Operational Update

30 Jul 2013 07:00

RNS Number : 3948K
Hambledon Mining PLC
30 July 2013
 



30 July 2013

Hambledon Mining Plc

("Hambledon" or "the Company")

 

Activities Report for the Second Quarter Ended 30 June 2013

 

Hambledon Mining plc (AIM: HMB), the gold mining and development group, today provides its operational update for the Sekisovskoye deposit for the three months to 30 June 2013.

Highlights include:

·; The underground mine at Sekisovskoye became operational in mid-June 2013 - a key milestone in the Company's development - and had an average mined gold grade of over 4 grams per tonne. Notwithstanding the delays and problems experienced last year, the new management has managed to start underground mining on time and within budget.

 

·; Hambledon produced 7,589 ounces of gold during the second quarter of 2013. This represents a 30 per cent increase in production year on year and a circa. 50 per cent increase compared with the previous quarter.

·; Increased production has been driven by a nine per cent year on year increase in ore milled and a higher ore grade, sourced from the open pit mine and complemented by ore extracted from the underground mine.

 

·; Increase in gold grade was a function of both the rich underground ore grade as well as higher open pit grade, the latter being a result of the deeper mining operations nearing the high grade ore body. This high grade ore body is also the target, at varying depths, of the underground mining operations.

Aidar Assaubayev, CEO of Hambledon Mining commented:

"I am very pleased that the underground mining has started on time and within budget. I expect the underground mine development to transform Hambledon into a company with a strong and rising gold production profile as well as a competitive cost structure, creating significant value for shareholders even at the current gold price. We are committed to demonstrably enhancing the value of the Company's assets and further optimising operational and financial performance."

 Processing Plant and Underground Mine

The recovery rate at the processing plant was below target in May 2013 due to the high variability of gold grade in the feed ore. The recovery rate was restored from 76.5 per cent in May to the budgeted level of 83.2 per cent in June.

The mining of ore from the underground mine commenced in mid-June 2013 with 5,016 tonnes of ore processed at the plant and tests undertaken, before 30 June 2013, to ascertain optimal mix and recovery rates of the underground ore.

·; In a test with a 50:50 ratio of underground ore and open pit ore, with an overall gold content of 2.1 grams per tonne, the achieved recovery rate was 82.67 per cent.

 

·; In a test using solely underground ore, with a gold content of 4.04 grams per tonne, as the source of material for the plant, the achieved recovery rate was 91.3 per cent for gold and 95.4 per cent for silver.

 

These recovery rates are a positive indicator for the future productivity of the plant, when the source material consists of only underground ore, which is forecast to be the case from mid-2015, when the production life of the open pit comes to an end.

Production figures

Production figures for three months from April 1 to June 30 2013:

April

May

June

Total

Total ore mined, t

63,504

74,839

75,020

213,363

Total ore milled, t

59,203

69,312

66,712

195,227

Gold grade, g/t

1.42

1.55

1.50

1.49

Contained gold, oz

2,700

3,465

3,220

9,384

Gold recovery, %

83.7

76.5

83.2

80.9

Recovered gold, oz

2,260

2,652

2,678

7,589

Recovered silver, oz

3,032

3,131

2,912

9,075

 

Of which:

April

May

June

Total

Underground ore mined, t

5,200

5,200

Underground ore milled, t

5,016

5,016

Gold grade, g/t

4.04

4.04

Contained gold, oz

690

690

Contained silver, oz

1,222

1,222

 

A copy of this report will be available on the company's website, www.hambledon-mining.com

 

 

 

 

Enquiries:

Hambledon Mining plc

Bogdan Poustovoi (Investor Relations)

 

+44 (0) 207 932 2455

Strand Hanson (Nomad and Broker)

Andrew Emmott

James Spinney

James Dance

 

+44 (0) 207 409 3494

 

 

Blythe Weigh Communications

Tim Blythe

Halimah Hussain

Eleanor Parry

+44 207 138 3204

 

+44 (0) 7816 924626

+44 (0) 7725 978141

+44 (0) 7551 293620

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPGUBWMUPWGCB
Date   Source Headline
20th Jan 20159:47 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
19th Jan 20157:00 amRNSKarasuyskoye Ore Fields Licence Update
19th Dec 20147:00 amRNSFirst Day of Trading on Official List
16th Dec 201411:49 amRNSAdmission to UKLA Official List & LSE Main Market
20th Nov 20146:11 pmRNSAdmission to Standard Segment of Official List
17th Nov 20147:00 amRNSCPR Results and an Upgrade on Resource and Reserve
8th Oct 20147:00 amRNSExploration Drilling
30th Sep 201412:51 pmRNSInterim Report
19th Aug 20147:00 amRNSOperational Update H1 2014
11th Aug 20147:00 amRNSApproval for Sekisovskoye Development Plans
30th Jun 20143:29 pmRNSAccounts Posting and Result of AGM
23rd Jun 20144:29 pmRNSHolding(s) in Company
17th Jun 20149:30 amRNSFinal Results
6th Jun 20144:29 pmRNSNotice of AGM
3rd Jun 20147:00 amRNSSekisovskoe Mine Update
24th Mar 20147:00 amRNSGoldbridges does not have to pay $9.4m fine
14th Mar 20147:00 amRNSHolding(s) in Company
10th Mar 20147:00 amRNSFurther Update re Placing
7th Mar 201412:40 pmRNSHolding(s) in Company
5th Mar 20147:00 amRNSUpdate re Placing
28th Feb 20147:01 amRNSCompletion of GBP11.96 million Placing
14th Feb 20144:41 pmRNSHolding(s) in Company
4th Feb 20147:15 amRNSFourth Quarter and Full Year Operational Update
29th Jan 20147:00 amRNSChange of Name to GoldBridges Global Resources plc
13th Jan 20142:15 pmRNSResult of General Meeting
10th Jan 20147:00 amRNSCompletion of £1.93 million Placing
24th Dec 20131:15 pmRNSShare Authorities Renewal, Name Change & GM Notice
16th Dec 20137:00 amRNSConversion of Convertible Loan Notes
6th Dec 20137:00 amRNSStrategic Review of Mining Operations
12th Nov 20137:01 amRNSAppointment of Joint Broker
30th Oct 20137:00 amRNSQuarterly Report 30 September 2013
23rd Oct 201312:00 pmRNSResult of General Meeting
23rd Oct 20137:00 amRNSBoard Changes - New Chairman and Two New INEDs
21st Oct 20137:00 amRNSVenmyn Deloitte Appointment
4th Oct 20137:00 amRNSKarasuyskoye Ore Fields Transaction
23rd Sep 20137:00 amRNSInterim Results
6th Sep 20137:00 amBUSNotice of EGM
5th Aug 201310:25 amRNSTailing Dam 3 Fines Update
30th Jul 20137:00 amRNSOperational Update
28th Jun 20133:49 pmBUSResult of AGM
6th Jun 20135:50 pmRNSFinal Results
30th Apr 20132:35 pmRNSReport for Quarter Ended March 31 2013
20th Feb 20132:52 pmRNSChange of Adviser and Directorate Changes
8th Jan 201312:57 pmBUSHolding(s) in Company
24th Dec 20127:00 amBUSDirectorate Change
24th Dec 20127:00 amBUSHolding(s) in Company
17th Dec 20127:00 amBUSSenior Management Appointment
12th Dec 201210:02 amBUSDrilling Update
10th Dec 20123:56 pmBUSHolding(s) in Company
7th Dec 20123:04 pmBUSDirectorate Change

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.