Expect to Double Production Capacity25 Oct 2019 11:31
From the July 11th RNS:
'Current proposed planning, subject to the award of an exploitation license, is to double current production capacity from 6,500tpm to 13,000tpm of saleable ore through a plant upgrade which will include a downstream screening circuit to produce these size fractions. The plant as currently configured is capable of producing some 75,000 tons per annum, which would result in a substantial profit for Keras. However, on receipt of the exploitation licence Keras expects to expand and improve the plant to add more value as well as increasing production. The Company intends this to be financed in conjunction with an offtake agreement rather than equity funding.'