RE: My first target 1p.Hugely Under value16 Jun 2020 11:46
Brighteyes,
Research?
2 years waiting for SCC permission?
The planning application for HH-1 ewt and drilling and testing of HH-1z and HH-2z was submitted in November 2016. Further documents were added up until August 2017 presumably addressing planners recommendations for further information, and planning permission granted in December 2017.
The planning application for the HH development was submitted in December 2018, documents added until July 2018 and permission granted in September 2019.
UKOG has never offered the excuse of OGA limits - which not only would be based on what UKOG requested but have also been increased as required - as a reason for any published flow rates.
Yes, the well could only flow one level at a time, but only 2 levels have been tested for any length of time during the 18 months of testing. In October 2018 a few months into testing the Portland was declared commercial and an initial flow rate for the Portland horizontal predicted of 720 to 1080bopd, and an initial stable 362bopd for the vertical Portland, yet they are still messing around with the HH-1 Portland completion during production and no news about HH-2z apart from initial rates 3 months ago during initial clean up following the intervention to block the water ingress. There has been no recent statement re stable rates from HH-1 (targeted or actual) or test rates from HH-2z although there are opinions it's shut in for furhter intervention work, although the only intervention mentioned was to fine tune and optimise in the 9 March RNS - surely not a reason to stop testing.
The recent placing raised cash at 0.2p per share, this was mainly for paying off the CLN, an intervention in HH-1 not previously mentioned of re-reperforation, a bigger pump already installed and other changes to the Portland completion (the expected intervention was dual completion with ESP) to materially increase production - though it would have been better if they had stated an increase from x bopd to y bopd - or even just what the increased rate was expected to be. It was also for future work on Loxley and IOW. £275,000 was possibly for the second hand site equipment initial payment, although the previous placing was also for that purpose, the remainder (£275,000) to be paid in shares. The balance of the £1.65mm agreed for the site equipment (which was only costing $4 a barrel OPEX anyway) would be paid by shares and / or cash.
If you want to understand why a lot of lth are cynical about UKOG plans and RNS read the January 2019 2020 strategy and drilling plans. Remembering this was late January how's this for a fail:-
'.......by the drilling and production testing of two horizontal wells, HH-1z and HH-2, both planned to start in spring 2019.'