RE: When GGP gets cash from Havieron27 Oct 2021 00:15
@Zoros - thanks for your excellent post. I agree (as I said earlier in this thread) that there's scope for more than the 2Mtpa throughput that NCM have based the PFS on. This could have a major impact on the key project economics - NPV, IRR, FCF, PBP etc.
I am less optimistic about the compression of the declared timeframe such that gold production is underway in 2023. Despite the presentation deck comment, GGP's own RNS says first ore in 1H FY2024 and first production of Gold/Copper in 2H FY2024. I think it is too punchy at this point to bring production forward a whole year from what the JV partners are saying.
So, to your three beliefs:
(a) No - I don't think that GGP will see revenue during 2023 from gold mined at Hav
(b) Yes - it's entirely possible that throughput will be at 3Mtpa r/r by the end of 2024
(c) Yes - I think they will want 100% too