RE: production c373 Sep 2019 12:48
kelsbells - from the 23 november 2018 update....
As announced on November 2, 2018, the Company's A-80 truck-mounted workover rig has run in hole with a scraper to cleanout the production casing shoe at a depth of 3,904 metres. During the operation an obstruction was encountered at a depth of 1,830 metres. As a result, the Company pulled the scraper out of hole and performed running in hole of 2-7/8" tubing with mule shoe which successfully cleared the obstruction and cleaned out the wellbore to a depth of 3,904 metres.
The Company's field team is currently running in hole with a tri-cone drill bit which has successfully cleared the previously detected obstruction at a depth of 1,830 metres and expects to reach the target depth of 3,904 metres (production cashing shoe) during the course of this morning.
Following completion of the aforementioned activity, the Company will pull the tri-cone drill-bit out of hole and subsequently re-run a scraper in hole to perform a final cleanout of the casing to a depth of 3,904 metres.
The Company will begin wireline logging as soon as the scraper has been pulled out of hole following successful cleaning out of the casing to a depth of 3,904 metres. Construction of the drilling pad is expected to commence immediately after the conclusion of wireline logging.
The wellbore will be considered ready for well deepening operations once these activities have successfully been concluded.