RE: days till production20 Mar 2019 09:31
Sorry, bobster, but, it’s not 700 days until production I’m afraid. It may be 700 days until ‘first polyhalite’, however, there is a material - and key - difference in that. ‘First polyhalite’ is achieved by intersecting the Fordon polyhalite seam as we drill the mineshaft, whilst first ‘production’ will be achieved sometime later - once the shafts are completed, the mine is fitted out completely and the MTS is up and running. This will then enable us to attack the seam directly and, as such, make us a producer.
Sorry if you think I’m being picky, however, the difference is significant. And no doubt why the company carefully sticks to using the term ‘first polyhalite’.
Regards,
per ardua ad astra