RE: Started Drilling4 May 2021 22:56
re timings john so you won't think I was just deramping .
28th Jan last year SDX RNS'd they'd moved their rig already to the BMK-1 location to drill 1,551 meters.
They RNS'd they'd finished and were moving the rig again on 4th march which gave them 5 weeks or 35 days for 1551 meters.
They're now planning 3 drills and associated rig movements, one of 1,160m another of 1,720m and a third which is a dual target well, testing the Guebbas reservoir at 1,600m and the the Hoot reservoir at around 1,790m.
First well spud 30th April should be around 28 days being 20% shallower then the next 2 close to 38,39 days each being 1700m+ each and one needing 2 zones tested? Thats 15 weeks without delays which is what 14th,15th Aug?
I know they've said they'll be quicker and maybe they will just think that if there's delays it may be that prd's drill gets pushed to the back of the line rather than their own.
If I'm wrong on the calcs show me and I'll happily apologise by the way.