Briquetting Update

30 Jan 2013 09:32

null

Watermark Global Plc ("Watermark" or the "Company")

Watermark advises shareholders that it's 40% owned associate company, Mine Restoration Investments Limited ("MRI") listed on the AltX of the Johannesburg Stock Exchange, recently made the following announcement:

UPDATE ON COMPLETION OF THE ANTHRACITE BRIQUETTING PROJECT ("BRIQUETTING PROJECT")

1. Introduction

Shareholders are referred to the circular dated 2 April 2012 ("the circular"), wherein they were advised, inter alia, that MRI had concluded an agreement with Water Utilities Limited ("Water Utilities"), a BVI company incorporated in the United Kingdom, and its holding company, Watermark Global PLC, an AIM listed company, for the acquisition of Western Utilities Corporation (Pty) Ltd ("WUC"), a wholly owned subsidiary company of Water Utilities and the owner of a 51% interest in Octavovox (Pty) Ltd, the company in which the briquetting project, which will be the main commercial business of MRI, is held ("the acquisition"). The acquisition was approved by MRI shareholders on 30 April 2012.

The circular incorporated details of the briquetting project. At the time of the circular it was anticipated that the project would be completed shortly thereafter and that production would be commissioned within 9 months, followed by a three month ramp-up period to full production. The circular also contained a profit forecast based on the time periods documented above.

2. Update on completion of the briquetting project

Due to a number of factors it is currently expected that commissioning will commence in April 2013 with full production of the briquetting project commencing in June 2013.

The reasons for the delay are as follows:

2.1 The replacement of the preferred contractor for the construction of the briquette rollers (which took place during the course of completion) due to its failure to deliver timeously and properly in terms of the construction contract;

2.2 Price escalations exceeding initial allocations, which led to scope changes;

2.3 A requirement to undertake additional studies and reports, such as a geotechnical report, traffic impact study, infiltration test work report and dam stability report;

2.4 Changes to the EMP (Environmental Management Programme) addendum - while the approval was expected to be imminent it took longer than expected.

The delay has also impacted on the costs of the completion of the briquetting project, which is expected to be covered by an existing loan agreement with MRI's two major shareholders: Watermark Global Plc and Trinity Asset Management (Pty) Ltd.

The pilot plant work on the fines produced by the mine has indicated that the Intellectual Property relating to the binders to be used has produced stable briquettes which handle well and adhere to the specified requirements with regards to strength and water repulsion.

Enquiries:

Investor Relations

Charles Zorab Tel: + 44(0) 20 7233 1462

czorab@watermarkglobalplc.com

Nominated Adviser:

Cenkos Securities

Ian Soanes Tel: +44(0)20 7397 8900

Copyright Business Wire 2013

Date   Source Headline
27th Mar 20188:15 amBUSMahenge Liandu Scoping Study Delivers NPV of US$349m with 122% IRR
19th Mar 20187:00 amBUS31 Year Mine Plan Completed for Mahenge Liandu Graphite Project
2nd Mar 20181:16 pmBUSStatement re Broker
7th Feb 201810:00 amBUSMahenge Liandu Resource Upgrade to 51.1Mt at 9.3% TGC with 75% now in the Indicated Category
29th Jan 20187:00 amBUSExploration Update and Licencing Applications Commence at Mahenge Liandu
12th Jan 20187:00 amBUSArmadale agrees to sell non-core Mpokoto Project
2nd Jan 20187:00 amBUS98.2% Purity Achieved from Bulk Test Work at Mahenge Liandu
19th Dec 20179:00 amBUSIssue of Equity
27th Nov 20177:00 amBUSIssue of Equity
23rd Nov 201710:30 amBUSAppointment of Study Manager and Development Update
7th Nov 20178:31 amBUSExcellent Drilling Results Continue at Mahenge Liandu
20th Oct 20178:30 amBUSFunding Secured to Advance Development of Mahenge Liandu Graphite Project
29th Sep 20177:00 amBUSHigh Value Graphite Concentrate with +48% in Super Jumbo, Jumbo and Large Flake Size Produced
26th Sep 20177:00 amBUSInterim Results
7th Sep 20177:00 amBUSExceptional Graphite Concentrate of up to 99.1% Graphitic Carbon Produced from Mahenge Liandu
17th Aug 20177:00 amBUS1.2km Mineralised Strike Identified at Mahenge Liandu Graphite Project
1st Aug 20177:00 amBUSExcellent Drilling Results Continue at Mahenge Liandu Graphite Project
19th Jul 20177:00 amBUSExploration Update at Mahenge Liandu Graphite Project, Tanzania
13th Jul 201712:01 pmBUSConvertible Note Update
4th Jul 20172:31 pmBUSTanzanian Legislation
26th Jun 20174:35 pmBUSResult of AGM
26th Jun 20177:00 amBUSAGM Statement
21st Jun 20177:00 amBUSExploration Update: Trenching Intercepts Wide Zones of High Grade Graphite
5th Jun 20177:00 amBUSUpdate on 2017 Exploration Programme at Mahenge Liandu Graphite Project
2nd Jun 20177:00 amBUSFinal Results
3rd May 20177:00 amBUSGraphite Concentrate Upgraded to Purity of up to 99.99% Graphitic Carbon
21st Apr 20179:31 amBUSExcellent Test Results for Mahenge Liandu Graphite Concentrate
29th Mar 20177:00 amBUS2017 Mahenge Liandu Exploration Programme Commenced: Targeting Resource Increase and Upgrade
28th Feb 201712:47 pmBUSDirectorate change
2nd Feb 201711:45 amBUSInitial Metallurgical Test-work Results
23rd Jan 20172:16 pmBUSDirector/PDMR Dealing
20th Jan 20174:12 pmBUSNew Corporate Website - Replacement
20th Jan 20173:40 pmBUSNew Corporate Website
18th Jan 20177:00 amBUSPlacing to Raise £650,000
5th Jan 20177:00 amBUSNumber of Shares in Issue
8th Dec 20167:00 amBUSMaiden JORC Compliant Mineral Resource Estimate of 40.9Mt @ 9.41% Total Graphitic Content
5th Dec 20167:00 amBUSJoint Venture Agreement Proceeding on Mpokoto Gold Project
11th Nov 201610:00 amBUSHolding(s) in Company
8th Nov 20167:00 amBUSInitial Assay Results Confirm High-Grade Graphite Mineralisation up to 26% TGC
2nd Nov 20169:45 amBUSHolding(s) in Company
26th Oct 20167:00 amBUS85% Strike Rate of High Grade Graphite Mineralisation from Drilling at Mahenge Liandu, Tanzania
18th Oct 20167:00 amBUSPositive Drill Results from Mahenge Liandu Graphite Project
18th Oct 20167:00 amBUSDirectorate change
11th Oct 20167:00 amBUSIssue of Equity
7th Oct 20167:00 amBUSDiscovery of High-Grade Coarse Flake Graphite Mineralisation Mahenge Liandu Project
28th Sep 20167:39 amBUSBinding HOA to Form Joint Venture to Develop Mpokoto and Directorate Change
23rd Sep 20167:00 amBUSDrilling Commences at the Mahenge Liandu Graphite Project, Tanzania
22nd Sep 20167:00 amBUSInterim Results
16th Aug 20167:00 amBUSGeological Mapping Identifies Extensive Outcropping Mineralisation at Mahenge Liandu Graphite Project, Tanzania
10th Aug 20167:00 amBUSDirectorate Change

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.