RE: Angus Energy CEO George Lucan predicts 1.5M therms in May, 3M by August - debt free by the year-end1 Apr 2022 12:40
Taverham, we can forget March as we all agreed that gas in March was not possible.
However, gas next month is perfectly doable, is a matter of planning the work and from what GL disclosed he is on the right path.
Cable installation begins shortly, if it hasn’t already started. Equipment can be installed and precommissioned as it arrives. Compressors and packages would have already been tested at the Vendor’s works and they would need is installation and integration within the overall control and safety systems.
Most of this work will be done this month as equipment arrives at site. Flare, fuel skid, flare knockout drum, metering package, analyser package … are already at site.
As we saw from the pictures most of the pipework is already done. Pipes are laid out and welded. Welding was 40% completed in last GL interview according to him. Weld radiography can be happening in parallel to welding. Then sections of piping can be isolated and pressure tested.
From the pictures, looks like that outstanding pipework are runs to connect to equipment.
Last package arrives late April. Be generous and allow two weeks for installation and integration - job done by latest mid-May.
Let the gas in and fully commission - another two weeks - production by end of May.