Current position (late May 2026)2 Jun 2026 13:01
All principal contracts finalised. Lycopodium has issued 14 detailed engineering packages for final approval and the SAG mill — highest-value, longest-lead item — has been ordered. The 47km grid connection is underway with the first substation well advanced and all towers delivered to the district. Two access roads to site are under construction. Resettlement housing (350 units) is active, with bulk earthworks by BCM gated on licence area clearance.
On security, a permanent government protection force is in place as a formally contracted lender condition precedent, independently inspected and signed off prior to AFC/TDB financial close, layered over private on-site security. Commitment risk is low given the sovereign liability implications of any degradation. The residual risk is sufficiency rather than intent — specifically whether the protection architecture covers the full logistics corridor rather than just the site perimeter, and whether ENDF overstretch from a Tigray re-escalation could degrade force quality without formally breaching the commitment. Contractor duty-of-care thresholds (Lycopodium, BCM) remain the more likely near-term mechanism of any schedule disruption than a direct security incident at site.
On financing, AFC/TDB debt drawdowns are the relevant liquidity gate for Lycopodium's capital procurement pipeline. BCM operates under a schedule-of-rates structure — paid per tonne moved — and self-funds mobilisation against the contractual payment stream, so its deployment pace is driven by resettlement clearing the licence area rather than drawdown timing.
Where they should be at year-end (Dec 2026)
By month ~10 of a 24-month build from February 2026 groundbreaking:
Resettlement complete — 350 houses handed over, licence area cleared and available to BCM
Bulk earthworks well advanced — BCM fully deployed, pit pre-strip underway, waste dumps established, haul roads cut
Grid connection energised — 47km line and both substations commissioned, construction power available to site
Access roads complete — heavy haulage routing fully operational
Process plant civil works underway — mill and CIL circuit foundations poured, structural steel erection beginning
SAG mill on site — given ~9-12 month lead times from ordering, arrival and installation commencement expected Q4
Site infrastructure complete — permanent camp, workshops, reagent storage operational
Key gating items by year-end:
Resettlement pace remains the primary constraint on BCM's pre-strip start. AFC/TDB drawdown initiation (expected mid-2026) gates Lycopodium's broader procurement pipeline beyond the SAG mill already ordered. These are separate constraints on separate critical paths. Oromia security — and specifically contractor duty-of-care responses to any deterioration — is the exogenous risk capable of disrupting both simultaneously.