RE: Equipment8 Dec 2021 09:18
More info due from company this month :
Site civil engineering is under tender and slated to begin in mid-December running through to mid-
January, starting with piling, foundationing and, where appropriate, bunding for the flare, storage
tanks and compressors and ending with pipe racks supports. Pipework procurement has also begun
and welding is scheduled to take place on a continuous basis from early January through to the end of
February. Electrical, control and instrumentation installation layout will begin at the end of January
with tie-in to particular skids as they arrive.