RE: RE: Overall positive6 Jun 2023 08:55
Not quite right SCE2 or Ezhik. Excerpt below
While the Company is pleased to note that the Slawson wells have been drilled and fully completed (with no remaining drilling or completion risk exposure to the Company), Slawson recently provided an update to the expected schedule for related surface facilities build-out. As a result, the Company now expects to see first production from the wells in October 2023 and first cashflows in January 2024 (versus earlier forecasts of March 2023 and August 2023, respectively).