Rig hunting20 Dec 2018 21:24
I thought that this might be the drilling rig : Sakson SK604, 2,600HP.
It was planned to spend approx. 4 months to drill 4,500m + complete + test a first well = July to end October 2018.
Then if that was successful to-
Then spend approx. 5 months to drill 5,000m + complete + test a second well = November to end March 2019.
The rig could then travel by ship from Pate field, Faza Island, Lamu, Kenya down to a Tanzanian port in a couple of weeks (arrive mid April 2019).
But as of 26-11-2018 they were only at 3,800m (which is 100m more than they were at on 18-10-2018) for the first well.
If the first well is a failure then the rig could be in Tanzania mid February 2019.
If the first well is a success (looking likely) then the rig could be in Tanzania by either mid July 2019 (or up to mid October 2019 if they have the same problems with the second well).
Zarara Oil & Gas (Midway Resources International)
Pate 1 well - historic high pressure gas blow out, plug + abandoned.
Pate 2 well - exploration vertical 4,500m sandstone targets, gas find at 300m, drilling in progress.
Pate 3 well - exploration deviated 5,000m sandstone targets. Not started yet.
https://www.londonstockexchange.com/exchange/news/market-news/market-news-detail/other/13674325.html
11-06-2018
".....Zarara has contracted the Sakson Rig SK604, a 2,600HP rig owned by Sakson Drilling and Oil Services DMCC ..."
https://www.the-star.co.ke/news/2018/10/18/gas-drilling-in-lamu-to-be-done-by-october_c1835514
18-10-2018
https://www.youtube.com/watch?v=fW3foqo8DfQ
26-11-2018