RNS: Power Plant commissioned29 Jan 2014 12:13
Greenko, the Indian developer, owner and operator of clean energy projects, is pleased to announce that Phase-2 (50.0 MW) of its Balavenkatpuram wind farm has been commissioned. This takes Greenko's total generating portfolio to 476 MW, a 54% increase since April 2013.
The grid connection for the site's full capacity of 200 MW was completed in October 2013, ahead of Phase-1's commissioning. Balavenkatpuram Phase-3 (50.0 MW) is already under construction and on track for commissioning ahead of the main generating season, which begins with the monsoon in July.