RE: Goa18 Mar 2026 13:59
The work order is placed on M/s DigiSmart Networks Pvt Ltd. (AMISP), Jaipur, Rajasthan for an amount of Rs.890,11,97,693/- for installation of 7,50,356nos. of Smart Meters. The payment to AMISP will be carried out over a period of 93 months on a per meter per month basis.
M/s DigiSmart Network Pvt Ltd has appointed M/s Schneider Electric India Pvt. Ltd., Mysore, Karnataka and M/s Esyasoft Landis & Gyr Ltd, Kolkata, West Bengal for supply of smart meters.
Response to questions. Figures are slightly different to Annex B
The target fixed for the installation of Smart Meters is 7,50,356 nos. to be completed by August 2027 in phase manner,1) Substation Feeders – 827 Nos.2) DT Meters – 8,369 Nos.3) Government premises - 12,392 Nos.4) Industrial Consumers – 6224 Nos.(b)the technical features and specifications of the smart meters being installed, including whether they support prepaid and post-paid modes, remote disconnection/reconnection, time-of-day metering, load monitoring and communication to consumers;data (c) whether the smart meters support or enable dynamic or time-of-day pricing, and if so, whether such pricing has already been implemented for industrial or commercial consumers in the State;5) Commercial / Domestic Consumer -7,22,544 Nos.