RE: GBP ยฃ to USD13 Jan 2025 17:05
Oiltdr,
I guess we are looking at Anchois-2 development being all good to go.
FEED was started with the Subsea Alliance on the 20 Jun 2022 07:00. RNS Number : 3859P
And
FEED completed 8 Mar 2023 07:00. RNS Number : 2161S
If we read all below from the RNS we had a full project confirmed on the 8th of March, which is part of the continually reported fast track development. It was only derailedwhen CHAR announced the terms of the Energean farm in where the demanded to confirm Anchois-3 was commercial.
Anchois-3 is NOT part of this FEED anaysis SO it is assumed that procurement has been advanced during the Energean farm in irrespective as it has been detailed by Adonis in this RNS
RNS 2161S states (cross check for full detail):
Three initial subsea producer wells, including the Anchois-2 well drilled by Chariot in 2022, with multi zone completions to enable gas recovery across multiple stacked sands;
o Subsea infrastructure ("SURF" and "SPS") capable of delivering produced hydrocarbons from the wells to the onshore facilities via a subsea flowline and controlling the wells via an umbilical, with future expansion capabilities to tie-back additional wells;
o Onshore central processing facility ("CPF") to process the hydrocarbons and to deliver treated gas and condensate to market, with an initial capacity of 105 mmscfd; and
o Onshore gas pipeline to deliver the gas to the anchor gas offtakers via the Maghreb Europe Gas Pipeline ("GME"), for which a tie-in agreement has already been signed.
ยท Engineering, Procurement and Construction ("EPC") commercial proposals have now been requested.
ยท In addition to the FEED, other technical work has been progressing in parallel, in the lead up to development sanction, including:
o Environmental, Social Impact Assessment ("ESIA"), for which onshore and offshore environmental baseline surveys ("EBS") have already been conducted;
o Field Development Plan ("FDP") is being finalised by the Lixus joint venture partnership to enable the award of the production concession;
o Development drilling planning is ongoing which can further evaluate the potential of an additional 754 Bcf of 2U prospective gas resources for minimal additional cost. The targets identified have an independently assessed geological chance of success ("Pg") ranging from 49-61%.
Adonis Pouroulis, Chief Executive Officer, commented:
"We have made excellent progress across all aspects of our planned development for Anchois and detailed discussions on partnering, gas sales agreements and project finance continue concurrently as we move towards Final Investment Decision.
"The conclusion of the FEED stage, largely performed by the Subsea Integration Alliance ('SIA'), is an important step in defining the initial development plan to deliver gas to our anchor customers. In conjunction with the Field Development Plan and Environmental and Social Impact Assessment work completed to date, we have further cemented the viabilit