Coal to Methanol - Technical Feasibility Study

5 Aug 2013 07:00

RNS Number : 9014K
Altona Energy PLC
05 August 2013
 



5 August 2013

 

Altona Energy Plc

("Altona")

 

Arckaringa Project

Coal to Methanol - Technical Feasibility Study

 

Altona Energy (AIM:ANR) is pleased to announce that it commissioned the UK branch of a leading international engineering firm to conduct a Technical Feasibility Study ("TFS") for a Coal to Methanol ("CTM") plant based on the Arckaringa coal resources. The TFS has now been received and a summary is set out below.

 

Background

Arckaringa in South Australia is a prime location for a Coal-to-Liquids ("CTL") and Power project, which remains the current focus of the ongoing CNOOC joint venture. However the board has observed the continued growth in global methanol demand, particularly in Asia, with methanol being used increasingly as a fuel additive and feedstock for a wide range of high value products including acetic acid, Di-Methyl Ether, formaldehyde, olefins and gasoline. Methanol prices have been averaging more than US$400/tonne in recent years.

 

With the use of well proven and commercially available CTM technologies, there is an opportunity to enhance the inherently low in situ value and cost of Arckaringa coal beyond CTL and Power.

 

The high returns and diverse markets for Methanol, combined with Arckaringa's coal resource, which is capable of sustaining a wide range of coal conversion options or projects for a hundred years or more, make CTM a potentially valuable additional option for the Project. Furthermore methanol production could also provide a hedge against oil and gas price volatility in the future.

 

Technical Feasibility Study

The recently completed TFS demonstrated that CTM could be a viable project capable of augmenting the Bankable Feasibility Study ("BFS") for Altona's flagship Arckaringa Clean Energy CTL and Power Project in South Australia. The original CTL proposal was for a 45,000 Barrels per day ("BPD") CTL facility developed in three separate 15,000 BPD/ 280MW phases over a 10 year period. The CTM study proposes that one 15,000 BPD train is replaced by a 6,200 Methanol Tonne per day ("MTPD") CTM Plant to be built in tandem with a 15,000 BDP CTL Plant rather than building the first 2 CTL plants in series. 

 

Altona will now present the CTM project to the Arckaringa JV partner CNOOC for further evaluation. The highlights of the study are as follows:

 

·; The CTM project is still essentially based on the conversion of Arckaringa coal into syngas via above ground coal gasification and the study confirmed that:

o The same quantity of gasified coal needed to make 15,000 barrels per day of FT liquids could instead produce 6,200 Tonnes per day of methanol.

o The available power was sufficient to operate the CTM plant - The retained 15,000 BPD CTL plant produces 280 MWhr of excess electricity with the CTM Plant expected to utilise ~95% of this.

o The CO₂ emissions from the CTM plant were 0.3 tonnes of CO₂ per tonne of methanol.

o The investment costs for CTL / CTM plant were essentially the same as the two train CTL plant.

·; Furthermore Altona's in house study estimated that the CTL/CTM plant would potentially increase annual project revenue significantly, when compared to a CTL only plant, by approximately US$ 212 million, or 18%.

 

A copy of the report is available on the Company's website. The report can be accessed via the 'Feasibility Studies - CTM' link on the Project Development page on the website (www.altonaenergy.com/project.php)

 

Altona's Executive Director Technology, Peter Fagiano, commented: "CTM offers a real opportunity to further enhance the already favourable project economics at Arckaringa. The study has confirmed our preliminary views, and Altona will now present the project to the Joint Venture for evaluation at the BFS level and potentially to other external parties with a special interest in the growing market for methanol production."

 

For further information, please visit www.altonaenergy.com or contact:

 

Altona Energy Plc

Christopher Lambert, Chairman

Christopher Schrape, Managing Director

Peter Fagiano, Executive Director 

 

 +44 (0) 20 7024 8391

 

WH Ireland Ltd

Adrian Hadden

James Bavister 

 +44 (0) 20 7220 1666

Old Park Lane Capital Plc

Michael Parnes

Luca Tenuta 

 

 +44 (0) 20 7493 8188

Tavistock Communications

Mike Bartlett

Simon Hudson

 +44 (0) 20 7920 3150

 

About Altona Energy

Altona Energy is listed on the London Stock Exchange's AIM market. Its current focus is firmly on the evaluation and development of the Company's 49% interest in its flagship coal-to-liquids Arckaringa Project to exploit the huge coal resources contained in three exploration licences covering 2,500 sq. kms in the northern portion of the Permian Arckaringa Basin in South Australia. The Base Case Project is designed to include a modern, combined-cycle power station adding electricity to the national grid and to produce clean burning fuel for Australia and the world from a resource equivalent to 7.8 billion barrels. Altona Energy has forged a Joint Venture with CNOOC New Energy Investment Co., Ltd., a subsidiary of the China National Offshore Oil Corporation (CNOOC), to complete the Project Bankable Feasibility Study and expedite the Project's development.

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSSEFSLFDSEIA
Date   Source Headline
23rd Nov 20177:30 amPRNBoard Changes and Grant of Options
23rd Nov 20177:00 amPRNPlacing
16th Nov 20177:28 amPRNCommissioning of Further Coal Study
9th Nov 20173:07 pmRNSHolding(s) in Company
9th Nov 201712:28 pmRNSHolding(s) in Company
3rd Nov 20178:13 amPRNBoard Appointment
1st Nov 201711:53 amPRNNotification made in Error
1st Nov 201711:22 amPRNLaunch of First Star Academies - UK
31st Oct 20171:16 pmPRNResult of General Meeting
13th Oct 201712:00 pmPRNPlacing and Notice of General Meeting
11th Oct 201710:44 amRNSClaim Update
25th Sep 20177:00 amRNSCompany Update
11th Sep 20177:00 amPRNDirector/PDMR Shareholding
10th Aug 20179:32 amPRNStrategy Update
7th Jul 20177:00 amPRNPlacing
3rd Jul 20177:00 amRNSPetroleum Exploration Licence Application Update
16th May 20177:00 amPRNPEL Application Update
28th Apr 20179:18 amRNSChange of Registered Office
31st Mar 20177:00 amRNSInterim Results
29th Dec 20162:08 pmRNSAGM Statement
9th Dec 20167:00 amPRNAGM Information
2nd Dec 20167:00 amRNSFinal Results
18th Oct 20167:00 amRNSPEL Application
6th Sep 20168:14 amPRNUpdate on Joint Venture
28th Jul 20169:13 amPRNUpdate on Joint Venture
27th Apr 20167:00 amRNSBusiness Update
21st Apr 20167:00 amRNSFurther Sino-Aus Financial Contribution
12th Apr 20168:58 amRNSSino-Aus Financial Contribution
1st Apr 201612:42 pmRNSResult of General Meeting
24th Mar 201610:52 amRNSDirectorate Change
17th Mar 20167:00 amRNSProposal for Share Option Scheme
9th Mar 20169:15 amRNSUpdate on Sino-Aus
7th Mar 20167:00 amRNSHMRC Enquiry Closed
4th Feb 20167:00 amRNSInterim Results
25th Jan 20167:00 amRNSSubscription and JV Contribution
18th Jan 20167:00 amRNSUpdate on Subscription and JV Contribution
23rd Dec 20157:00 amRNSNotification of Subcription by Sino-Aus
18th Dec 20153:00 pmRNSDirector Dealing
16th Dec 20151:06 pmRNSAGM Statement
23rd Nov 20157:00 amRNSFinal Results
5th Nov 20157:00 amRNSJoint Venture Agreement
27th Oct 201510:06 amRNSUpdate on Joint Venture
10th Jul 20157:00 amRNSBusiness Update
15th Jun 20159:06 amRNSAppointment of Non Executive and Update
16th Apr 20157:00 amRNSDirectorate Change and Update
31st Mar 20159:11 amRNSJV Update
9th Mar 20157:00 amRNSInterim Results
13th Feb 20157:30 amRNSUpdate on Joint Venture
14th Jan 20157:00 amRNSSouth Australian Government Consent
7th Jan 20157:00 amRNSDirectorate Change

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.