The works on the Araguaia Project continue in full swing! Approximately 28% of the total construction has already been completed, a result that ensures that we are on schedule to start production in q1 2024.
The foundations of the electric arc furnace have been successfully completed and the bottom section of the oven, which is already on site, is expected to start assembly in the coming days. The electromechanical assembly has also begun with the installation of the first structures of the oven building. (See below the video of the completion of the concreting)
"In general, this was a year of transformation for Horizonte Minerals. I thank our employees, contractors and key stakeholders for their efforts so far to advance the construction of the Araguaia Project. This will quickly add more value to Araguaia as we approach the production of the first nickel," said Jeremy Martin, CEO of Horizonte Minerals.