Operational Update

5 Aug 2019 07:00

RNS Number : 8205H
Anglo African Oil & Gas PLC
05 August 2019
 

Anglo African Oil & Gas PLC / Index: AIM / Epic: AAOG / Sector: Oil & Gas

 

ANGLO AFRICAN OIL & GAS PLC ('AAOG' or the 'Company')

Operational Update

 

Anglo African Oil & Gas plc, an independent oil and gas developer, is pleased to provide an operational update following the successful results from drilling the TLP-103C well at the producing Tilapia oil field in the Republic of the Congo. This update sets out details of the Company's plan to re-enter TLP-103C and seek to bring the Djeno reservoir into production.

Overview of operational plan

The Company will seek to bring the Djeno into production by re-entering well TLP-103C and drilling a sidetrack just below the Mengo horizon. This sidetrack will be designated TLP-103CST1 and will initially deviate away from TLP-103C for a short distance before continuing vertically downwards. This design reduces the risk of shifting too far from the original location where the Company logged positive results.

TLP-103CST1 will vertically intersect the Top Djeno and then continue into the Middle Djeno, which was below the total depth of TLP-103C. Once the Middle Djeno has been tested, the Company will determine whether the Djeno can be brought into production from either horizon. In parallel, limited but necessary upgrades will be carried out to the topside facilities to ensure that the Company can produce from the well immediately following testing.

Technical details of the drilling plan

TLP-103CST1 is designed as a low side sidetrack. A land drilling rig will be used to clean out the 9 5/8" casing down to the current casing shoe depth at 2,100m measured depth (MD), using seawater with hi-viscosity mud sweeps. The well will then be displaced to a potassium chloride polymer water-based mud system, and a casing pressure test will be conducted to 80% of the casing burst rating. A further 5m of the original 8 ½" hole will be cleaned out, and a formation integrity test will be performed prior to drilling out the remainder of the lower cement plug to re-enter the previous 8 ½" open hole.

In preparation for drilling the sidetrack, a new cement plug will be set inside the 8 ½" open hole below the 9 5/8" casing shoe. The kick off plug is designed to have a compressive strength in excess of the formation strength to allow for successful kick off operations.

The 8 ½" hole sidetrack will be drilled directionally from a planned kick off point of 2,200mMD (approximately 100m below 9 5/8" casing shoe). Drilling parameters have been defined to achieve a 3 degree/100ft dogleg, dropping angle from 35 degrees to 0 degrees inclination, maintaining the same azimuth to attain a ±200m step out compared to TLP-103C at the same true vertical depth.

The 8 ½" hole section will continue to be drilled vertically down to an approximate target depth of 2,900m true vertical depth (TVD), through both the upper and middle Djeno reservoir targets.

Drilling through the reservoir sections will be carefully monitored so that the differential pressure will be maintained at a minimum 100-200psi above hydrostatic pressure so as to minimise formation invasion and minimise the potential for loss of circulation

A comprehensive suite of formation evaluation logs will be acquired across the Top and Middle Djeno reservoirs, including resistivity, sonic, density-neutron, spectral gamma ray, formation pressures, formation samples and mechanical sidewall cores will be retrieved.

Following this, a 7" liner will be run and cemented across the open hole interval in readiness for producing the Djeno reservoirs. Using High Shot Density perforation guns, the Djeno reservoir will be perforated prior to running the Completion string. Assuming that all results at this stage are positive, the well will be flowed tested and cleaned before putting TLP-103CST1 on production, utilising the existing surface facilities.

The Company has posted on its website two technical drawings which illustrate the above plan.

Planning of operations

The Company has identified two suitable drilling rigs, both currently situated in the Republic of the Congo, which have drilling slots available this year. The company is evaluating commercial offers from both rig companies and will update the market once the chosen rig is contracted.

Topside infrastructure

As stated above, the Company intends to minimise the scope of initial works in order to control capital costs ahead of drilling TLP-103CST1. Following these initial works, the topside facilities are estimated to be able to handle production of approximately 2,000bopd. The Company is, however, developing plans to further improve the topside facilities based upon several different levels of potential future production, with the exact plan to be finalised only once actual flow rates are known.

 

The Company confirms that the court in the Republic of the Congo has lifted the seizure order obtained by SMP against certain of the Company's subsidiary's assets.

The Company will provide further updates on the above operational points and plans in due course.

**ENDS**

 

For further information please visit www.aaog.com or contact:

Anglo African Oil & Gas plc

Tel: c/o St Brides Partners +44 20 7236 1177

David Sefton, Executive Chairman

James Berwick, Chief Executive Officer

 

 

 

finnCap Ltd (Nominated Adviser and Broker)

Tel: +44 20 7220 0500

Christopher Raggett, Giles Rolls, Teddy Whiley (Corporate Finance)

 

Camille Gochez (ECM)

 

 

 

St Brides Partners (Financial PR)

Tel: +44 20 7236 1177

Frank Buhagiar, Hugo de Salis

 

 

Notes to Editors

Anglo African Oil & Gas (AAOG) is an AIM-listed independent oil and gas company that owns a 56% stake in the producing Tilapia oil field in the Republic of the Congo. The Company boasts a low-cost production story in a prolific hydrocarbon region with significant exploration upside, differentiating it substantially from its E&P peers. Additionally, management's remuneration is tied to hitting production milestones, reflecting their strong focus on cost control.

Tilapia is located close to multi-billion-barrel fields that include the ENI-operated Litchendjili field and the 5,000bopd Minsala Marine field. Tilapia currently produces approximately 38 bopd from two near-surface intervals. It has an undeveloped discovery in the lower Mengo sands with gross contingent resources of 8.1m barrels and a deeper exploration prospect, with gross prospective resources of 58.4m barrels, in the productive Djeno interval from which the adjacent Minsala field produces. 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDBIGDILGGBGCS
Date   Source Headline
13th Nov 201812:03 pmRNSResult of General Meeting
8th Nov 20187:00 amRNSOperational Update
24th Oct 20187:00 amRNSOperational Update and Financing Facility
19th Oct 201811:05 amRNSSecond Price Monitoring Extn
19th Oct 201811:00 amRNSPrice Monitoring Extension
28th Sep 20187:00 amRNSHalf-year Report
24th Sep 20187:00 amRNSUpdate on Drilling Programme
7th Sep 20187:00 amRNSUpdate on TLP 103 well on Tilapia field
5th Sep 20189:05 amRNSSecond Price Monitoring Extn
5th Sep 20189:00 amRNSPrice Monitoring Extension
5th Sep 20187:00 amRNSTemporary suspension of drilling at Tilapia Field
22nd Aug 20183:30 pmRNSShareholder Q&A Podcast
15th Aug 201812:32 pmRNSCommencement of drilling at Tilapia oil field
13th Aug 201811:35 amRNSPre-spud Ceremony
2nd Aug 20187:00 amRNSRig Update
20th Jul 201812:43 pmRNSResult of General Meeting
11th Jul 20187:00 amRNSRig Mobilisation for Multi-Horizon Well
29th Jun 20182:32 pmRNSResult of AGM
29th Jun 20187:00 amRNSFinal results and Notice of Annual General Meeting
27th Jun 20187:00 amRNSHolding(s) in Company
25th Jun 20187:00 amRNSUpdate on workover of TLP-102 and rig for TLP-103
14th Jun 20188:15 amRNSHolding(s) in Company
7th Jun 20187:00 amRNSShareholder Conference Call
7th Jun 20187:00 amRNSHolding(s) in Company
4th Jun 201811:30 amRNSResult of General Meeting
17th May 20186:00 pmRNSConditional Placing and Notice of GM
3rd May 20187:00 amRNSOperational and financial update
17th Apr 20187:00 amRNSUpdate on workovers
19th Mar 20187:00 amRNSOperational Update
5th Mar 20187:00 amRNSOperational Update
16th Feb 201811:31 amRNSManagement Share Incentive Scheme
23rd Jan 20187:00 amRNSBoard changes
14th Dec 20178:20 amRNSManagement Share Incentive Scheme
11th Dec 20172:05 pmRNSSecond Price Monitoring Extn
11th Dec 20172:00 pmRNSPrice Monitoring Extension
11th Dec 20177:00 amRNSCorporate Update
26th Sep 20177:00 amRNSHalf Year Report
25th Sep 20177:00 amRNSBoard Change
14th Sep 20177:45 amRNSOperations Update
11th Aug 201710:30 amRNSHolding(s) in Company
10th Aug 201710:40 amRNSHolding(s) in Company
7th Aug 201712:50 pmRNSHolding(s) in Company
4th Aug 20177:00 amRNSSecondary Completion of Petro Kouilou
24th Jul 20177:00 amRNSOperations Update
29th Jun 201711:20 amRNSResult of AGM
6th Jun 20177:00 amRNSFinal Results
1st Jun 20177:00 amRNSHolding(s) in Company
26th May 201711:05 amRNSSecond Price Monitoring Extn
26th May 201711:00 amRNSPrice Monitoring Extension
26th May 20177:00 amRNSUpdate on first workover at Tilapia oil field

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.