPRELIMINARY RESULTS ANNOUNCEMENT YEAR ENDED 2017
24th Jan 20187:00 amRNSQ4 2017 PRODUCTION REPORT
25th Oct 20177:00 amRNSQ3 2017 PRODUCTION REPORT
14th Sep 20173:30 pmRNSInterim Dividend Payable
22nd Aug 20177:00 amRNSHALF YEARLY FINANCIAL REPORT JUNE 2017
9th Aug 201710:16 amRNSAntofagasta Half Year 2017 Results - Webcast
26th Jul 20177:00 amRNSQ2 2017 PRODUCTION REPORT
23rd Jun 20177:00 amRNSREPORT ON PAYMENTS TO GOVERNMENTS
24th May 20173:26 pmRNSResults of Annual General Meeting
24th May 20177:00 amRNSCHAIRMAN'S COMMENTS AT THE 2017 AGM
8th May 201710:56 amRNSFINAL DIVIDEND PAYABLE
26th Apr 20177:00 amRNSQ1 2017 PRODUCTION REPORT
11th Apr 20177:00 amRNSPUBLICATION OF 2016 ANNUAL REPORT & NOTICE OF AGM
3rd Apr 201710:00 amRNSNOTIFICATION OF TRANSACTIONS
21st Mar 201711:00 amRNSREKO DIQ PROJECT - Arbitration Ruling
14th Mar 20177:00 amRNSPRELIMINARY RESULTS FOR THE YEAR ENDED 2016
2nd Mar 20177:00 amRNSAntofagasta Preliminary Results
25th Jan 20177:00 amRNSQ4 2016 PRODUCTION REPORT
20th Jan 20177:00 amRNSALTO MAIPO PROJECT
16th Dec 201611:11 amRNSTWIN METALS MINNESOTA MINING LEASES
15th Dec 201612:03 pmRNSDirector Declaration
5th Dec 20168:16 amRNSINVESTOR AND ANALYST SITE VISIT
30th Nov 20167:00 amRNSCHANGES TO BOARD COMMITTEES
28th Nov 20167:00 amRNSSALE OF MICHILLA
28th Oct 20165:05 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
26th Oct 20163:16 pmRNSBOARD CHANGES
26th Oct 20167:00 amRNSQ3 2016 PRODUCTION REPORT
21st Oct 20161:00 pmRNSTR-1: Notification of major interest in shares
16th Sep 20169:57 amRNSINTERIM DIVIDEND PAYABLE
16th Aug 20167:00 amRNSHALF YEARLY FINANCIAL REPORT
15th Aug 20167:00 amRNSDirectorate Change
27th Jul 20167:00 amRNSQ2 2016 PRODUCTION REPORT
23rd Jun 20167:00 amRNSReport on Payments to Governments
18th May 20161:45 pmRNSResults of Annual General Meeting
18th May 20167:00 amRNSCHAIRMAN'S COMMENTS AT THE 2016 AGM
3rd May 20161:04 pmRNSDIRECTOR DECLARATION
27th Apr 20167:00 amRNSQ1 2016 PRODUCTION REPORT
8th Apr 201612:00 pmRNSAppointment of New CEO

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.