RE: The money Shot6 Aug 2020 12:46
Mixster, David Bramhill said two to three weeks before the geotechnical rig arrives. Those works, he said, will take two, two and a half weeks. The drilling rig can then arrive, and the drill will take around 7 weeks. He said that following drilling, the EWT of B-1 will be able to start after about 4 weeks, and it should take around 4 to 8 weeks. If they move straight on to EWT WNA-2, that's another 4 to 8 weeks. I make that a minimum of 23 weeks, which takes us to the middle of January. Of course hopefully we should get an idea of what they've found at WNB-1 around the end of October, and an idea of what flows hopefully mid December.
I assume they'll then put a revised CPR together if they intend to sell, or consider exploration of Ellerby and Spring Hill so they can put together an FDP.
Do you agree with these timings Mixster?