RE: Look at Navitas share price29 Feb 2024 11:50
Doing a bit of very rough back scheduling from end of 2026 First Oil date - they are going to need to get a wriggle on to get everything in place.
Vendors would have to start working based on some early letters of intent or FID is going to need to be sooner than later for order placement of all the hardware (Trees, manifolds and jumpers, controls system). Some of that has 12 - 18 months lead time.
All of that will need to be built, tested, then shipped.
Its a long way to ship by sea, so the kit will likely need a further inspection and potential test prior to deployment - so a local facility in the FI will be needed to allow local rework/checks to be carried out prior to deployment.
Such a facility currently doesnt exist. So that will need investment (cranage, pumps, test skids, flushing skids, etc, which although may be discussed and costed is unlikely to be moved forward until FID happens.
Looking at the date of accommodation requirements of end of Q2, 25 would give about 6 months for staff to get all that in place before start of hardware arrival if long lead orders placed at that time of FID.
As even after deployment and hook up there will need to be a period of commissioning of all the systems from subsea to FPSO before opening up the taps to get first oil.
So, I'm half expecting FID mid 2024 based on activities that need to happen to meet the end date.