RE: I asked AI what we could be worth @ 1M oz/year10 Apr 2026 16:57
Ricardo
I assume you mean produce rather than process and the quick answer is no which i base on the following and assume no additional
processing capacity is added
we know one train will be down graded to 6mtpa to process Hav and without re-reading rns and presentations will produce around 250k Ozs
this would leave about 14mtpa of process capacity which to produce a further 750k Ozs would require a head grade assuming 85% recover of just about 2g/t keeping it to round numbers
a second check would be best every year at Telfer was again round numbers 600k Ozs so adjust this from 20 to 14mtpa would give 420 kOzs so i think 650 to 700k Ozs would be the peak without upgrades and only for a few years so 500 to 600k ozs is more realistic without upgrades and increased tonnage from Hav beyond what is currently proposed